AG04T0S160056Solicitation.pdf

PDF 1 MB Posted

Attached to
STEWARDSHIP - DUNES DAY-USE AREA FOREDUNE RESTORATION PROJECT, SIUSLAW NATIONAL FOREST
Solicitation number
AG-04T0-S-16-0056
Issued by

About this file

Complete Solicitation

View the file

Other files

File Type Posted
AG04T0S160056Amendment1.pdf PDF
AG04T0S160056Maps.pdf PDF
AG04T0S160056ReturnPacket.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER AL ITEMS 1. REQUISITION NUMBER PAGE 1 OF 59

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 784342

2. CONTRACT NO. 3. AWARD/EFFECTIVE 4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICIATION ISSUE

DATE

AG-04T0-S-16-0056

DATE

06/15/2016

a. NAME b. TELEPHONE NUMBER(No collect calls)

8. OFFER DUE DATE/

7. FOR SOLICITATION Contracting Office: 541-750-7115 06/28/2016 4 p.m. PST

INFORMATION CALL: FAX: 541-750-7236

9. ISSUED BY CODE 10. THIS ACQUISITON IS

Siuslaw National Forest UNRESTRICTED OR SET ASIDE: 100 % FOR

3200 SW Jefferson Way SMALL BUSINESS EMERGING SMALL BUSINESS

Corvallis, OR 97331

HUBZONE SMALL

NAICS: 115310 BUSINESS

ATTN: CONTRACTING SERVICE-DISABLED VETERAN- 8(A)

SIZE STANDARD: $ 7.5 M OWNED SMALL BUSINESS

11. DELIVERY FOR FOB

DESTINATION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS 13a. THIS CONTRACT IS A RATED

ORDER UNDER DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY

See Block 9 CODE

17a. CONTRACTOR/OFFEROR

18a. PAYMENT WILL BE MADE BY CODE

Siuslaw National Forest 3200 SW Jefferson Way Corvallis, OR 97331

TELEPHONE No.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

OFFER IS CHECKED

SEE ADDENDUM

19. 20. 21. 22. 23. 24.

ITEM N0. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Stewardship – Dunes Day-Use Area Foredune

Restoration Project Oregon Dunes National Recreation Area

US Forest Service

Siuslaw National Forest

See Schedule Of Items

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4, FAR 52.212-3 AND 52.212-5 ARE

ATTACHED. ADDENDA

ARE ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4, FAR 52.212-5 IS ATTACHED.

ADDENDA

ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

29. AWARD OF CONTRACT: REF. your OFFER DATED

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

YOUR OFFER ON SOLICITATION

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING

OFFICER)

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE

SIGNED

31b. NAME OF CONTRACTING OFFICER (Type or print)

31c. DATE

SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (REV.3/2005)

Stewardship - Dunes Day-Use Area Foredune Restoration Project

PREVIOUS EDITION IS NOT USABLE

Prescribed by GSA - FAR (48 CFR)

CONTINUATION SHEET

SCHEDULE OF ITEMS

ITEM

NO.

SUPPLIES/SERVICES

QUANTITY

UNIT

UNIT PRICE

AMOUNT

Mechanical treatment of the foredune to lower its height and reshape it to create more naturally functioning transverse dunes in the Oregon Dunes Day-Use Dunes Restoration project area. Douglas County, Oregon.

TOTAL FOR ITEM #1

Mobilization/Demobilization/Operating Supplies included in hourly rate.

DUNS: _____________________________

EMAIL: ____________________________

HOURS

Contract Ceiling Amount: $______________ (Determined at time of award)

For technical questions, contact Michael Northrop at 541-271-6045 between the hours of 8:00 A.M. and 4:30 P.M. Monday thru Friday.

Pre-Quote Tour: June 21, 2016, 10 a.m. RSVP with Mike Northrop by June 20, 2016, 3p.m. Meeting location: From Hwy 101, go to Siltcoos Beach Access Road, travel approximately a mile, then park in turn-around area near gate of Waxmyrtle Campground.

The estimated start work date is September 15, 2016. All work shall be completed by February 28, 2017.

