AMENDMENT NO. 1

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

CONTRACT ID CODE PAGE 1OF2 PAGES

2 AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

02/17/15

4. REQUISITION/PUCHASE REQ. NO.

730305

5. PROJECT NO.(IF APPLICABLE)

6. ISSUE BY CODE 7.ADMINISTERED BY (if other than item 6) CODE

Dechutes National Forest 63095 Deschutes Market Rd.

Bend, OR 97701

8.NAME AND ADDRESS OF CONTRACTOR(No., street, county, State and ZIP Code) X 9A.Amend Solicitation. AG-04GG-S-15-0012

* 9B.Dated 02/05/2015

* 10A.Mod Contract/Order #

* 10B.Dated (see Item 13) code facility code

11. THIS ITEM APPLIES ONLY TO AMENDMENT OF SOLICITATION

[X ] The above numbered solicitation is amended as set forth in the item 14. The hour and date specified for receipt of Offers [X ] is extended

Quotes now due Monday February 23, 2015 C.O.B. 4:30PM[ ] is not extended. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted, or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegam or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. This change order is issued pursuant to; (specifiy authority) The changes set forth in item 14 are made in the Contract/Order # in item 10A.

B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.) set forth in item 14, pursuant to the authority of FAR 43.103(b)..

C. This supplemental agreement is entered into pursuant to authority of:

D Other: (Specify type of modification and authority):

E. IMPORTANT: Contractor [ ] is not [ ] is required to sign this document and return _ Original to the issuing office.:

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)

Deschutes National Forest - Design, Fabrication & Delivery of Prefabricated Steel Trail Bridge.

See attached questions, answers and clarificatons.

As provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A.NAME AND TITLE OF SIGNER (Type or print)

16A.NAME AND TITLE OF CONTRACTING OFFICER

MARIA D. GONZALEZ Contracting Officer

15B.CONTRACTOR/OFFEROR

By ______________________________ (Signature of person authorized to sign)

15C.DATE SIGNED 16B.UNITED STATES OF AMERICA

By______________________________ (Signature of Contracting Officer)

16C.DATE SIGNED

02/17/15

Standard Form 30 Prescribed by GSA FAR (48CFR) 53.243

Solicitation AG-04GG-S-15-0012

AMENDMENT 1

The following questions and answers are provided:

(1) Timber Deck (page 5 of 6)- 4”x8” Minimum

Would you accept a 2” or 3”? Since the bridge is so narrow it does not affect the performance and it would be more cost effective. The Forest Service is specifying a 4” thick minimum decking to lengthen the service life of the decking since it will not be pressure treated.

Clarification:

Top Rail Height:

In the drawing you have a 4’-6” min for bike use. Per AASHTO LRFD 2010 sections 13.8.1 and 13.9.2, both pedestrian and bicycle railing needs to be a minimum of 42" above the top of the path. Would you like to us to quote the 42” to be more cost effective? The Forest Service has Trail bridge Design Criteria that is listed in the

Forest Service Handbook. This particular bridge used the “Mountain Bike” Trail design Use Category which called for a Top of Rail/Top of Truss height of 54”. The reference to this is “Table1 - Trail bridge design criteria (Adapted from FSH 7709.56b, section 7.69, exhibit 01)”. This can be found on the website:

http://www.fs.fed.us/t-d/pubs/htmlpubs/htm10232808/page12.htm

Bridge Detail (page 6 of 6)

Clarification on deck planks (by others): supplied by bridge supplier and shipped installed at fabricators facility? The Forest Service will purchase the decking from another vendor and install the decking planks in house. The Bridge Supplier only provides the Shop Drawings for the decking showing the dimensions and the fabrication details for all cuts and hole boring and also an installation plan for the connection of decking planks to the superstructure.

Would you be open to other wood options for decking? The decking planks will be purchased by the

Forest Service from another vendor. On page 6 of 6 the detail in the top right corner shows items to be supplied by the bridge supplier and items supplied by “Others”.

CORRECTION: Dimension correction for the footing on Drawing Sheet 6 of 6. Attached separately.