Questions_from_Site_Visit.docx

DOCX document 15 KB Posted

Attached to
Provide electrical and HVAC upgrade to Buildings 1 and 20, USMARC, Clay Center, NE
Solicitation number
AG-32SD-S-17-0003
Issued by

About this file

Q&A and Additional requirements, from Site Visit 2-7-17

View the file

Other files

File Type Posted
Further_questions_from_site_visit.docx DOCX document
SF1442,_2-24-17.pdf PDF
SF1442_rev_2-13-17.pdf PDF
site_visit_attendees.pdf PDF
SF1442,_revised_1-31-17.pdf PDF
clz-prv,_1-31-17.doc DOC document
clz-prv,_1-19-17.doc DOC document
PkgA2_100CD_Bldg20_Elec_Specs,_rev_coversht.pdf PDF
1442,_dated_1-24-17.pdf PDF
GenDec,_S-17-0003,_1-6-17.docx DOCX document
Bldg_20,_HVAC,_PkgA1_100CD_Dwgs_Stamped.pdf PDF
PkgA1_100CD_Bldg20_HVAC_Specs,_rev_coversheet.pdf PDF
Package_A_Pictures.docx DOCX document
PkgA_100CD_Bldg1_Specs.pdf PDF
Bldg_20,_Elec,_PkgA2_100CD_Dwgs_Stamped.pdf PDF
Bldg_1,_Elec,_PkgA_100CD_Dwgs_Stamped.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A and Additional Requirements - Site Visit 2/6/17 Bldg. #20 Mechanical/Electrical, Bldg. #1 Electrical

Q&A:

1. Are faxed and email bids acceptable? Emailed, scanned proposals are OK. Faxed are too unwieldy. I have no local fax number (Louise L. Snitz)

2. Due to the time to get pricing, could the bid due date be moved to March 16, 2017? New proposal due date is March 6. Also note: provide further questions no later than February 27. (Louise L. Snitz)

3. What is meant by an EPA air quality permit and what is it needed for? Answer to be provided in next amendment.

4. Print B20-MH-201 key note #2 refers to floor mounted pumps and print B20-M-501 inline pump detail #5 shows the pumps hanging. Floor mounted is correct.

5. Air separator VJR 200 maximum pipe size is 2" the pipe size where the separator is shown is 2 1/2" VSR 2-12 has a size for 2 1/2" pipe. VSR 2-12 is correct since correct Pipe Size is 2 ½”.

6. RTU-2 I don't see any return drop from the unit. RTU-2 is 100% OA since those lab rooms are 100% exhausted through the hoods.

7. What is to be used for the fume hood duct material? Spec Section 23-31-13 details fume hood duct material.

8. With regard to controls, the specifications lists Siemens in base, but that 3 others are acceptable. Does bidder need to provide at least 2 different pricings (manufacturers) for this item? No.

9. What are the cleaning requirements after finishing each area? Is it required to have a cleaning service clean for each lab or office space? Refer to Spec Section 017700 – Closeout Procedures, Part 3 Execution, 3.1 Final Cleaning, and other specs sections as necessary.

10. What are the bathroom requirements? Owner cannot allow multiple contract personnel in owner's facilities. Is contractor to provide their own facilities? Contractor to provide restroom facilities.

11. The specification calls for stainless steel vent for the boiler in building #20. If polypropylene is acceptable to the boiler manufacturer, is it acceptable for the project? Specifications are to be followed.

12. Owner cannot be without ultra cold freezers and walk-in coolers and freezers for more than 8 hours. Do documents indicate that contractor shall provide generator(s)? Yes. Package A Dwgs, Sheet B1-E-401, Keyed Note # 13. This keyed note is hereby included for all ultra cold freezers and walk-in coolers and freezers for Dwg Package A1 and Package A2.

Additional Requirements:

1. Electrical power to Bldg. #1 may be off from noon on Friday to noon on Monday to accomplish the main power equipment replacement work.

2. The Pac Bio room in Bldg. #20 may be off for a maximum of 3 days straight to accomplish work in this area.

3. Bldg. #20 will be vacated for 3 weeks in order for the mechanical and electrical work to be accomplished. During this time, work shall be accomplished such that there will be no other interruptions to the lab and office work in this building.

4. No substitutions will be approved prior to bidding. It is incumbent on the contractor to bid according to the specs and drawings.