BASIS OF AWARD: The Government will issue an order as a result of this Request for Quotations to the responsible quoter whose quote conforming to the solicitation will be most advantageous to the Government, cost or price and other factors considered. The Government may issue orders to other than the lowest quote, waive minor informalities or irregularities in quotes received, or elect to not award at all. If necessary, the Government may conduct discussions with any or all quoters. Quoter must respond to the other factors as described under FAR 52.212-2 Evaluation – Commercial Items (Jan 1999). Award will be made on the best value for the Government.

Quoter MUST register online at www.sam.gov. System for Award Management (SAM). See FAR 52.212-4 (t) and Online Representations and Certifications Applications (ORCA) – See FAR clause 52.212-3. Contractors must have an “active” registration at the time of award for the Government to access electronically.

The contract awardee must register at the https://www.ipp.gov/vendors/enrollment-vendors.htm in order to submit invoices for payment. See page 13 for more information.

AG-04T0-S-16-0056

Stewardship - Dunes Day-Use Area Foredune Restoration Project http://www.sam.gov/ https://www.ipp.gov/vendors/enrollment-vendors.htm

Block 27: The full text of a clause or provision may be accessed electronically at www.arnet.gov/far/

CONTRACT CLAUSES

ADDENDUM TO FAR 52.212-4

52-212-1 Instructions to Offerors – Commercial Items (OCT 2015) 52.223-6 Drug-Free Workplace (MAY 2001) 52.211-18 Variation of Estimated Quantity (APR 1984) 52.216-31 Time-and-Materials/Labor-Hour Proposal Requirements – Commercial Items (FEB 2007) 52.242-15 Stop-Work Order (AUG 1989) 52.246-1 Contractor Inspection Requirements (APR 1984) 52.246-6 Inspection – Time-and-Material and Lobor-Hour (MAY 2001) 52.249-6 Termination – Cost-Reimbursement (ALT IV) (MAY 2004)

FAR 52.215-5 FACSIMILE PROPOSALS (OCT 1997)

(a) Definition. "Facsimile proposal," as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.

(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.

(c) The telephone number of receiving facsimile equipment is: 541-750-7236.

(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document--

(1) The Contracting Officer shall notify the offeror immediately and permit the offeror to resubmit the proposal.

(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and

(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timelines, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.

(e) The Government reserves the right to make award solely on the facsimile proposal. However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.

AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at the Headquarters of the Siuslaw National Forest or the Central Coast Ranger District.

http://www.arnet.gov/far/

DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer designates the Contracting Officer's Representative (COR). The Contracting Officer Representative for this project is:

Crystal Mullins Central Coast Ranger District/Oregon Dunes National Recreation Area 541-271-6055 Office 541-999-8219 Cell

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government, which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

FAR 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.

CONTRACTOR'S REPRESENTATIVE

The Government may, at its option, suspend work with full count of contract time continuing, if the Contractor fails to provide a Contractor's Representative (1) conversant in the English language and (2) able to read and understand the contract.

KEY PERSONNEL

Key personnel are those personnel considered essential for successful completion of this contract. All key personnel shall be identified in the Contractor’s Technical Proposal.

The Contractor agrees that assigned key personnel shall not be removed, substituted, or reassigned to another task without the written concurrence of the Contracting Officer. The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed personnel change and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. If the Contracting Officer determines that suitable replacement of key personnel is

AG-04T0-S-16-0056

not feasible or that the reduction of effort would be so substantial as to impair the successful performance of the work, the Contractor may be subject to default action under the affected task order(s) or the contract.

Ultimate approval/disapproval to replace key personnel is the responsibility of the Contracting Officer.

NOTIFICATION OF SUBCONTRACTING

The Contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement.

The notification shall include as a minimum:

1. The name, address, and telephone number of the subcontractor.

2. The date upon which the subcontract was entered into and its duration.

3. A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate.

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Government will issue a notice to proceed on each bid item as soon as the weather and ground conditions are favorable. Contract time will start on the date specified on the notice to proceed if hand delivered, or the third day after the post office has issued a notice of Certified Mail to the Contractor. Failure of the Contractor to pick up certified mail will not be considered an excusable delay.

