Pre Bid Meeting Notes.docx
DOCX document 13 KB Posted
- Attached to
- Princess Lake Boat Launch & Parking Ramp
- Solicitation number
- AG-04GG-S-10-0012
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 3 Word Doc.docx | DOCX document | |
| Amendment 2 Princess Creek Launch.docx | DOCX document | |
| Princess Creek Boat Launch Amendment One Word Doc.doc | DOC document | |
| Final Drawings for Princess Creek Boat Launch Parking Areas.pdf | ||
| Solicitation_Princess_RFP.doc | DOC document | |
| DOL Wage Rate OR2_dvb.htm | HTM file | |
| SF 25.pdf | ||
| SF 25A.pdf | ||
| Specifications.doc | DOC document | |
| SF 24.pdf | ||
| Attachment 04 R6_Fire_Requirements.rtf | RTF text file | |
| Spec List.xls | XLS spreadsheet |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre Bid Meeting Notes
Princess Creek Boat Launch and Parking Area
Date: June 15, 2010
Location: Deschutes NF SO, Project Location
Following are the items discussed during this meeting:
Acquisition:
1. Negotiated Solicitation
2. Government Range 250K – 500K
3. Set Aside for HUBZone in accordance with FAR 19.1305
4. Requirement of bonding
5. Bid acceptance period
6. Location, date and time set for bid submission
7. Contract authority
8. All contract sections
9. Wage determination
Engineering:
1. Slash pit disposal location as defined in specification
2. Disposal of pit toilet by awardee off FS Property
3. Site signs to be retained by the FS
4. Details on drawing sheets #8, 9, 13, 23, & 25
5. ADA requirements for project in general
Parties were reminded that all comments made today are informational only and would not bind the Government in any way. Parties were informed they must submit any request for clarification or questions to the Contracting Officer in writing and that they would be forward to engineering for evaluation and if needed an amendment would be issued. All parties were informed the Contracting Officer will make no verbal changes or alterations to this solicitation.
All parties were informed that any comments or promises made by any person other than Contracting Officer are non binding to the Government.
The pre bid meeting was moved to the project location at which time all parties in attendance were given the opportunity to view the site. Upon conclusion of the on site visit the meeting was completed.
Mark L LaCroix Contracting Officer 6/17/2010