CONSTRUCTION RFP SOL NO

UNIT

PROJ NAME

CONSTRUCTION RFP SOL NO

PROJ NAME

CONSTRUCTION RFP SOL NO AG-0489-S-10-0390

UNIT G-P NF

PROJ NAME Install Silver Creek and Wilamee Bridges

PART I—THE SCHEDULE

Project: Recovery - Silver Creek and Willame Creek Bridge Replacement Contract

A.9 FOR INFORMATION CALL:

Technical Contact Telephone No.

Sarah Rockey 360-497-1113

Dean Lawrence 360-497-1162

A.10 THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK

DESCRIBED IN THESE DOCUMENTS

Recovery – Silver Creek and Willame Creek Bridge Replacement Contract

Gifford Pinchot National Forest

Cowlitz Valley Ranger District

Lewis County, Washington

Price Range: Between 250,000 and $500,000.

PART I - SCHEDULE OF ITEMS

SECTION B – SUPPLIES, SERVICES, AND PRICES

RECOVERY- SILVER CREEK & WILLAME CREEK BRIDGE REPLACEMENT CONTRACT

GIFFORD PINCHOT NATIONAL FOREST

COWLITZ VALLEY RANGER DISTRICT

LEWIS COUNTY, WASHINGTON

B.1 SCHEDULE OF ITEMS

This is Bid item #1 and is for Silver Creek Bridge located on Forest Road 8500 – MP 21.8

ITEM

NO.

DESCRIPTION

PAY

EST.

QTY.

PRICE

TOTAL

15101

Mobilization

Lump Sum

All

15221

Construction Survey and Staking

15713

Soil Erosion & Pollution Control

20102

Clearing and Grubbing

20304

Removal and Disposal of

Existing Bridge

20435

Unclassified Borrow

(Government Source)

Cubic

Yard

20802

Foundation Fill

Cubic

20806

Structure Excavation

25101

Placed RipRap, Class 5

Cubic

26201

Grouted Rebar Column

Each

30103

Base Aggregate, Grading D

(Commercial Source)

Each 60

30809 Crushed Aggregate, Surfacing

Cubic

35 $________ $________

40401

Minor Hot Asphalt Concrete

Ton

55213A

Precast Concrete Member, Abutment

55213B

Precast Concrete Member, Wingwall

55601

Thrie Beam Bridge Rail, Type IV

Class B

Linear

Foot

57102

Government-Furnished Prefabricated

Bridge Superstructure, transport and install

Each 1

61702B

Terminal Section, Type Fleat, Test Level 2

61708

Guardrail System, Transition Section, Type IV

62503

Seeding, Dry Method (Government

Furnished Seed)

62509

Mulching, Dry Method

63501

Temporary Traffic Control

Total Bid Item #1 = $________________

B.1 SCHEDULE OF ITEMS

This is Bid Item #2 and is for Willame Creek Bridge located on Forest Road 4715 – MP 1.1

ITEM

NO.

DESCRIPTION

PAY

EST.

QTY.

TOTAL

15101

Mobilization

15221

Construction Survey and Staking

15713

Soil Erosion & Pollution Control

20102

Clearing and Grubbing

20304

Removal and Disposal of

Existing Bridge

20435

Unclassified Borrow

20802

Foundation Fill

Cubic

20806

Structure Excavation

25101

Placed RipRap, Class 5

Cubic

26201

Grouted Rebar Column

30103

Base Aggregate, Grading D

(Commercial Source)

30809

Crushed Aggregate, Surfacing

40401

Minor Hot Asphalt Concrete

Ton

55213A

Precast Concrete Member, Abutment

55213B

Precast Concrete Member, Wingwall

55601

Thrie Beam Bridge Rail, Type IV

Class B

Linear

Foot

57102

Government-Furnished Prefabricated

Bridge Superstructure, transport and install

Each 1

61702B

Terminal Section, Type Fleat, Test Level 2

61708

Guardrail System, Transition Section, Type IV

62503

Seeding, Dry Method (Government

Furnished Seed)

62509

Mulching, Dry Method

63501

Temporary Traffic Control

Total Bid Item #2 = $________________

TOTAL PRICE = $_________________

(Bid Item #1 + Bid Item #2)

B.2 NOTE:

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction

Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

There are two separate work sites associated with this contract.

