Sheet Total Sheets
ESTIMATED
MILE POST DESCRIPTION OF WORK PAY ITEM QUANTITY
Road # 9030, TALAPU LAKE TRAILHEAD
0.00 BEGIN PROJECT.
Jct. with I-90 off ramp and Road # 9030000
0.07 Existing arch culvert.
0.12 Spur road on right, flagged into Unit # 6.
0.34 Existing culvert with grated drop inlet, clean & reshape inlet 60710 1 Each
0.40 End of Pavement.
Begin road reconditioning,compaction method C, Typical D - 3. (Grading) 30322C 0.42 Miles
Remove existing culvert (Live stream) 20301 1 Each
Install 18-Inch corrugated Plastic Pipe. 60275A 34 Foot
Backfill bedding Material. 20950 4 CY
Crushed aggregate surfacing. 32203 4 CY
Place 1 & 2 CY of Class 2 riprap at inlet & outlet. 25101 3 CY
0.42 Existing 24-Inch culvert (Live stream)
Place Class 2 riprap at outlet. 25101 3 CY
0.45 Existing 24-Inch culvert (Live stream), reconstruct & lower ditchdam. 60710 1 Each
0.47 Install 36-Inch corrugated Plastic Pipe. 60275C 50 Foot
Backfill bedding Material. 20950 8 CY
Crushed aggregate surfacing. 32203 5 CY
Place 2 & 3 CY of Class 2 riprap at inlet & outlet. 25101 5 CY
0.49 Remove existing culvert. 20301 1 Each
Install 18-Inch corrugated Plastic Pipe. 60275A 30 Foot
Backfill bedding Material. 20950 4 CY
Crushed aggregate surfacing. 32203 4 CY
Place 1 & 2 CY of Class 2 riprap at inlet & outlet. 25101 3 CY
Construct outlet lead-off ditch, Typical D -1. 20419C 30 Foot
0.54 Remove existing culvert. 20301 1 Each
Install 18-Inch corrugated Plastic Pipe. 60275A 34 Foot
Backfill bedding Material. 20950 5 CY
Crushed aggregate surfacing. 32203 5 CY
Place 1 & 2 CY of Class 2 riprap at inlet & outlet. 25101 3 CY
0.58 Remove existing culvert. 20301 1 Each
Install 18-Inch corrugated Plastic Pipe. 60275A 34 Foot
Backfill bedding Material. 20950 5 CY
Crushed aggregate surfacing. 32203 4 CY
Place 1 & 2 CY of Class 2 riprap at inlet & outlet. 25101 3 CY Construct outlet lead-off ditch, Typical D -1. 20419C 15 Foot
WORK DESCRIPTION
ARRA DEFERRED MAINTENANCE - TINKHAM AREA ROAD REPAIRS
Sheet Total Sheets
ESTIMATED
MILE POST DESCRIPTION OF WORK PAY ITEM QUANTITY
Road # 9030, TALAPU LAKE TRAILHEAD (CONT.)
0.67 Remove existing culvert. 20301 1 Each
Install 18-Inch corrugated Plastic Pipe. 60275A 34 Foot
Backfill bedding Material. 20950 5 CY
Crushed aggregate surfacing. 32203 4 CY
Place 1 & 2 CY of Class 2 riprap at inlet & outlet. 25101 3 CY
0.72 Remove existing culvert. 20301 1 Each
Install 18-Inch corrugated Plastic Pipe. 60275A 34 Foot
Backfill bedding Material. 20950 5 CY
Crushed aggregate surfacing. 32203 4 CY
Place 1 & 2 CY of Class 2 riprap at inlet & outlet. 25101 3 CY
Construct outlet lead-off ditch, Typical D -1. 20419C 15 Foot
0.81 Construct 1D, 2W ditch on right, See Typical D. 20419A 55 Foot
0.82 Jct. with Road # 9031000 on the left.
End road reconditioning,compaction method C.
End constructing ditch on right.
END PROJECT
WORK DESCRIPTION
ARRA DEFERRED MAINTENANCE - TINKHAM AREA ROAD REPAIRS