NRCS
Golden Meadow PMC Drainage and Irrigation improvement site showing.
August 3, 2016
9:00 AM
• Introduction of NRCS employees
Scott Crist, Brandon Sampson, Doug Baker, Christopher Toups, Garret Thomassie.
• All parties are asked to sign in
• Overview of the specifications
-bid schedule -variation in quantities -inspection and acceptance -time of performance -time extension clause -construction schedule -falling behind the construction schedule -termination for falling behind -weather days -adverse weather and time -Average work day 10 hours—six days a week.
• Contractor asked question: Does there need to be a designated QC man on site or can a foreman act as both?
9:15 AM
• Scott covers
- Section G
- Safety on site
- Inspector or Co can stop work for safety violations
- I.P.P. invoice payment process.
- SAM.GOV account
- Documentation and submitting an invoice
- Davis Bacon wage act
- Bilingual signage
9:20 AM
• Brandon covers NRCS 1920 1926 NRCS requirements -Sect. 1.1 proposed safety plan
- 1.2 preconstruction safety meeting
- 1.3 joint safety meeting
- 1.4 safety man on site. Weekly tool box safety meetings
- 1.7 foreman to be first aid certified
- 2.3 medical stretchers and blankets
- 3.2 crane workers need physicals
- 4.1 jobsite hard hat area—all
- 4.2 hard hat signage and dimensions of sign
- 5.1 safety belt
- 5.2 tag out lock out
- 5.36 riding on equipment
- 5.41 crane certification
- Bathroom facilities for workers
- Archeological finds
- Certification and test data for materials
• Contractor questions: Do all employees need physicals or the operators?
9:30 am
• Brandon covers
- LA one call
- Access of roads
- Benchmark plan set
- Site damage
• Scott covers
- Contractor clauses
- Performance and pay bonds
- Differing site conditions
• Brandon covers
- Layout of site
- Shop drawing approval
• Contractor requests data files of survey data.
9:40 AM
• Scott covers
- Buy America act
- Due date and time for bids
- Bid guarantee
- Preconstruction conference
- Reimbursement of bonds
- Bid instructions
- Email of what contractors need to submit and when.
9:50 AM
• Doug covers
- Plans and four components of work
- NRCS specifications
- Pollution control
- Vegetative planting
- Seeding and mulching
- Construction surveys
- Mobilization and demobilization
- Water removal
10:25 AM
• Scott covers
- Surety bond
- Letter of material suppliers
- List of future work
- Letter of qualified employees and personnel
• Contractor questions: When is the notice to proceed going to be issued? Is there liquidated damages?
10:45 AM
• Visit the construction site
- Structure 4
- Structure 1
- Drainage canal
- Levee repair site
- Temporary storage site for spoil
- Pump station site
- Brandon speaks of the bringing in of power from Entergy.
Work order required. 10 day waiting period.
11:05 AM
• Conclusion of site visit