RFP No. AG-05M6-S-15-0041

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

11. The contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

AG-05M6-S-15-0041 X 05/28/2015 1 190

05M6

USDA Forest Service ATTN: Brian A. Johnson 2930 Wetmore Ave., Suite 3A Everett, WA 98201-4067

Same as Block 7.

Brian A. Johnson, CO (425) 783-6056, bajohnson03@fs.fed.us

Denny Creek Trailhead (Phase 1) Snoqualmie Ranger District

Mt. Baker-Snoqualmie National Forest Washington State (King County)

10 45 X X

X Fourteen (14)

1 3:30 PM

7/17/2015

X

Sixty (60)

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 1 of 190 bajohnson03 Highlight bajohnson03 Highlight

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 4-85) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

20b. SIGNATURE 20c. OFFER DATE

DUNS No.: __________________

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 2 of 190

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND

Denny Creek Trailhead (Phase 1) Snoqualmie Ranger District

Mt. Baker-Snoqualmie National Forest Washington State (King County)

B.1 SCHEDULE OF ITEMS (Page 1 of 2)

ITEM

NO. DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101 Mobilization Lump Sum 1 $ $

15201 Construction survey and staking, method 2, tolerance D

Lump Sum 1 $ $

15713 Soil erosion & pollution control Lump Sum 1 $ $

20101 Clearing and grubbing Acre* 0.74 $ $

20301 Removal of 6’ or greater boulders Each 4 $ $

20304 Removal of asphalt pavement (approx. 85 tons) Lump Sum 1 $ $

20407 Select borrow (embankment & trail ramp) Ton 400 $ $

20490 Excavation and embankment, compaction method B, finishing method A

Cubic Yard* 1100 $ $

20701 Earthwork geotextile type 1A or 1B (subsurface drainage)

Square Yard* 3000 $ $

32451 Aggregate base, 1‐1/4” WSDOTB compaction method B (Dense Graded base )

Ton 500 $ $

32453A Aggregate base, AASHTO size #1, compaction method A (Erosion Protection Rock )

Ton 200 $ $

32453B Aggregate base, WSDOT Permeable Ballast or AASHTO size #3, compaction method B

Ton 2150 $ $

32453C Aggregate base, AASHTO size #6 or 67, or approved equal, compaction method B (Choker Course)

Ton 150 $ $

32453D Aggregate base, 5/8” minus crushed limestone, compaction method A (ramp & trail surfacing)

Ton 15 $ $

40311A State of WA asphalt concrete pavement, Class ‘B’ (Dense Graded)

Ton 150 $ $

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 3 of 190

B.1 SCHEDULE OF ITEMS (Page 2 of 2)

ITEM

NO.

DESCRIPTION PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

40311B

State of WA asphalt concrete pavement, Class ‘Porous HMA Cl. ½” PG‐28ER’

Ton

60272A

24” polyethylene pipe with smooth interior and annular exterior, compaction method B

Foot

60272B

36” polyethylene pipe with smooth interior and

60501

Underdrain system

60909

Wheel stop

Each

62201A Equipment rental – Excavator mini/trail excavator, 60” maximum tread width

Hour 40 $ $

62201B Equipment rental – Excavator medium size with thumb

Hour 40 $ $

62201C Equipment rental – dump truck min. 10 CY capacity

Hour 40 $ $

62503 Seeding and mulching, dry method – Seed Mix C1 Lump Sum 1 $ $

63301 Sign system Each 16 $ $

63406 Pavement markings, Type H & Type J Lump Sum 1 $ $

90201A Two panel kiosk Each 1 $ $

*Indicates contract quantity

TOTAL PRICE ALL BASE ITEMS: ‐‐‐‐>$

OPTION ITEM 1

60272C

36” polyethylene pipe with smooth interior and

TOTAL PRICE ALL ITEMS: ‐ ‐‐‐>$

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 4 of 190

B.2 PAYMENT FOR BOND PREMIUMS

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 15101 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 5 of 190

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

This project involves the construction of a new trailhead parking area and includes but is not limited to: construction surveying/staking, clearing, excavation, embankment, culverts, dense graded and permeable/porous aggregate base and asphalt surface courses, pavement markings, wheelstops, signs, trail construction, and a two-panel kiosk. The Contractor shall furnish all labor, materials, equipment, tools, transportation of supplies, and perform all work required according to the drawings and specifications of the contract.

