Attch_2_RussellPondRd_PlanClarification.docx

DOCX document 21 KB Posted

Attached to
Russell Pond Road reconstruction Federal contract opportunity
Solicitation number
AG-1484-S-16-0006
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Attch 2 RussellPondRd_PlanClarification

View the file

Other files for this federal contract opportunity

Other files attached to Russell Pond Road reconstruction, newest first.
File Type Posted
RussellPondRd_QandA_051316.docx DOCX document
AG-1484-S-16-0006-000001_Complete.pdf PDF
Bid_Schedule_RussellPondRd_SectB.docx DOCX document
Attch_4_RussellPondRd_Permits.pdf PDF
Attch_3_RussellPondRd_SupplementalSpecs.docx DOCX document
AG-1484-S-16-0006_Solicitation_041516.pdf PDF
Attch_1_RusselPondRd_DesignPlans.pdf PDF
Attch_5_DBWD_NH160029_010816_NH29_Highway_Grafton_Co.docx DOCX document
Attch_6_GovtProvidedTechnicalProposalForms.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Russell Pond Road Reconstruction Pemigewasset Ranger District White Mountain National Forest Thornton/Woodstock, New Hampshire

Plan Clarifications A. Design Plan Notes:

1. All Sheets: Scales may not be as indicated on the drawings.

2. Sheets 5&6: Item #33218 Crushed Stone/Stone Bedding is to conform to gradation for ADS pipe bedding/backfill requirements for Class I (structural) fill. Gradation can be found on Table 5-2 “Classes of Embedment and Backfill Materials” of the ADS, Inc. Drainage Handbook. A link to the current (Accessed December 2015.) version is below. Material shall conform to AASHTO M43 size #67 stone.

http://www.ads-pipe.com/pdf/en/ADH5-Installation_December_2015.pdf

3. Sheet 6: Items # 60203 Corrugated Metal Pipe Arches shall be 16 gauge (minimum structural thickness of 0.064”) or thicker.

4. Sheet 6: Ditch Block typical section Aggregate Base should read Item #30103.

5. Sheet 40: On the Plan View, the leader near Sta. 93+50 pointing at rock hatching should read “Construct stone lined ditch. See Detail Sheet 6 of 69.”

6. Sheet 43: Both roadway typical sections: Item #30319 Roadbed Reconditioning should read Compaction Method B.

7. Sheet 43: Both roadway typical sections: Recondition Existing Ditch leaders should read Item #30304.

8. Sheet 43: Add a note on the typical sections that Item # 30805 Bedding and Backfill Aggregate material shall be used where necessary to bring up vertical profile of roadbed.