The Contractor shall be required to (a) commence work under this contract within 3 calendar days after the date the Contractor receives the notice to proceed, (b) execute the work diligently, and (c) complete the entire work as mutually agreed upon times listed below. The time stated for completion shall include final cleanup of the project sites.

A Progress Work Schedule shall be prepared by the Contractor based on priorities provided in the contract unless superseded by the Contracting Officer in advance of work.

The Contractor shall maintain progress at a rate which will ensure completion within the contract time indicated below. The minimum acceptable rate of progress will be calculated by dividing the total units of work for each bid item by contract time specified below, or as established by the approved progress schedule.

If the Contractor's progress falls behind that scheduled, the Contractor shall take such action as necessary to improve progress; in addition the Contracting Officer may require the Contractor to submit a revised schedule and proposed plan of work to ensure completion of the work within the time(s) set forth in the contract.

The Government shall determine the order and time period of the project sites.

The C.O.R. may require the Contractor to finish the portion in progress before additional work is started on any additional portion.

Whenever weather or ground conditions are unsuitable the C.O.R will issue a verbal Stop Work Order and the Contractor shall suspend work and contract time will stop for that project area. When conditions are again favorable, the COR will issue a verbal resume work order. Contract time will resume on the effective work resumption date. In all cases, the Contractor shall resume work within 3 calendar days after the effective work resumption date. It is the Contractor's responsibility to keep the COR currently advised as to where the Contractor or Contractor's Representative may be reached by phone during periods of work suspension. If the Contractor cannot be reached at the phone number provided, or if the Contractor fails to leave a number, a written resume work order will be mailed and contract time will resume on the date specified on the resume

AG-04T0-S-16-0056

work order. The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel and equipment during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site.

PERIOD OF CONTRACT

CONTRACT TIME AND REQUIRED RATE OF PROGRESS

The Contractor will complete each item within the time allowed per item. Due to normal variations in seasonal weather conditions, it is mutually agreed that the starting date may be adjusted for each item with no adjustment in contract time or price.

Contract Time Item No. District Hours Estimated Start Work Date Contract Time

1. Central Coast 154 September 15, 2017 February 28, 2017

CONTRACTOR QUALITY CONTROL PLAN

A. Quality Control Plan

The Contractor shall provide a Quality Control Plan (QCP) as part of this Technical Proposal. The Plan must demonstrate how the Contractor shall assure that quality of performance meets the objectives and requirements of the contract. The QCP shall specify:

- How quality will be monitored to ensure performance standards are met.

- How the work will be supervised.

- How results of the monitoring will result in quality performance.

- Identify the personnel responsible for performing quality control.

Quality control shall include monitoring while work is in progress.

B. Contractor Quality Control Inspection

The Contractor shall assure themselves that performance meets contract specifications, in accordance with FAR 52.212-4, Contract Terms and Conditions -- Commercial Items, paragraph (a), prior to requesting the Government to inspect for payment or acceptance. The Contractor shall contact the Contracting Officer upon completion of a project area. The Contracting Officer may observe the Contractor’s inspection at any time and shall otherwise have unlimited access to the inspection data.

GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN

INSPECTION AND ACCEPTANCE EQUIPMENT

Pre- and post-inspections of equipment will be conducted by the COR or designated Inspector. Additional inspection of equipment may be conducted on a regularly scheduled basis as the project progresses. Approval in writing by the COR shall be issued following the inspection.

Any equipment found not in compliance with the contract specifications will be corrected by the Contractor at no additional expense to the Government.

AG-04T0-S-16-0056

INSPECTION AND ACCEPTANCE OF SERVICES

The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract. Inspections will be visual and be performed at the project site. Visual inspections for acceptance or unacceptance will be based on contract specifications.

Each project area will be verified separately and not added to any other project site for acceptance.

Determination of the acceptability of the work performed will be based on the Government’s visual inspections. The Contractor or a designated representative is encouraged to observe the inspections while they are underway. Verification inspection of a project area may or may not be performed immediately following work performed.

UNSATISFACTORY WORK

The Contractor may be required to rework any area 1 acre or larger, as identified on the ground by the C.O.R.

where the quality of work is unacceptable.