C.2 PROJECT LOCATION

The project is located in King County, Washington. T22N, R11E, Sec. 8. From Exit 47 on I-90, go to the north side of the freeway, turn right at the ‘T’ intersection, go about 500’ and turn left on to Road #58 just after the underpass. Then take FS Road #58 for 2.5 miles east and north to the project site.

C.3 DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECT

Between $250,000 and $500,000.

C.4 WORK RESTRICTIONS

There shall be no construction activity from noon on Friday through Sunday, or on holidays during the campground operating season (mid-May through mid-September).

C.5 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS (FP-03)

These specifications are included by reference only. The requirements contained in these Standard Specifications are hereby made a part of this solicitation and any resultant contract.

They are available online at http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm

C.6 APPLICABLE SPECIFICATIONS (ROAD PROJECTS)

Standard and Supplemental Specifications for FP-03 shown in the specification listing contained in the attachments are applicable to this contract. All specifications not included in the specification listing but referenced by listed specifications, are applicable. The Supplemental Specifications shown on the specification list are physically attached.

C.7 AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 6 of 190 http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm

C.8 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS

(FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C.9 MATERIAL CERTIFICATIONS, INVOICES, TESTING REPORTS & OTHER

SUBMITTALS

Submit the following certificates, test reports, samples and test data for this project (3 sets each except only 2 samples unless noted). See FP-03 sections 104, and 106 for timely submittal and approval by the Contracting Officer. Materials associated with the following Pay Items will require certifications and/or testing reports submitted to the Contracting Officer Representative prior to implementation on the project:

ITEM DESCRIPTION

TIME FOR

GOVERNMENT

APPROVAL

15101 Traffic Control Plan 2 days

15713 Soil Erosion and Pollution Control Plan 2 days

20407 Select Borrow 7 days

20701 Earthwork Geotextile Type 1A or 1B 7 days

32451 Aggregate Base, 1-1/4” WSDOT (Dense Graded Base) 7 days

32453A Aggregate Base, AASHTO Size #1 (Erosion Protection Rock) 7 days

32453B Aggregate Base, WSDOT Permeable Ballast or AASHTO Size #3 7 days

32453C Aggregate Base, AASHTO Size #6 or 67, or Approve Equal (Choker Course) 7 days

32453D Aggregate Base, 5/8” Minus Crushed Limestone (Ramp & Trail Surfacing) 7 days

60272A-C 24” & 36” Polyethylene Pipe with Smooth Interior and Annular Exterior 7 days

60909 Concrete Wheelstops 7 days

62503(1) Seed Mix C1, Weed free mulch 7 days

63301 Sign Systems 7 days

63406 Pavement Markings, Type H & Type J 7 days

90201 Two Panel Kiosk 7 days

(1) A list of certified growers of mulch in the state of Washington can be found by following this link:

http://agr.wa.gov/PlantsInsects/WWHAM/WWHAM.aspx

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 7 of 190 http://agr.wa.gov/PlantsInsects/WWHAM/WWHAM.aspx

C.10 BIOBASED PRODUCTS

The Contractor must comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Executive Order (EO) 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” and the Federal Acquisition Regulation to provide biobased products.

The Contractor shall utilize products and material made from biobased materials (e.g., insulating foam, composite panels, and concrete and asphalt release fluids) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).

The following is an example list of products that may be used in this contract for minor construction for which biobased products are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

Concrete and asphalt release fluids Fluid-filled transformers Wood and concrete sealers Composite panels Adhesive and mastic removers Hydraulic fluid Water tank coatings

Biobased products that are designated for preferred procurement under USDA’s BioPreferred program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material

In addition to the biobased products designated by the U.S. Department of Agriculture in the BioPreferred Program, the Contractor is encouraged to use other commercially available biobased products.

The awarded Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes.

The Contractor shall comply with the provision at FAR 52.223-1, Biobased Product Certification.

The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 8 of 190 http://www.biopreferred.gov/

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 9 of 190

SECTION E--INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-1 Contractor Inspection Requirements (APR 1984) 52.246-12 Inspection of Construction (AUG 1996)

E.2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at* the project site.

E.3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT

The government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the contractor by the Forest Service specifications or by the Special Project Specifications.

E.4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground.

"Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 10 of 190 http://www.arnet.gov/far/

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/?q=browsefar www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984)

F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than forty-five (45) calendar days. The time stated for completion shall include final cleanup of the premises.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 11 of 190 https://www.acquisition.gov/?q=browsefar

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at the Snoqualmie Ranger District, North Bend Office, 902 SE North Bend Way, Bldg. 1, North Bend, WA 98045.

G.2 CONTRACTOR INVOICE CERTIFICATION

When submitting partial payments the contractor shall submit the following certification with each invoice submission. This certification shall be attached in the Invoice Processing Platform (IPP) at www.ipp.gov:

CONTRACTOR CERTIFICATION

(FAR 52.232-5 Payments under Fixed-Price Construction Contracts)

I hereby certify, to the best of my knowledge and belief, that—

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.

(Signature / Printed Name)

(Title)

(Date)

G.3 CONTRACT RELEASE

When submitting the final invoice via IPP, the contractor shall provide a signed and dated Contract Release that includes the following information:

"In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein. Reservations, if any:______________."

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 12 of 190 http://www.ipp.gov/

G.4 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE

The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 13 of 190

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 FAR 52.236-4 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Forest Service Personnel.

(b) Weather conditions: Normal west slopes of Cascade Mountains weather. Elevation of this project is about 2300’.

(c) Transportation facilities: FS Road #58 is a good double lane paved road to the project site.

(d) Other Physical Data: None.

H.2 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,

EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damaged promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

H.3 USE OF PREMISES

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless provided otherwise, the Contractor shall: (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State, and local regulations.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 14 of 190

H.4 AGAR 452.236-73 ARCHAEOLOGICAL OR HISTORIC SITES (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

H.5 AGAR 452.236-74 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION

(NOV 1996)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or near rivers, streams, OR impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H.6 RIGHTS IN AND USE OF MATERIALS

(a) The Contractors, with the written approval of the Contracting Officer, may use on the project suitable stone, gravel, and sand or other material found in the excavation. Payment will be made both for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. The Contractor shall replace without additional compensation sufficient suitable materials to complete the portion of work which was originally contemplated to be constructed with such material.

(b) Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to reimburse the Contractor for the cost of their production.

H.7 STORAGE AND STOCKPILING OF MATERIALS

Material shall be stored to assure the preservation of quantity and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by the Forest Service, shall be restored at Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered land.

H.8 AGAR 452.236-77 EMERGENCY RESPONSE (NOV 1996)

(a) Contractor's Responsibility for Fighting Fire. (1) The Contractor, under the provision of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish, all fires on the work site other than those fires in use as a part of the work. (2) The Contractor may be held

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 15 of 190 liable for all damages and for all costs incurred by the Government for labor subsistence, equipment, supplies, and transportation deemed necessary to suppress a fire set or caused by the Contractor or the Contractor's agent or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergency. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-5.

H.9 LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products onsite, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states.

Servicing of all equipment shall be done only in the area approved by the Contracting Officer.

If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR

112) including certification by a registered professional engineer.

The Contractor will be required to make reasonable attempts to preserve the scenic and natural environment along this construction project.

(c) Trash and Refuse - Contractor shall remove all of its own trash and refuse from the contract area. Material to be removed includes, but is not limited to; used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper, garbage, etc. This material must be removed to a State, County, or Municipality-designated solid waste disposal area.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 16 of 190

H.10 CONTROL OF NOXIOUS WEEDS--CLEANING OF EQUIPMENT

To prevent the introduction and control the spread of seeds of noxious weeds onto and around National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. When the Contractor is working in an area that has been identified as a noxious weed infestation area, the Contractor shall ensure equipment is cleaned of weed seeds prior to moving to another work area on the Forest. The Contractor shall employ whatever cleaning methods necessary to ensure compliance with the terms of this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forest land, unless otherwise agreed in writing.

Notification will include identifying the location of the equipment's most recent operations.

The Contractor shall certify, in writing, compliance with the terms of this clause prior to each start-up of operations. For the purposes of this clause, "equipment" includes all motorized equipment operated off system roads, transport vehicles, and all motorized equipment used in road maintenance. Not included are log trucks, chip vans, pickup trucks, cars, or other vehicles used to daily transport personnel.

