- Covered Walkways for Beltsville, MD Federal contract opportunity
- Solicitation number
- AG-32KW-S-12-0248
About this file
Information for prospective bidders.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-32KW-S-12-0248.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-32KW-S-12-0248
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
APHIS-ASD-SCB-32KW
RIVERDALE MD 20737
Unit 45
4700 RIVER ROAD
USDA-APHIS-ASD-SCB
NONE08/21/2012000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/02/2012
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Tax ID Number: Not Available
DUNS Number: Not Available
The purpose of this amendment is to provide information from the Site Visit.
1. The closing date remains 8/24/2012 at 5:00 pm EST.
2. A listing of questions is provided to prospective vendors, at attachment 1.
3. Attachment 2 is sample pictures.
4. Attachment 3 is the list of propestive bidders.
5. All terms and conditions remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
HERBERT L. SUBER
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Site Visit Questions
1. What are the normal business hours?
6:30am ‐4:00pm. Approval from the Facility Manager is required to work until 6:00 pm each day. All employees must sign‐ in and sign‐out each day at the front desk in the main lobby.
2. Where is the staging area?
Staging area will be outside the modular office building that is adjacent to the Virology
Diagnostic Laboratory (VDL).
3. Are gutters required?
Yes, a gutter system is required to channel rainwater away from the existing buildings and front sidewalk.
4. Will a rain barrel required?
Rainwater barrels should collect runoff.
5. What is the estimated price range for this construction project?
Between $25,000 and $100, 000.
6. Are contractor employees required to be U.S. citizens?
Employees must be U.S. citizens or have appropriate documentation to work in the U.S.
7. What are the preferred specifications for the covered walk way?
Rails, lights and power are not required. Metal posts and beams shall be considered but wood is preferred. Design should prevent the roosting of birds.
8. What type of design is required for this project?
Contractor’s option to provide wood or metal design. Samples are attached to provide ideas but choice still remains contractors.
9. Are field investigations and site surveys required?
Contractor is responsible for locating all underground utilities. Government personnel will be on‐site.
10. Are drawings available for the existing modular office building?
No.
11. Who is the builder of the modular office building?
Modular Genius, 1201 South Mountain Road, Joppa, MD 21085 Phone: 888‐420‐1113
12. Can contractors build on the grass?
The grassy areas will remain. Limited work might be required in grassy areas for the location of support covered walkway posts.
13. How are proposals to be submitted in terms of format?
Written or emailed proposals are expectable and must be submitted by Friday, August 24, 2012
5:00 pm EST. Proposals must include copies of payment and bid bonds.
14. Are wage determinations required?
Yes, according to all government regulations regarding construction.
15. Are state and local permits required?
Yes, must comply with all applicable state, local and county regulations concerning permitting.
16. Is 8(a) certification required?
Yes.
SITE VISIT- BELTSVILLE, MD COVERED WALKWAY
15 Aug2012
NAME
I. !4rh7 {,J~/klk
2. l3o6 @4HL~c}J
3.Jbj.So~ I ~ve~14:.
4. /110 t-~vt.); s
s. 1(1 Lt:.f c~ ~.-~
SIGN-IN
ORGANIZATION
~~toll eH{' l),T, Q,::i)o $1p~LG
10. c MIS ~r-\ ("l.MAN ~ w Cu\rr{ZA(:"Glt.-~
11. 1lA Lf'l.\ a ,28AJ~ c J w C<»re.A c.x:u es
PHONE
4f1~6Cf s-: $6z o
41(/- .5b l -fbi fa
3o l ~ Z..l e - L./7 >o
. ' ' I
;t))- 3~5-/7«/D
3ot· 3<f;-t7'/o s 0 l - 2.7. 0 - 6'2(.06
.sDI-5J(-!7o0
14. 7/H )g;ltrte At?JU/f!IJ tL
15. fud Jqfbnc:q ~£Lc
16. L.f..eJf"'~ CfJ-~~11 U50/J -IIPfffS
1s. Mrr TJMfA.tVu
19. .51>\W G JL,/vtOtte
2o.JE.ff,Jv'l:y G~LtJ r
21. ~IV GA€.4-AA.)t-o
22. _____ _
23. _____ _
24. _____ _
25. _____ _
J)
??3 51[ J-1 j(JJ
33tJ -[o 1--3 to9 Ce
| AG-32KW-S-12-0248-0001 |
| Binder1.pdf |
| Questions proposed at Site Visit A |
| Sample 1 |
| Sample 2 |
| Sample 3 |