REINSPECTION AFTER REWORK

Reinspection after the rework will be made in the same manner as the first inspection. Inspection will be of the area that was reworked.

USE OF PREMISES

A. The Contractor shall comply with the regulations governing the operation of premises that are occupied and shall perform this contract in such a manner as not to interrupt or interfere with the conduct of Government business.

B. Before any camp is opened or operated on National Forest land or lands administered by the Forest Service, the Contractor shall request permission (in writing) from the COR. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor. If permission is granted, a camping permit will be issued.

C. It is further stipulated that in addition to clean up of any campsites, the Contractor shall remove its equipment from National Forest land before final acceptance and payment of the project.

ARCHAEOLOGICAL OR HISTORIC SITES (AGAR 452.236-73) (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

LANDSCAPE PRESERVATION

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements:

A. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or natural features unless specifically authorized by the Government. Unless otherwise

AG-04T0-S-16-0056

provided, the Contractor shall confine contract operations to within the areas designated in contract documents. Unless otherwise provided in this contract, the Contractor shall gather rock, which falls outside the roadway due to contract operations and dispose of it as directed, by the Government.

B. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumen, dust palliatives, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Government. If a petroleum spill should take place in the water, the Contractor shall immediately notify the COR and the Oregon Emergency Response System (OERS), telephone 1-800-452- 0311 or 1-503-378-4124.

THREATENED, ENDANGERED, AND SENSITIVE SPECIES

Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, or Federal candidate (Category 1 and 2), sensitive or state listed species, are discovered to be present in or adjacent to the project area. Actions taken under this paragraph shall be subject to the Suspension of Work clause, FAR 52.242-14.

BIOBASED PRODUCTS

The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting form the overall quality delivered of the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal Specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative.

The following is an example list of products that may be used in this contract for which biobased products or recovered materials are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications:

Equipment lubricants and oils

The Contractor shall comply with the provision of FAR 52.223-1, Biobased Product Certification and FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

FAR 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE

AND CONSTRUCTION CONTRACTS (SEP 2013)

(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA)-designated items unless—

(1) The product cannot be acquired—

(i) Competitively within a time frame providing for compliance with the contract performance schedule;

(ii) Meeting contract performance requirements; or

(iii) At a reasonable price.

AG-04T0-S-16-0056

(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:

(i) Spacecraft system and launch support equipment.

(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.

(b) Information about this requirement and these products is available at http://www.biopreferred.gov.

(c) In the performance of this contract, the Contractor shall—

(1) Report to http://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(2) Submit this report no later than—

(i) October 31 of each year during contract performance; and

(ii) At the end of contract performance.

(End of clause)

PROPERTY AND PERSONAL DAMAGE

(a) The Contractor shall use every precaution necessary to prevent damage to public and private property.

Land monuments and property markers shall not be disturbed until the Contracting Officer, or his/her representative, has witnessed or otherwise referenced their location and directed their removal.

(b) The Contractor shall be responsible for all damage to property and to persons, including third parties, that occur as a result of his/her agent's or employee's fault or negligence. The term "third parties" is construed to include employees of the government.

PUBLIC OFFICIALS NOT PERSONALLY LIABLE

There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them, by, or with the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.

TRASH AND REFUSE MATERIAL

Contractor shall remove all of his/her own trash and refuse from the contract area. Material to be removed includes, but is not limited to: used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper garbage, etc. All placement of sanitary facilities will require prior approval of the Contracting Officer.

STORAGE OF MATERIALS AND EQUIPMENT

Materials shall be stored to assure the preservation of their quality and fitness for work. Approved portions of the right-of-way or other areas on Government land may be used for storage purposes. All storage sites approved by the Government shall be restored to a satisfactory condition at the Contractor's expense.

http://www.biopreferred.gov/ http://www.sam.gov/

POTENTIAL SAFETY HAZARDS

INHERENTLY HAZARDOUS CONDITIONS SAFETY PLAN CERTIFICATION

(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.

