Work Description 041310.pdf
PDF 57 KB Posted
- Attached to
- RECOVERY - EVANS CREEK ORV AREA ROADS - MT. BAKER-SNOQUALMIE NATIONAL FOREST - WASHINGTON
- Solicitation number
- AG-0489-S-10-0332
About this file
Work Description with station-by-station work listing with associated payment items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_4.pdf | ||
| Amdt4_Continuation.docx | DOCX document | |
| Amendment_3.pdf | ||
| Amdt3_Continuation.docx | DOCX document | |
| Amendment_2.pdf | ||
| Amendment_1.pdf | ||
| Amdt1_Continuation.docx | DOCX document | |
| Offer Submittal Package.doc | DOC document | |
| Drawings1-21.pdf | ||
| RFP_Evans_Ck_ORV_Roads.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARRA - Evans Creek ORV
Base Project
FSR 7920
Mile Post Work Description Sub-Item Estimated Quantity
Begin Project at Junction with SR 165 0 Begin road reconditioning, 811(1) 2 MILES
Compaction method C
Typical D-3
(Other heavy equipment and grading)
All removed culverts are to be disposed of in observance of all federal regulations
0.0-2.0 Clean ditches and drainage structures 834F-1(15) 2 MILES
0.056 Begin Spot Surfacing 321(15)A 7182 Ton
0.196 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
0.387 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
0.525 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
0.661 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
0.744 Remove & Replace 18" CMP with 24" HDPE 5 60201A 36 L.F
0.939 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.067 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.13 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.217 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.274 Remove & Replace 18" CMP with 24" HDPE 10 60201A 36 L.F
1.34 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.392 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.442 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.541 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.578 Remove & Replace 18" CMP with 24" HDPE 15 60201A 36 L.F
1.579 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.622 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.65 Begin Underdrain for 380' 605(03) 380 LF
1.701 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.755 Remove & Replace 18" CMP with 24" HDPE 60201A 36 L.F
1.965 Remove & Replace 18" CMP with 24" HDPE 20 60201A 36 L.F
2.00 End Spot Surfacing 811(1)
6.1 Install Earth Mound and Boulder Barrier 650(04) 1 EA
2.15-6.1 Clean and recondition culverts 834F-1(5) 24 EA
FSR 7920 ORV Park Entrance
Mile Post Work Description Sub-Item Estimated Quantity 0 Begin Project 811(1) 0.15 MILES
Begin road reconditioning, compaction method C, Typical D-3
(Other heavy equipment and grading)
2.0-2.15 Clean ditches and drainage structures 834F-1(15) 0.15 MILES
0.012 Install Double Arm Gate 619(01) 1 EA
0.05 Clearing and Grubbing 173 1 LS
.01 to .15 Add rock to a depth of 6" compacted for parking lot 321(15)A 4700 CY
.01 to .15 Install concrete wheel backstops 553(01)A 27 EA
.01 to .15 Install rock road monuments for road division 251(14) 100 EA
.01 to .15 Excavate hard earth material for road/parking 807F-1(2) 1 EA
FSR 7920 ORV Day Use
Mile Post Work Description Sub-Item Estimated Quantity 2 Begin Project 811(1) 0.25 MILES
Begin road reconditioning, compaction method C, Typical D-3
(Other heavy equipment and grading)
2.15-2.4 Clean ditches and drainage structures 834F-1(15) 0.25 MILES
2.15 Clearing and Grubbing 173 1 LS
2.15 Install 36" HDPE 60201B 120 L.F
2.0-2.2 6" compacted rock for parking lot and road 321(15)A 2050 CY parking lots Install concrete wheel backstops 553(01)A 17 EA parking lots Install rock road monuments for road division 251(14) 75 EA
FSR 7930
Mile Post Work Description Sub-Item Estimated Quantity Begin Project 4.91 Miles
0.0-0.05 Begin road reconditioning, compaction method C, Typical D-3811(1) 0.05 MILES
(Other heavy equipment and grading)
0.0-0.05 Clean ditches and drainage structures 834F-1(15) 0.05 MILES
0.01 Remove and Replace 18" CMP with 24"HDPE 60201A 40 LF
0.1 Remove and Replace 18" CMP with 24"HDPE 60201A 40 LF
0.21 Remove and Replace 18" CMP with 24"HDPE 60201A 40 LF
FSR 7930110
Mile Post Work Description Sub-Item Estimated Quantity 0 Begin Project 811(1) 0.1 MILES
Begin road reconditioning, compaction method C, Typical D-3
(Other heavy equipment and grading) see map Remove 18" CMP 60201A 40 LF see map Remove 18" CMP 60201A 40 LF see map Remove 18" CMP 60201A 40 LF see map Remove 18" CMP 60201A 40 LF
Decommission work
Mile Post Road Work Description Sub-Item Estimated Quantity 7920610 Remove 18" CMP 833F-1(2) 12 EA
Cross Ditch Installation 833(6) 11 EA
Install Road Closure Device 60201A 1 EA
Embankment Pullback 836F-1(9) 500 LF
7920199 Remove 18" CMP 833F-1(2) 10 EA
Cross Ditch Installation 833(6) 1 EA
Install Road Closure Device 60201A 1 EA
7920280 Remove 18" CMP 833F-1(2) 4 EA
Cross Ditch Installation 833(6) 2 EA
Install Road Closure Device 60201A 1 EA
7920281 Remove 18" CMP 833F-1(2) 6 EA
Cross Ditch Installation 833(6) 2 EA
Install Road Closure Device 60201A 1 EA
7920300 Remove 18" CMP 833F-1(2) 1 EA
Cross Ditch Installation 833(6) 7 EA
Install Road Closure Device 60201A 1 EA
7920410 Remove 18" CMP 833F-1(2) 1 EA
Cross Ditch Installation 833(6) 7 EA
Install Road Closure Device 60201A 1 EA
3.2-4.2 7930 Remove 18" CMP 833F-1(2) 5 EA
Cross Ditch Installation 833(6) 13 EA
Install Road Closure Device 60201A 1 EA
7930310 Remove 18" CMP 833F-1(2) 8 EA
Cross Ditch Installation 833(6) 22 EA
Install Road Closure Device 60201A 1 EA
7930410 Remove 18" CMP 833F-1(2) 14 EA
Cross Ditch Installation 833(6) 8 EA
Install Road Closure Device 60201A 1 EA
7930510 Remove 18" CMP 833F-1(2) 5 EA
Cross Ditch Installation 833(6) 11 EA
Install Road Closure Device 60201A 1 EA see decomm Install Earth Mound and Boulder Barrier 650(04) 10 EA map (See Map)
Estimated Quantity