POV Campground Road Rehabilitation AG-05G1-S-14-0020 Section 01 02 30, Schedule of Items Page 1 of 1
SECTION 01 02 30
SCHEDULE OF ITEMS
PART 1 GENERAL
1.01 RELATED REQUIREMENTS SPECIFIED IN OTHER SECTIONS
A. Payment Procedures.
B. Change Order Procedures
1.02 SCHEDULE HEADINGS
A. As a basis for computing progress payment values, separately list installed value of each of the following:
1. Each major work item.
2. Each subcontracted work item. For each subcontract, list products and operations of that subcontract as separate line items.
3. Any products to be stored, for which separate payments will be requested with copy of invoice for materials.
B. Include directly proportional amount of Contractor’s overhead and profit in each component listing.
C. Round off values to nearest dollar.
END OF SECTION 01 02 30