(b) The following conditions have been identified by the Government as inherently hazardous to a degree that failure to take the proper precautions could lead to serious injury or loss of life. This listing shall not be construed as all-inclusive. The successful Contractor shall certify that his/her Safety Plan conforms to the requirements of OSHA. The Safety Plan certification shall be submitted prior to commencing work on the project. Appropriate actions shall be taken by the Contractor to implement this plan during performance and to take any and all other necessary steps to mitigate the dangers from hazards.

Sneaker waves.

Big Surf (storm surge).

Soft sand.

Other vehicles.

Beach debris.

Working along surf/ high tides.

The inability to see hazards within the project area.

The inhalation of potentially hazardous material.

Excavation/slope stability removing sand dunes.

Traffic control on high-volume, high-speed and/or limited visibility roads.

Travel on sand roads and decommissioned roads, roads with waterbars and other barriers.

Heavy equipment operation.

Fire hazards.

Hazardous materials handling.

Hydraulic and/or pneumatic and/or high pressure hazards.

Mechanical hazards such as pulleys, springs, etc.

PERSONAL PROTECTIVE EQUIPMENT

1. The contractor will train in the safe operation and use of equipment to all workers using such equipment.

2. Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.

3. Defective or damaged personal protective equipment shall not be used.

4. The contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support. Employees operating chain saws shall wear foot protection that is constructed with cut-resistant material which will protect the employee against contact with a running chain saw.

5. The contractor shall provide, at no cost to the employee, and assure that each employee who works in an area where there is potential for head injury from falling objects or flying objects wears a hard hat that meets the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

6. The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

7. The contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise e.g., chain saw operation.

AGAR 452.236-77 EMERGENCY CONTROL (NOV 1996)

(a) Contractor's Responsibility for Fighting Fire. (1) The Contractor, under the provisions of FAR clause

52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS, shall immediately extinguish, all fires on the work site other than those fires in use as part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-1.

FSAR 4G52.222-701 EMPLOYMENT OF ELIGIBLE WORKERS (DEC 1999)

Section 274A of the Immigration and Nationality Act (8 USC 1324a) makes it unlawful for an employer to hire undocumented workers. The Immigration and Naturalization Service (INS) has established the Form I-9, Employment Eligibility Verification Form, as the document to be used for employment eligibility verification (see 8 CFR 274a).

The contractor is required to (1) have all employees complete and sign the I-9 Form to certify that they are eligible for employment; (2) examine documents presented by the employee and ensure the documents appear to be genuine and related to the individual; (3) record information about the documents on the form, and complete the certification portion of the form; (4) retain the form for three years, or one year past the end of employment of the individual, whichever is longer.

It is illegal to discriminate against any individual (other than a citizen of another country who is not authorized to work in the United States) in hiring, discharging, or recruiting because of that individual's national origin or citizenship status.

Compliance with Section 274A of the Immigration and Nationality Act (8 U.S.C. 1324a) is a material condition of the contract. If the contractor employs unauthorized workers during contract performance in violation of section 274A, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.

AG-04T0-S-16-0056

For further information on the requirements of the Act, contractors should contact the Employer and Labor Relations Officer of their local INS office.

Field Sanitation In accordance with US Department of Labor Fact Sheet No. ESA 97-28 “Field Sanitation Standards” (Ref.

29CFR 1928.110), employers must provide:

► Potable drinking water, suitably cool and in sufficient amounts, dispensed in single-use cups or by fountains, located so as to be readily accessible to employees.

► Facilities maintained in accordance with public health sanitation practices include upkeep of water quality through daily change or more often if necessary.

► Notification to each employee of the location of the water and allowance of reasonable opportunities during the workday to use them. The employer also must inform the employee of the relevant health hazards in the field and the practices necessary to minimize them.

Employees cannot be made to bear the costs incurred by the employer for providing required facilities.

(e) For further information on the requirements of the Act, contractors should contact their local Wage and Hour Division of the Department of Labor.

FSAR 4G52.222-703 MIGRANT AND SEASONAL AGRICULTURAL WORKER PROTECTION

ACT REGISTRATION (DEC 1999)

The Migrant and Seasonal Agricultural Worker Protection Act (MSPA) (29 U.S.C. 1801-1872) and implementing regulations issued by the Department of Labor (29 CFR 500), require any employer who hires or anticipates hiring employees subject to MSPA to obtain an MSPA registration number.

