f.6625270 Plans.pdf
PDF 1 MB Posted
- Attached to
- East Pine Creek Road 6625270 Culvert Replacement
- Solicitation number
- AG-04M3-S-11-0037
About this file
f. Plans
View the file
Other files
| File | Type | Posted |
|---|---|---|
| a.quoters_packet.docx | DOCX document | |
| d.6625270Specs.pdf | ||
| b.final_solicitation.docx | DOCX document | |
| c.6625270 Spec_List.pdf | ||
| e.6625270MaintSpecs.PDF | ||
| h.FireProtectionandSuppressionr6_fS_6300_52.rtf | RTF text file | |
| j.FireSuppressionCommunicationR6630054.doc | DOC document | |
| g.OR2_dvb.mht | MHT file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quantity
15101 Mobilization
LS
FSSS 171 Equipment washing and written notification requirements.
15204 Drainage structure survey and staking LS FP-03 Table 152-1 Tolerance for Culverts
15713 Soil Erosion & Pollution Control
LS
FSSS 157.03 Submit a written soil and erosion control plan.
15709 Dewatering and Diversion LS FP03 157.09 Stream Diversion and Groundwater
20105 Clearing and grubbing, disposal of tops and limbs 4, logs 4, stumps 4 LS
201.04 Utilization of Timber 6" top, 8' length; deck. 201.06
Disposal: (4) Scattering.
20305 Removal of structures and obstructions LS Removal of existing 14' x 75' culvert and Footings; Culvert:
Disposal method A (off government lands) Footings:
Disposal method C
20401 Roadway excavation & embankment, compaction method B, finishing method B CQ CY
Unsuitable material to be hauled to a material source location as designated by the COR.
20950 Pipe bedding (Govt. furnished stockpile) CQ CY From Stockpile at Round Mtn. Pit
20964 Foundation Fill (Govt. furnished stockpile) CQ CY From Stockpile at Round Mtn. Pit
25101 Placed riprap, class 4 CQ CY 60 Riprap and placement. From Forest Service Designated Sources and excavation.
25104 Keyed riprap, class 6 CQ CY Riprap and placement. From Forest Service Designated Sources and excavation.
30801 Roadway aggregate, compaction method B CQ CY 31 From Stockpile at Round Mtn. Pit. Grading D or approved equal, Compaction Method B; Water Indirect to this item
55203 Structural concrete LS All
For Precast: Includes Footing design, construction and placement For Cast In Place: Includes Footing design, materials (including rebar), forms, labor, and pouring
60302 19' span, 6' 4" rise, structural plate pipe-arch LS 63' bottom Length, 19' span, 6'4" rise with 1 1/2h:1v step bevel end treatment. Includes culvert, and all labor, materials and equipment needed to install structure
63501 Temporary traffic control LS FSR 6625270 will be closed during project.
64802 Placed fish rest stop rock, Channel Rock class 3, method A Each Channel rocks (sheet 7 of 7) sorted from onsite excavation and stream bed
64804.12 Placed Streambed simulation rock, bed class 12, method A CQ CY 163 Sorted from onsite excavation and stream bed
64804.16 Placed Streambed simulation rock, bed class 16, method A CQ CY 70 Sorted from onsite excavation and stream bed
65101 Pit and Quarry Development Each 2 On-Site Source
Control Pt. Description Location Northing Easting Elevation
CP1 Rebar in Road South Shoulder @ Intersection 6625 - - 1010.87
CP2 Spike in 8" Pine STA 0+53 16' Rt 4942.08 4943.62 999.10 CP3 Rebar in Road STA 1+33 1' Lt 5000.00 5000.00 1000.00 CP4 Spike in 30" Fir STA 2+16 33' Rt 5025.89 5092.87 1005.97
Foundation Pt. (CL) Northing Easting
Elevation @ Bottom of
Foundation A 5046.11 5014.79 986.80 B 5045.23 5034.77 986.80 C 4979.18 5011.83 985.83 D 4978.30 5031.81 985.83
GENERAL NOTES:
File details come from the government source that posted it. Updated .