H.11 FIRE PROTECTION REQUIREMENTS

The following fire requirements are attached in Section J and are applicable:

Fire Protection and Suppression, R6-FS-6300-52 (5/97)

Additional Fire Precautionary Measures - Tank Truck, R6-FS-6300-53 (5/89)

Additional Fire Precautionary Measures - Communications, R6-FS-6300-54 (5/89)

H.12 FSAR 4G52.222-704 PERSONAL PROTECTIVE EQUIPMENT (FEB 2007)

The Contractor shall train workers in the safe operation and use of equipment that the worker may use before the worker begins using such equipment.

Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities must be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered which may cause injury or impairment in the function of any part of the body. Defective or damaged personal protective equipment must not be used.

The Contractor shall provide chain saw chaps to each employee who operates a chain saw, at no cost to the employee. These chaps must be approved by an Underwriters Laboratory or meet Forest Service specification 6170-47. The chaps must cover the full length of the thigh and must extend to the top of the boot on each leg.

The Contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support. Employees operating chain saws shall wear foot protection that is

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 17 of 190 constructed with cut-resistant material which will protect the employee against contact with a running chain saw.

In any area where the worker is exposed to the potential for flying or falling objects, the Contractor shall provide a hard hat, at no cost to the employee, and the Contractor shall assure that the employee wears the hard hat. The hard hat must meet the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

The Contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

The Contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise for example, chain saw operation.

H.13 NATIONAL BEST MANAGEMENT PRACTICES FOR WATER QUALITY

MANAGEMENT ON NATIONAL FOREST SYSTEM LANDS, VOLUME 1 (2012)

The BMP’s are a part of this Contract for all the related items listed herein. The Contractor shall have a copy of the BMP’s available and on-site at all times. A complete copy of the document can be found online at: http://www.fs.fed.us/biology/resources/pubs/watershed/

H.14 CONTRACTOR’S REPRESENTATION & RESPONSIBILITY

a. In making formal request for substitution the contractor represents it:

1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.

2. Will provide same warranties and bond for substitute as for originally specified product.

3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.

4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.

5. Cost data is complete and includes related costs under the contract, but not:

a) Costs under separate contracts; and

b) Contracting officer costs for redesign or revision of contract documents.

b. The contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.

c. The contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 18 of 190 http://www.fs.fed.us/biology/resources/pubs/watershed/

H.15 POTENTIAL SAFETY HAZARDS

(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.

(b) The following activities have been identified by the Government as potential safety hazards.

1) Temporary excavation/deep trenching/slope stability

2) Tree falling

3) Fall hazard from work heights exceeding six feet

4) Working over water

5) Heavy equipment operation

6) Fire hazards

7) Hydraulic and/or pneumatic and/or other high pressure hazards

8) Mechanical hazards such as pulleys, springs, etc.

9) Crane operation

H.16 SUSPENSIONS FOR OTHER THAN GOVERNMENT’S CONVENIENCE

The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable; or (2) Failure of the contractor to comply with Specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 19 of 190

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

(FAC Number / Effective Date: 2005-82/06-08-2015)

I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of

Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-7 System for Award Management (JUL 2013) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013) 52.204-13 System for Award Management Maintenance (JUL 2013) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (OCT 2014) 52.219-14 Limitations on Subcontracting (NOV 2011) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (MAY 2014)

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 20 of 190 http://www.usda.gov/procurement/policy/agar.html

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2015) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUL 2014) 52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (JUL 2014) 52.222-40 Notification of Employee Rights under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-54 Employment Eligibility Verification (AUG 2013) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2014) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(SEP 2013)

52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991)

52.217-4 Evaluation of Options Exercised at Time of Contract Award (JUN 1988)

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 21 of 190

52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997), Alternate I (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (APR 2015) 52.245-1 Government Property (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2010) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

I.2 AGAR 452.209-71 ASSURANCE REGARDING FELONY CONVICTIONS OR TAX

DELINQUENT STATUS FOR CORPORATE APPLICANTS (FEB 2012) ALTERNATE I

(FEB 2012)

(a) This award is subject to the provisions contained in sections 433 and 434 of the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, as amended and/or subsequently enacted, regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid

Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.

(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434, amended and/or subsequently enacted.

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 22 of 190

I.3 FAR 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award

RFP No. AG-05M6-S-15-0041 Denny Creek Trailhead (Phase I) Page 23 of 190 https://www.acquisition.gov/far/current/html/52_217_221.html%23wp1135887 http://www.sba.gov/content/table-small-business-size-standards

Management (SAM) and its data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the…