If the contractor employs or anticipates hiring employees subject to MSPA, the contractor shall provide a valid U.S. Department of Labor MSPA Registration Number to the Contracting Officer within 10 days after notification of award of the contract.

The Government may demand that the contractor display MSPA registration at any time during contract performance if it appears that the contractor is employing workers subject to MSPA. On demand, the contractor shall display its MSPA registration or state why it is exempt from MSPA.

Compliance with MSPA is a material condition of the contract. If the contractor fails to provide a valid MSPA number in accordance with this clause, or falsely states that it is exempt from the MSPA, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.

FSAR 4G52.222-702 LABOR STANDARDS FOR CONTRACTS INVOLVING MIGRANT AND

SEASONAL AGRICULTURAL WORKERS (DEC 1999)

(a) General. This contract is subject to the Migrant and Seasonal Agricultural Workers Protection Act (MSPA) (29 U.S.C 1801-1872) and to Department of Labor regulations implementing MSPA (see 29 CFR 500). The purpose of MSPA is to eliminate activities that are detrimental to migrant and seasonal agricultural workers, to require registration of farm labor contractors, and to assure necessary protections for the workers.

In addition to traditional farm labor activities, the Act applies to predominately manual forestry work including, but not limited to, tree planting, release, precommercial thinning, and site preparation and wildland fire fighting.

(b) Definitions.

AG-04T0-S-16-0056

"Migrant Agricultural Worker" and "Seasonal Agricultural Worker", as used in this clause, mean individuals employed in agricultural (including forestry) work on a seasonal or temporary basis. A worker who moves from one seasonal activity to another is employed on a seasonal basis even though the worker may continue to be employed during a major portion of the year. Migrant workers are required to be absent overnight from their permanent place of residence. Seasonal workers are not required to be absent overnight from their permanent place of residence. Members of the contractor's immediate family are not considered to be either migrant or seasonal workers. "Immediate family" includes only (1) spouse; (2) children, stepchildren, or foster children; (3) parents, stepparents, or foster parents; and (4) brothers and sisters.

"Farm Labor Contractor", as used in this clause, means an individual who, for any money or other valuable consideration, paid or promised to be paid, performs any recruiting, soliciting, hiring, employing, furnishing, or transporting of any migrant or seasonal agricultural worker.

(c) Registration Requirement. Any contractor who provides or hires migrant or seasonal workers to perform agricultural or manual forestry work shall first obtain a Certificate of Registration from the Department of Labor or an authorized State agency. The contractor shall carry the Certificate at all times while engaged in contract performance, and shall display it upon request. Any of the contractor's employees who also perform any one or more of the activities defined for a "Farm Labor Contractor" in paragraph (b) must have their own Farm Labor Contractor Employee Certificate.

(d) Worker Protections. The contractor shall comply with the following protections and standards related to wage disclosure, recordkeeping, vehicle safety, and housing:

(1) The contractor shall display and maintain at the place of employment the MSPA poster provided by the Department of Labor.

(2) Wage and Payroll Standards

(i) The contractor shall disclose in writing to each worker in a language common to the worker the full terms of their employment, including workers compensation information, at the time they are recruited or hired.

The Department of Labor provides an optional form WH-516 for contractor's use in disclosure.

(ii) The contractor must keep the following payroll records for each employee: name, address, social security number, basis for wages (i.e. per hour, per tree, per acre), number of units earned if paid on a per unit basis, hours worked, total pay, withholdings and purpose for each, and net pay. Payroll records shall be retained for three years.

(iii) Payments must be made no less frequently than every two weeks or semi-monthly. At the time of each payment, the contractor shall provide to the employee a written itemization of the information listed above and which shall include the employer's tax identification number.

(iv) If paid on a piece rate basis, the employee's wage must be at least equivalent to the required hourly wage for the hours worked, including overtime differential for time in excess of 40 hours per week.

(3) Motor Vehicle Safety

(i) The contractor must be registered to transport employees, unless employees provide their own transportation or carpool by their own arrangement in one of their own vehicles. The authorization to transport employees must appear on the contractor's certificate. If the contractor directs or requests employees to carpool, the registration requirement is still applicable. Any driver who transports workers for a

AG-04T0-S-16-0056

fee or at the direction of the contractor must be registered as a farm labor contractor or a farm labor contractor employee.