Site # 1 – Silver Creek Bridge Replacement, FR 85.

Remove existing log stringer bridge, scatter logs as directed by CO

Remove existing bridge abutments

Load, transport and unload Government Furnished Bridge at Project Site

Install Government Furnished Bridge.

This site involves removing the 70 foot long Log Stringer bridge referred to as Silver Creek that is located on Forest Road 85 at mile post 21.8 and the transport and installation of a government furnished 88 foot long modular bridge and associated hardware from the storage site at the *Packwood Work Center

Compound to its final destination at the project site. See Project Location for specific directions to project site.

Site # 2 – Willame Creek Bridge Replacement, FR 4715.

Remove existing log stringer bridge, scatter logs as directed by CO

Remove existing bridge abutments

Load, transport and unload Government Furnished Bridge at Project Site

Install Government Furnished Bridge.

This site involves removing the 71 foot long Log Stringer bridge referred to as Willame Creek that is located on Forest Road 4715 at mile post 1.1 and the transport and installation of a government furnished

88 foot long modular bridge and associated hardware from the storage site at the *Packwood Work Center

Compound to its final destination at the project site. See Project Location for specific directions to project site.

Disturbed ground shall be seeded at both bridge sites. Provide drafted as-built construction plan drawings of finished bridges and site including bridge superstructure, substructure, backwall, and any other significant details.

C.2 PROJECT LOCATION

This project is located within the Gifford Pinchot National Forest, in the State of Washington. Contractor will be responsible for loading, transporting, and unloading of each bridge package from its storage site, listed below, to the specified project site for installation.

Site # 1 – Silver Creek Bridge Replacement, FR 85. The first project site is located at mile post 21.8 on

USFS Road 85. This site is located over Silver Creek, T 13 N, R 7 E, Section 13. Road access to site one from the town of Packwood is North on Forest Road 52 (Skate Creek) road for 18.2 miles then turn left onto Forest Road 84 and follow it South for 14.2 miles then turn right on Forest Road 47 and follow it

West for 5.0 miles before turning right onto Forest Road 85 and following it North for 0.4 miles to the location of the Silver Creek bridge work site.

Site # 2 – Willame Creek Bridge Replacement, FR 4715. The second project site is located at mile post

1.1 on USFS Road 4715. This site is located over Willame Creek, T 13 N, R 9 E, Section 18. Road access to site two from the town of Packwood is North on Forest Road 52 (Skate Creek) road for 18.2 miles then turn left onto Forest Road 84 and follow it South for 14.2 miles then turn left on Forest Road

47 and follow it East for 5.4 miles before turning right onto Forest Road 4715 and following it South for

1.1 miles to the location of the Willame Creek bridge work site.

Storage site for the government furnished modular bridges and hardware is located at:

*Packwood Work Center Compound (70 miles east of I-5 on State Route 12)

360 Cannon Road

Packwood, Washington 98361

Directions to the Packwood Work Center Compound include the following:

From Interstate 5, take the Highway 12 exit, towards Randle/Packwood. Proceed East on Highway 12 until you have reached the town of Packwood. Near the end of town, turn left onto Skate Creek Road and travel North. Shortly after crossing a bridge over the Cowlitz River, turn right onto Cannon Road.

Proceed approximately 1.5 miles to the Forest Service yard that will be located on the right side. There will be a large barn visible. Once at the yard the bridge location can be found by traveling down a short road on the right that is gated with a Forest Service lock. Prior arrangements will need to be made in order to get access behind the gate. In order to obtain gate access, the contractor will need to contact the

Engineering Department at the Cowlitz Valley Ranger District. Please contact one of the following

Engineers to make arrangements:

Sarah Rockey – 360-497-1113 or Dean Lawrence – 360-497-1162

C.3 PRICE RANGE

The Government‘s estimate is between $250,000 and $500,000.

C.4 PROSECUTION OF WORK

(a) General:

The contractor shall conduct activities so that interference with the public is kept to a minimum.

(b) Timing Restrictions:

Site # 1 – Silver Creek Bridge Replacement, FR 85:

The Forest Service anticipates that work on this project site shall begin on June 15 th . The Forest

Service is conducting owl surveys to confirm this date.

All In-Stream work shall occur between: July 1st and September 30th. The Forest Service has requested an Hydraulic Project Approval with Washington Department of Fish and Wildlife for this In-Stream work period.

Site # 2 – Willame Creek Bridge Replacement, FR 4715:

Willame Creek has been identified as potential Marbled Murrelet nesting habitat by the US Fish and Wildlife Service. Consequently any significant noise making activities are not allowed prior to August 6.

Any planned work at the Willame Creek Bridge site before August 6 will need to be approved by the Forest Service.

From August 6 through September 15 th , construction activities at the site will be allowed from

7:15 am until 7:15 daily.

From September 16 th until the end of the construction season there will be no wildlife restrictions.

All In-Stream work shall occur between: August 1 st and September 30 th . The Forest Service has requested an Hydraulic Project Approval with Washington Department of Fish and Wildlife for this In-Stream work period.

(c) Transport & Delivery – Use of Roads by Contractor:

The Contractor is authorized to use roads that are part of the construction project and those Forest Service

Roads designated below for performance of work under this contract.

For Site # 1 Forest Roads 52. 84, 47 & 85

For Site # 2 Forest Roads 52, 84, 47 & 4715

Load Limits – All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, overwidth permits.

Coordinate planned transport and installation date with the Contracting Officer and Contracting Officers

Representative. The Contractor shall notify the Contracting Officer a minimum of 3 days before transporting any material. The Contractor is responsible for loading and unloading the bridge materials

(including any necessary equipment) and any support material needed to adequately support the structures.

Traffic Control Plan – Contractor shall submit a traffic control management plan and allow 7 days for approval. Contractor shall perform no work that interferes or conflicts with traffic or existing access to the roadway surface until the required traffic control management plan is submitted and approved and is not to proceed with work on the project until all required signs and safety devises are in place and approved. During transport on USFS roads, contractor shall provide sufficient traffic control in compliance with MUTCD standards and standard specification sections 156 & 635 in order to control and protect public traffic. Contractor shall be responsible for traffic control during the equipment & material transport on Forest Service land. Contractor is responsible for submitting a traffic control plan.

Road Use Permit - Contractor will obtain a road use permit from the Forest Service prior to transporting the bridge across Forest Service property. Forest Service road use permits for this project may be obtained by contacting the Cowlitz Valley District Ranger. Please allow up to 7 days to process these permits.

Overload Limit & Overwidth Permits (As required)- All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, overwidth permits. Forest Service overload permits for this project may be obtained by contacting the

Cowlitz Valley District Ranger, and/or the Gifford Pinchot National Forest Bridge Program Manager located at Forest Headquarters. Please allow up to 14 days to process these permits.

The Contractor is responsible for any damage to the structure during loading, transport, and unloading.

(d) Road Closure

Contractor shall close USFS Road(s) 85 & 4715 at the project sites for the duration of the project work.

Contractor shall sign the road closure and place temporary barricades in accordance with the MUTCD, FP-03 section 156, and section 635. This will include the use of ―Road Closed‖ and ―Road Closed

Ahead‖ signs, as well as the use of Type III Barricades. Do not proceed with work on the project until all required signs and safety devises are in place and approved. Contractor shall at all times be responsible for ensuring that necessary temporary traffic control devices remain in place for the duration of the project work. All temporary signs and barricades shall be removed from the project by the contractor after work is complete and approved by the CO. Removal of signs and barricades shall not occur before

CO approval.

Limit road closure time as acceptable to reduce interference with public traffic.

C.5 APPLICABLE SPECIFICATIONS AND MATERIAL CERTIFICATIONS

(a) Applicable Specifications:

References to Standard Specifications in the contract refer to the STANDARD SPECIFICATIONS

FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS, FP-03

US CUSTOMARY UNITS.

Sections 100 through 149, and other Standard Specifications, listed on the Specification List, are included in this solicitation by reference only. Specifications not on the list but referenced by other Standard

Specifications, shall also be applicable to this document.

The Supplemental Specifications are also given on the Supplemental List but are physically attached in

Section J. All requirements contained on the Supplemental List are hereby made a part of this solicitation and any resultant contract.

(b) Product Substitution:

Any modification of other items, designs, materials, products or equipment (including Government-

Furnished Property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

(c) Shop Drawing Submittals:

As-Built Plans required. To be submitted to the CO before the final inspection. Refer to FP-03 specification 104.03, for more details regarding drafting specifications. Provide at least 4 copies on tabloid size paper (11‖x17‖) to the CO/COR. When shop drawings have been approved, the Contractor shall supply a Portable Document Format (PDF) file created to print on 11‖ by 17‖ paper. All notes, details and dimensions must be clear, readable and professional in appearance.

The As-Built plans shall include all structural elements as they exist after construction. Include plan, elevation, and section views of the final structure as constructed in the field. Include all important elements not limited to but including the approach railing, all elements of the superstructure, and all elements of the substructure constructed in the field. As-Built plans shall include any modifications, additions, changes, or elements removed from the original shop drawings. The drawings shall be prepared, sealed and signed by registered professional engineers who are currently licensed in the State where the bridge will be constructed.

(d) Material Certifications, Testing Reports & Other Submittals:

The following plans, details, specifications, designs, certificates, test reports, samples and test data shall be submitted on this project (see table below for number of copies required). See AGAR section 452.236-76 for timely submittal and approval by Contracting Officer.

Brief Title Basic

Reference

Detailed

Requirements

Section

Number

Of

Copies

To

Section

Allowable

Time for

Government

Approval

After Total

Submittal

(Days)

Hazardous Spill Plan 107.10 1 7

Quality Control Plan 153.02 153.02 2 7

Erosion Control Plan 157.03 157.03 1 7

Weather-Caused Suspensions of Work

Plan

H.2 1 7

Fire Plan J.3 1 7

Project Work Schedule FAR 52.236-15 2 7

Traffic Control Plan 156 & 635 156.03 1 7

Road Use permit 36CFR261.12 &

261.54(c)

RCW 46.44 1 7

Road Oversize/Overweight permit(s) 36CFR261.12 &

261.54(c)

1 14

Gradation range target values 0322.03 Table 703-2 2 7

Riprap (If commercial source) 251.07 & 106.03 705.02 2 7

Concrete Mix Design, including admixtures

552.03, 552.09, FS Supp 552.03

2 30

Concrete Placement Schedule FS Supp 552.09

Portland Cement Production

Certification

552.19 701.01 (a) 2 N/A

Concrete Quality Control Certificates, including batch tickets and test results

552.09, FS Supp

552.09 & 106

1 N/A

Reinforcing Steel Production

Certification

554.10 709.01 & FS Supp

709.01

1 N/A

Non-pressure Epoxy Grout Anchors -

Manufacturer‘s test information and/or other Anchor Data

571.10 571.10 2 15

As-Built Plans 104.03 4 21

(e) General Guidelines for Submittals:

Submittals are required by their corresponding specification (basic reference & detailed requirement).

Work requiring submittals shall not begin until submittals have been approved.

Submittals shall include:

Date and Revision Dates

Project Name and Contract Number.

Names of Contractor, Subcontractor, Supplier, and Manufacturers.

Field Dimensions and Relation to Adjacent Structures.

Contractor's stamp, initialed or signed, certifying review of submittal, verification of field measurement and compliance with contract documents.

Samples:

Physical examples shall illustrate materials, equipment, or workmanship, and establish standards by which completed work shall be judged. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of product or material, with integrally related parts and devices.

Manufacturer's requirements:

Supply manufacturer's catalog sheets or brochures with diagrams, schedules, or performance charts.

Illustrations shall be clearly marked to identify pertinent materials or models, dimensions, and clearances required. Supplement standard drawings to provide information unique to this project.

Approval or Rejection Time Allowance:

Submittals will be reviewed and either approved or rejected within 30 calendar days of their receipt by the

Contracting Officer or COR unless otherwise noted.

C.6 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-73)

(FEB 1988)

The attachments to the Statement of Work/Specifications, listed in Section J, are hereby made part of this solicitation and any resultant contract.

C.7 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS (AGAR 452.236-78)(NOV 1996)

The STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL

HIGHWAY PROJECTS, FP-03, U.S. CUSTOMARY UNITS, is included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.

C.8 CONSTRUCTION PLANS

Copies of the plans pertinent to this project have been attached in section J.

C.9 BRIDGE COMPONENTS

The provided bridge structure comes in two main parts; basically the bridge has been split down the middle. There will also be other small components associated with the bridges installation that will need to be transported.

C.10 DISPOSAL OF EXCAVATION MATERIAL

Dispose of all other excavation material, including slash and other organics, at a site adjacent to the project site, to be staked by the COR. Follow specification 203.05 for proper burial of debris and organic materials within layers of compacted earth. Seed and mulch the disposal areas according to section 625.

C.11 ABUTMENT ANCHORS

The contractor will be responsible for properly installing anchor bolts in the abutments. Payment for these anchors will be incidental to Pay Item #55213A. Refer to plan sheets B. 6-9 and C. 6-9 for details regarding the anchor bolt placement locations and size.

C.12 ABUTMENT EXCAVATION AND BACKFILL

Refer to plan sheets B. 5 and C. 5 for details.

C.13 REMOVAL OF TRAFFIC SIGNS AND BARRICADES AFTER BRIDGE INSTALLATION

Remove all closure signs and barricades associated with the project site road closure after performance of the contract work is approved by the Contracting Officer. All signs and barricades removed are to remain the property of the government. These include all ―Road Closed‖, ―Road Closed Ahead‖, Type III Barricades, and possible other warning signs installed by as was specified by the MUTCD.

C.14 ROADWAY APPROACHES

Survey and stake bridge location. Align bridge with roadway approaches.

Ensure that roadway approaches to bridge are constructed to provide a smooth transition for traveling vehicles.

Use grade D aggregate (i.e. ¾‖ minus) for the base material before placing the final asphalt approach surface.

Both sides of the bridge require a final paved approach surface that is described in the plan drawings. Perform initial compaction while the mixture is above 250° F. Grade surface according to existing road grade and so that drainage is directed towards existing ditch lines. Seed any disturbed areas.

C.15 TECHNICAL CONTACT(S)

1. Woody Starr via telephone @ 360-891-5159 or E-Mail @ estarr@fs.fed.us

2. Shea Becker via telephone @ 360-891-5166 or E-Mail @ stbecker@fs.fed.us

3. Sarah Rockey via telephone @ 360-497-1113 or E-mail @ ssrockey@fs.fed.us

4. Dean Lawrence via telephone @ 360-497-1162 or E-Mail @ delawrence@fs.fed.us

AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

mailto:estarr@fs.fed.us mailto:delawrence@fs.fed.us mailto:ssrockey@fs.fed.us mailto:delawrence@fs.fed.us

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996) http://www.arnet.gov/far/

SECTION F—DELIVERIES AND PERFORMANCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR

1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days after the date the Contractor receives the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

Estimated start work date: June 15th, 2010

F.3 MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE (AGAR 452.236-75)(NOV 1996)

Within 7 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is Monday through Friday, 7:00 am to 7:00 pm.

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract:

1. Two Bridges and accompanying hardware for installation on Road 85 at milepost 21.8 and Road 4715 at milepost 1.1.

Bridge Name NFS Road No. Nominal Deck Deck Width Storage Site

Silver Creek

Bridge 85-21.8 88 Feet 15 Feet -10 Inches

*Packwood Work

Center

Willame Creek

Bridge 4715-1.1 88 Feet 15 Feet -10 Inches

*Packwood Work

Center

2. Unclassified Borrow. Located at Boundary Quarry on Forest Road 4740015 at milepost 0.75. An alternate borrow source is on Forest Road 6300091 located at milepost 7.4 on Road 6300.

3. Riprap. Source located on Forest Road 5240 at milepost 0.5.

4. Crushed Aggregate, Surfacing. Source located on Forest Road 5240 at milepost 0.5.

5. Seed

6. ARRA Project Sign.

The Government will furnish the proper seed required in the contract upon the Contractor‘s request. Notify the

COR at least 7 days prior to obtaining the seed so that the proper arrangements can be made to provide the seed.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 EMERGENCY CONTROL (USDA 452.236-77)(JUL 1985)

(a) Maintenance of Existing Facilities:

The Contractor shall conduct his operations to minimize disruptions to the Government employees and public using the existing facilities.

H. 2 LANDSCAPE PRESERVATION

EROSION CONTROL MEASURES

(a) Install check dams and sediment fences as necessary to minimize the entry of silt-laden water into streams or other water bodies.

(b) Seed and mulch all disturbed areas within 7 days of completion of the project.

LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the clearing limits shall be repaired as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(c) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live steams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting

Officer.

(d) Prevention of Oil Spills - If the Contractor maintains storage facilities for oil or oil products on Project

Area, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States.

(e) If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of

660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan.

Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

CLEANING OF EQUIPMENT

Cleaning of Off-Road Equipment used by the Contractor for contract work shall be conducted outside the boundary of any National Forest Service land prior to moving each piece of equipment onto the project. The

Contractor shall notify the Forest Service prior to moving each piece of equipment onto the project. Upon request from the Forest Service, arrangement will be made for Forest Service to inspect each piece of equipment prior to it being placed into service. The Contractor shall use cleaning methods necessary to ensure equipment is free of all attached mud, dirt, and plant parts. If noxious weeds are present at a project site, cleaning may also be required before moving between locations within the same project. These measures will assist to prevent the introduction/spread of the seeds of noxious weeds onto National Forest land. The

Contractor shall certify in writing, compliance with the above requirements. "Off-road Equipment" includes all machinery other than log trucks, chip vans, pickup trucks or vehicles used to transport personnel on a daily basis.

PLAN FOR WEATHER-CAUSED SUSPENSIONS OF WORK

The Contractor shall prepare a plan for weather-caused suspensions of work to ensure preservation of resources affected on the work site or sites. The plans shall be consistent with the requirements in the

LANDSCAPE PRESERVATION clause contained in this contract. The plan shall be submitted in writing to the Contracting Officer for review and, if acceptable, approval not later than 14 days after contract award. The plan shall distinguish between short-term shut-downs caused by intermittent weather activity and longer-term shut-downs associated with the advent of winter. If rejected by the Contracting

Officer, the Contractor shall revise the plan and re-submit it for consideration within three working days of verbal or written notification by the Contracting Officer. The Contractor shall take action consistent with the plan before suspending activity on the site(s). Acceptance of the plan by the Contracting Officer in no way waives any of the requirements of the LANDSCAPE PRESERVATION clause.

H. 3 USE OF PREMISES

(a) Forest Service Regulations for Use of Campground prohibits occupancy of developed recreation sites for other than primarily recreation purposes. One camp unit will be allowed at the project site for use by a watchman.

(b) A storage site will be permitted at a designated site within the project area. The Forest Service assumes no liability for materials stored within the storage site. The Contractor will be allowed to erect a temporary fence to secure materials and equipment, however, the fence shall be removed and the site restored prior to final acceptance of the contract.

(c) When the Contractor's operations require a temporary electrical power distribution system, the system shall comply with the National Electrical Code, applicable local codes and utility regulations. The

Contractor shall make all arrangements with the serving utility for temporary power and shall pay the serving utility for all applicable fees and power consumed.

(d) Potable water and sanitary facilities are not available for use during construction.

H. 4 SITE SPECIFIC SPECIAL PROJECT REQUIREMENTS

Site # 1 – Silver Creek Bridge Replacement, FR 85 & Site # 2 – Willame Creek Bridge Replacement, FR

4715.

Both left and right bridge footings/pillars will be removed from bankfull channel.

No new structures will be placed within bankfull channel.

Disturbed areas will be stabilized and restored to emulate immediate up and downstream site characteristics.

Sediment control measures will be implemented for all activities.

Contractor shall install Government Furnished ARRA project sign at the junction of Forest Road

47 and Forest Road 85. Contractor shall remove ARRA sign at end of project and return to Forest

Service.

DEFINITIONS AND ABBREVIATIONS

Wherever in these provisions, or in other contract documents, the following terms, or pronouns in place of them are used, the intent and meaning shall be interpreted as follows:

Building Limits - A line 5 feet outside foundations of the structure.

Calendar Day - Every day shown on the calendar, Sundays and holidays included.

Change Order - A written order issued by the Contracting Officer, to the Contractor documenting modifications within the scope of the contract.

Contract Amendment - A bilateral written supplemental agreement between the Government and the

Contractor.

Contract Time - The number of calendar days allowed by the contract for the completion of the work.

Contracting Officer's Representative (COR) - The duly authorized representative of the Contracting

Officer, responsible for on-site administration of the contract within the limits of specific written delegation of authority.

Contractor - The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract and acting directly or through their agent, employees, or subcontractors.

Equipment - All machinery and equipment, together with the necessary supplies for upkeep and maintenance, including tools and apparatus necessary for the proper construction and acceptable completion of the work.

Forest Supervisor - The person, or designated representative, responsible for administration of a National

Forest.

Inspector - The Government authorized representative designated in writing by the COR responsible for detailed inspections of contract performance, within delegation of authority.

Materials - Any substances specified for use in the construction of the project and its appurtenances.

Notice of Non-Compliance - Written notice issued detailing specific area(s) of Non-Compliance with contract requirements.

Original Contract Quantities - Those quantities shown in the Schedule of Items.

Right-of-way - A general term denoting land, property, or interest therein acquired for or devoted to a road or a construction site.

Schedule of Items - Schedule in the contract which contains a listing and description of construction items, quantities, units of measure, method of measurement, unit price and amount.

Specifications - A general term applied to all written directions and requirements pertaining to performance of the work.

Utility Services - Services such as electricity, gas, steam, water and sewerage.

Work Order - A written instruction directing the Contractor to fulfill contract requirements.

Reference to a specific standard or specification shall mean the latest edition or amendment in effect on date of invitation to bid.

––-–––– ACRONYMS –––––––

AA Aluminum Association

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete Institute

ADA Americans With Disabilities Act

AGC Associated General Contractors

AI Asphalt Institute

AISC American Institute of Steel Construction

AISI American Iron and Steel Institute

AITC American Institute of Timber Construction

ALSC American Lumber Standards Committee

ANSI American National Standards Institute

APA American Plywood Association

API American Petroleum Institute

ARTBA American Road and Transportation Builders Association

ASHRAE

American Society of Heating, Refrigerating & Air Conditioning

Engineers

ASME American Society of Mechanical Engineers

ASTM American Society for Testing and Material

ATCC American Type Culture Collection

AWPA American Wood Preservers Association

AWPB American Wood Preservers Bureau

AWS American Welding Society

AWWA American Water Works Association

CFR Code of Federal Regulations

CRSI Concrete Reinforcing Steel Institute

CS Commercial Standard issued by U.S. Department of Commerce

CSI Construction Specifications Institute

DEMA Diesel Engine Manufacturers Association

DOT U.S. Department of Transportation

FAR Federal Acquisition Regulations

FED.

SPEC. Federal Specifications

FS

FHWA Federal Highway Administration

FLH Federal Lands Highway (Federal Highway Administration)

FSS Federal Specifications and Standards

GSA General Services Administration

ICBO International Conference of Building Officials

ISSA International Slurry Surfacing Association

MIL Military Specifications

MSHA Mine Safety and Health Administration

MUTCD Manual on Uniform Traffic Control Devices

NBFU National Board of Fire Underwriters

NBS National Bureau of Standards

NEMA National Electrical Manufacturers Association

NESC National Electrical Safety Code

NFPA

(Fire) National Fire Protection Association

NFPA

(Forest) National Forest Products Association

NWMA National Woodwork Manufacturers Association

OSHA Occupational Safety and Health Act

PCA Portland Cement Association

PCI Prestressed Concrete Institute

PS Product Standard Issued by the U.S. Department of Commerce

PTI Post-Tensioning Institute

RIS Redwood Inspection Service

SAE Society of Automotive Engineers

SF Standard Form

SI International System of Units

SMACNA Sheet Metal & Air Conditioning Contractors National Association

SSPC Steel Structures Painting Council

UBC Uniform Building Code

UFC Uniform Fire Code

UL Underwriter's Laboratories, Inc.

UMC Uniform Mechanical Code

UPC Uniform Plumbing Code

USASI United States of America Standards Institute

WCLIB West Coast Lumber Inspection Bureau

WWPAA Western Wood Products Association

WWPI Western Wood Preservation Institute

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

52.202-1 Definitions (JUL 2004)

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (APR 1984)

52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)

52.203-7 Anti-Kickback Procedures (JUL 1995)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007)

52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (MAY 2008)

52.211-18 Variation in Estimated Quantity (APR 1984)

52.215-2 Audit and Records -- Negotiation (JUN 1999)

52.219-8 Utilization of Small Business Concerns (MAY 2004)

52.219-16 Liquidated Damages --Subcontracting Plan (JAN 1999) (Applicable if > $1 Million)

52.222-3 Convict Labor (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005)

52.222-6 Davis-Bacon Act (JUL 2005)

52.222-7 Withholding of Funds (FEB 1988)

52.222-8 Payrolls and Basic Records (FEB 1988)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (JUL 2005)

52.222-12 Contract Termination - Debarment (FEB 1988)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (FEB 1988)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and other

Eligible Veterans (SEP 2006)

52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998) http://www.usda.gov/procurement/policy/agar.html

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and other

Eligible Veterans (SEP 2006)

52.222-50 Combating Trafficking in Persons (SEP 2007)

52.223-5 Pollution Prevention and Right-to-Know Information (AUG 2003)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-14 Toxic Chemical Release Reporting (AUG 2003)

52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)

52.227-1 Authorization and Consent (DEC 2007)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)

52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)

52.228-2 Additional Bond Security (OCT 1997)

52.228-11 Pledges of Assets (FEB 1992)

52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995)

52.228-14 Irrevocable Letter of Credit (DEC 1999)

52.228-15 Performance and Payment Bonds – Construction (NOV 2006)

52.229-3 Federal, State, and Local Taxes (APR 2003)

52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002)

52.232-17 Interest (OCT 2008)

52.232-23 Assignment of Claims (JAN 1986)

52.232-27 Prompt Payment for Construction Contracts (OCT 2008)

52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003)

52.233-1 Disputes (JULY 2002)

52.233-3 Protest After Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by The Contractor (APR 1984)

52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 Other Contracts (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR

1984)

52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991)

52.236-14 Availability and Use of Utility Services (APR 1984)

52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-16 Quantity Surveys (APR 1984)

Alternate I (APR 1984)

52.236-17 Layout of Work (APR 1984)

52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate I (APR 1984)

52.236-26 Preconstruction Conference (FEB 1995)

52.242-13 Bankruptcy (JUL 1995)

52.243-4 Changes (AUG 1987)

52.244-6 Subcontracts for Commercial Items (MAR 2009)

52.245-1 Property Records (JUN 2007)

52.245-2 Government Property (Fixed-Price Contracts) (JUN 2007)

52.246-21 Warranty of Construction (MAR 1994)

52.248-3 Value Engineering – Construction (SEP 2006)

52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--Alternate I (SEP

1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)

452.236-72 Use of Premises (NOV 1996)

452.236-73 Archeological or Historic Sites (FEB 1988)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

52.204-7 Central Contractor Registration (APR 2008)

(a) Definitions. As used in this clause—

“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the

FAR at Subpart 32.11) for the same concern.

“Registered in the CCR database” means that—

(1) The Contractor has entered all mandatory information, including the DUNS number or the

DUNS+4 number, into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer

Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record

―Active‖. The Contractor will be required to provide consent for TIN validation to the

Government as a part of the CCR registration process.

(b)

(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ―DUNS‖ or ―DUNS+4‖ followed by the DUNS or DUNS+4 number that identifies the offeror‘s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the

United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.

The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting

Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government‘s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is http://fedgov.dnb.com/webform current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(g)

(1)

(i) If a Contractor has legally changed its business name, ―doing business as‖ name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day‘s written notification of its intention to:

(A) Change the name in the CCR database;

(B) Comply with the requirements of Subpart 42.12 of the FAR;

(C) Agree in writing to the timeline and procedures specified by the responsible

Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the

―Suspension of Payment‖ paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims

(see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the

CCR database. Information provided to the Contractor‘s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the ―Suspension of payment‖ paragraph of the EFT clause of this contract.

(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the

Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.

52.222-39 Notification Of Employee Rights Concerning Payment Of Union Dues Or Fees (Dec 2004)

(a) Definition. As used in this clause-

"United States" means the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.

http://www.ccr.gov/

(b) Except as provided in paragraph (e) of this clause, during the term of this contract, the Contractor shall post a notice, in the form of a poster, informing employees of their rights concerning union membership and payment of union dues and fees, in conspicuous places in and about all its plants and offices, including all places where notices to employees are customarily posted.