e.Spec870.pdf

PDF 9 KB Posted

Attached to
South Zone rock Crushing
Solicitation number
AG-04M3-S-15-0047
Issued by

About this file

E. Spec 870

View the file

Other files

File Type Posted
f.Pit_Plan.pdf PDF
g.05-2569.txt TXT text file
h.FirePlanr6fs6300521.rtf RTF text file
d.Spec850.pdf PDF
i.Return_This_Copy.rtf RTF text file
c.Spec820.pdf PDF
b.Vicinity_Map.pdf PDF
a.AG-04M3-S-15-0047.rtf RTF text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 870 – Materials Source Reclamation

Services Required

Contractor shall reclaim the materials source after production of the ordered quantity is complete.

Performance Standards

Reclaim the materials source as shown on the Pit Plan. All work shall be performed in accordance with MSHA 30 CFR, part 56.

Acceptable Quality Levels

Suitable and unsuitable residual materials are uniformly smoothed over floor, except oversized materials are consolidated in the location shown on the Pit Plan. Excavated slopes are uniformly shaped, and no steeper than 1:1. Pit floor is sloped toward the center, to retain water.

Payment

The accepted quantity will be paid at the contract price for the Section 870 pay item shown in the Schedule of Items. Payment will be full compensation for the work prescribed in this section.

Section 870 – Materials Source Reclamation