(ii) Any vehicle under the ownership or control of the contractor shall comply with safety standards applicable to that vehicle. Generally passenger vehicles or station wagons must comply with Department of Labor regulations at 29 CFR 500.104. Vehicles other than passenger vehicles or station wagons which are driven more than 75 miles must comply with Department of Transportation Regulations at 29 CFR 500.105.

All drivers must have a current, valid State drivers license.

(iii) Each vehicle under the ownership or control of the contractor which is used to transport any migrant or seasonal agricultural worker shall be covered by vehicle insurance of $100,000 per seat (maximum $5,000,000). A workers compensation policy which covers the workers while being transported plus an additional property damage policy for $50,000 for loss or damage in any one accident to the property of others may be substituted for the vehicle insurance requirement.

(4) Housing

(i) The contractor shall house workers only in a commercial establishment or a facility that has been certified by a health authority or other appropriate agency. The contractor must post the certificate of occupancy at the housing site.

(ii) The authorization to furnish housing, other than commercial lodging, must appear on the contractor's certificate.

(e) For further information on the requirements of the Act, contractors should contact their local Wage and Hour Division of the Department of Labor.

TERMINATION FOR DEFAULT, DAMAGES FOR DELAY

Employment of undocumented workers is conducive to creating situations that cause undue and unwarranted disruptions to contract work. To avoid these situations, it is hereby mutually agreed in the event the Contracting Officer receives written notice from the U. S. Immigration and Naturalization Service of two (2) separate instances where undocumented workers were employed on work under this Contract; action will be taken to place the Contractor in default.

INVOICE PROCESSING PLATFORM

NOTE: The paragraph below replaces the paper invoice copies requirement referenced on FAR 52.212-4 (g) invoices.

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in the previous communications from USDA and Treasury. All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Please make sure that your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account.

https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm

FAR 52.212-4 (ALT 1) CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (MAY

2015)

(a) Inspection/Acceptance. (1) The Government has the right to inspect and test all materials furnished and services performed under this contract, to the extent practicable at all places and times, including the period of performance, and in any event before acceptance. The Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in contract performance. The Government will perform inspections and tests in a manner that will not unduly delay the work.

(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.

(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.

(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements. Except as otherwise specified in paragraph (a)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the “hourly rate” attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. [Insert portion of labor rate attributable to profit.]

(5)(i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may—

(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or

(B) Terminate this contract for cause.

(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.

(6) Notwithstanding paragraphs (a)(4) and (5) above, the Government may at any time require the

Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to—

(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor's managerial personnel; or

(ii) The conduct of one or more of the Contractor’s employees selected or retained by the Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.

AG-04T0-S-16-0056

(7) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.

(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.

(9) Unless otherwise specified in the contract, the Contractor's obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. (1) The clause at FAR 52.202-1, Definitions, is incorporated herein by reference. As used in this clause—

(i) Direct materials means those materials that enter directly into the end product, or that are used or consumed directly in connection with the furnishing of the end product or service.

(ii) Hourly rate means the rate(s) prescribed in the contract for payment for labor that meets the labor category qualifications of a labor category specified in the contract that are—

(A) Performed by the contractor;

(B) Performed by the subcontractors; or

(C) Transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.

(iii) Materials means—

(A) Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates of the contractor under a common control;

(B) Subcontracts for supplies and incidental services for which there is not a labor category specified in the contract;

(C) Other direct costs (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.);

(D) The following subcontracts for services which are specifically excluded from the hourly rate: [Insert any subcontracts for services to be excluded from the hourly rates prescribed in the schedule.]; and

(E) Indirect costs specifically provided for in this clause.

AG-04T0-S-16-0056

Stewardship - Dunes Day-Use Area Foredune Restoration Project http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_233_240.html#wp1113304 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137572

(iv) Subcontract means any contract, as defined in FAR Subpart 2.1, entered into with a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract including transfers between divisions, subsidiaries, or affiliates of a contractor or subcontractor. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, contract line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct…