8FEB10 Solicitation Coldwater Decking Repair.pdf
PDF 527 KB Posted
- Attached to
- RECOVERY-COLD WATER LAKE DECK RAIL REPLACEMENT. GIFFORD PINCHOT NF, COWLITZ COUNTY, WASHINGTON
- Solicitation number
- AG-0489-S-10-0164
About this file
Solicitation to include site visit information (section L-3).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1.docx | DOCX document | |
| ESR-1078.pdf | ||
| Rev1 Site Visit Questions.docx | DOCX document | |
| Site Visit Questions.docx | DOCX document | |
| Coldwater_Lake_Decking_Replacement.pdf | ||
| Attachment 1 Decking Scan.pdf | ||
| Attachment 2 Wage RatesWA48_dvb.htm | HTM file | |
| Attachment 3 Past Performance.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COLDWATER LAKE DECKING AND RAILING REPLACEMENT
GIFFORD PINCHOT NATIONAL FOREST
REQUEST FOR PROPOSAL
SOLICITATION NUMBER AG-0489-S-10-0164
U.S. Department of Agriculture
EROC-NW CONTRACTING OFFICE
16400 CHAMPION WAY
SANDY, OR 97055
CONSTRUCTION RFP AG-0489-S-10-0164
Gifford Pinchot National Forest
Coldwater Lake Decking and Railing Replacement
NOTICE TO OFFEROR:
This notice is a Total Small Business Set Aside.
PROPOSAL BOOKLET:
Offeror is responsible to verify the proposal booklet is complete. Offeror is also responsible for submitting all required forms and documents with their offer.
Applicable FAR provisions and clauses in this RFQ are incorporated by reference or full text. FAR provisions and clauses incorporated by reference can be accessed on the Internet at www.arnet.gov/far/. Offerors are strongly encouraged to review provisions and clauses referenced in this document before submitting a quotation.
CENTRAL CONTRACTOR REGISTRATION:
You must register in the Central Contract Registration (CCR) prior to award of this contract. Failure to register prior to contract award will require award to be offered to the next successful registered offeror. See FAR
Subpart 4.1103. Register online at www.ccr.gov or call toll free: (888) 227-2423.
INSTRUCTIONS TO OFFERORS
GENERAL:
By submission of its offer in accordance with the instructions provided in this Section, the offeror unconditionally assents to the terms and conditions in this solicitation document and in any attachments hereto.
DISCREPANCIES:
If an offeror believes the requirements in this solicitation contain an error, omission, or are otherwise unsound, the offeror shall immediately notify the Contracting officer (CO) in writing with supporting rationale. The offeror is reminded that the Government reserves the right to award this effort based on the initial quotation, as received, without discussions.
SUBMISSION OF OFFERS:
Offerors shall submit the following information by 4:00 Pacific Time, Tuesday, March 9, 2010:
SITE VISIT SCHEDULED IN SECTION L-3
Priced proposals shall include the following items:
1. Section A – SF1442 fill out blocks: 14,15,16,17,18, and 20. In doing so, the offeror accedes to the contract terms and conditions as written in the RFP. These sections constitute the model contract.
2. Block Section B – Supplies or Services and Prices/Costs, for all items. Any corrections, erasures, whiteout or other changes to your prices must be initialed by the offeror. Contractor must submit an offer on all items to be considered responsive.
3. Section J Attachment 3 - Past history relevant to this type of project.
4. Section K - Complete the necessary fill-ins and certifications in the Representations and Certifications.
The offeror shall submit only those pages that require a fill-in in the remaining solicitation package.
5. Bid Bond is required. Reference FAR Provision 52.228-1 for bid bond amount.
The packaging used in submitting the proposal must clearly identify the solicitation number and the date and local time specified in the solicitation for receipt of quotation. Offerors using commercial carriers should ensure that this information is marked on the outermost wrapper. Quotations should be submitted to the following address:
EROC-NW, CONTRACTING OFFICE
ATTN: AG-0489-S-10-0164
http://www.arnet.gov/far/ http://www.ccr.gov/
PART I - SCHEDULE OF ITEMS
SECTION B – SERVICES AND PRICES
(COLDWATER LAKE DECKING REPLACEMENT)
Mount St Helens National Volcanic Monument
Cowlitz County
B- 1 - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
06305(1)
Platform #1
Lump
Sum 1
06305(2)
Platform #2
06305(3)
Platform #3
06305(4)
Boardwalk
Total $______ $_______
B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-
Price Construction Contracts, shall not be in addition to the contract price.
PART I – THE SCHEDULE
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 Scope of Contract
Coldwater Lake Decking and Railing Replacement:
Furnish all labor, equipment, and materials to accomplish the work under this contract which includes, but is not limited to the following items: replace all of the tread decking and side railings on three view platforms and one boardwalk. All structures are built out over Coldwater Lake. Three of the structures have built in bench seating; replacement of the bench seating material is to be included in this contract.
Proper disposal of used material is to be included as part of this contract.
The magnitude of construction for this acquisition is between $100,000 and $250,000.
The Government intends to award a firm fixed price contract.
C-2 Project Location
From Interstate 5, take exit 49 Castle Rock WA to Highway 504. Proceed Easterly along Highway 504 to
Coldwater Lake Recreation Area.
C-3 SCHEDULE
60 days after Notice to Proceed
C-4 AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C-5 Statement of Work
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1 Summary
This contract is to replace all of the tread decking and side railings on three view platforms and one boardwalk. All structures are built out over Coldwater Lake. Three of the structures have built in bench seating; replacement of the bench seating material is to be included in this contract. The Boardwalk is
420 ft in length and 6,208 sq ft in area, Platform #1 is 400 sq ft, Platform #2 is 250 sq ft, and Platform
#3 is 403 sq ft, for a total of 7,261 sq ft. Proper disposal of used material is to be included as part of this contract.
1.2 Location
This project is in Washington State on the Gifford Pinchot National Forest, within the Mount St. Helens
National Volcanic Monument. It is located at the Coldwater Lake Recreation Area, which is off milepost
44.5 on State Route 504.
1.3 GENERAL SITE CONDITIONS AND WEATHER.
The elevation of the site is approximately 2,500 feet above mean sea level. The construction site experiences heavy snowfall and extremely cold temperatures, with snow on the ground typically from mid-November through March. These structures are located along the paved ―Birth of a Lake‖ trail and can be accessed from the picnic area.
1.4 USE OF PREMISES
The Contractor shall have limited use of premises for construction operations, including use of project site, during the construction period. Contractor's use of premises is limited to the access trail and to the structures to be re-decked, with a small staging area for materials. The Contractor shall not impede the public‘s use of the picnic area or the public restrooms. Electricity is not available.
Contractor shall at all times conduct his operations in a manner to ensure the least inconvenience to the public and employees. Trail and structure closures will be permitted, when required, upon written approval of the Contracting Officer (CO).
Confine storage of materials to areas as approved by the CO.
Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
Provide temporary barriers to protect existing trees and plants and root zones.
Do not remove, injure, or destroy trees or other plants without prior approval. Consult with CO and remove agreed-on roots and branches that interfere with construction.
Do not fasten ropes, cables, or guys to existing trees.
Do not work off of the developed trail.
1.5 MEALS AND LODGING
Meals and lodging are available in the City of Castle Rock, WA within 44.5 miles of the construction site.
1.6 construction sequence
There is no specified construction sequence or season for this project.
1.7 Field verification
Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.8 permits
No permits required.
END OF SECTION 01100
SECTION 01025
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 summary
The intent of this section is to explain, in general; what is and what is not included in a bid item, and method of measurements and basis of payment for work items listed in the Bid Item Schedule.
Work:
Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the
Contractor.
Payment:
Payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.
Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 DETERMINATION OF QUANTITIES
The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
Quantity Measurements:
1. The contractor shall compute the quantities for periodic progress payments; the Contracting
Officer shall compute the quantities for the final payment based on measurements taken by the
Contractor.
2. All Contractor measurements are subject to verification.
The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
PART 2 - METHOD OF MEASUREMENT
The following methods of measurement for determining final payment is designated on the Schedule of
Items for each pay item:
LUMP SUM QUANTITIES (LSQ)
These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
END OF SECTION 01025
SECTION 01732
SELECTIVE DEMOLITION
PART 1 - GENERAL
SUMMARY
This Section includes demolition and removal of selected site elements, as well as procedures for selective demolition operations. All demolished materials shall become the contractor's property and shall be removed from project site. The contractor shall comply with hauling and disposal regulations of authorities having jurisdiction.
DEFINITIONS
Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
PART 2 – PRODUCTS
REPAIR MATERIALS
Use repair materials whose installed performance equals or surpasses that of existing materials.
PART 3 – EXECUTION
SELECTIVE DEMOLITION
General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.
Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition.
PATCHING AND REPAIRS
General: Promptly repair damage to adjacent construction caused by selective demolition operations.
Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
DISPOSAL OF DEMOLISHED MATERIALS
Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 01732
SECTION 06305
PRESSURE TREATED WOOD
PART 1 – GENERAL
1.1 PAYMENT
Payment will be considered full compensation for all materials, labor, and equipment to replace tread decking, side railings, and bench seating, as well as proper disposal of demolished materials.
Pay Item Number Description Pay Unit
Quantity
06305(1) Platform #1 Lump Sum
06305(2) Platform #2 Lump Sum
06305(3) Platform #3 Lump Sum
06305(4) Boardwalk Lump
PART 2 – PRODUCTS
2.1 LUMBER
Lumber shall be of a species and grade for which allowable unit stresses are set forth in the current edition of the "National Design Specification for Wood Construction," by the National Forest Products
Association (NFPA), and shall bear the grade mark of, or have a certificate of inspection issued by, a lumber grading or inspection bureau or agency recognized as being competent.
Decking lumber shall be Douglas-fir No. 2 or hemlock fir No. 2, 3‖X 12‖ pressure treated (non-incised), with a ½‖ spacing for expansion.
Railing lumber shall be 2‖X 8‖ GRN-TK-S1S2E Cedar
Bench seating lumber shall be 2‖X 6‖ GRN-TK-S1S2E Cedar
2.2 PRESERVATIVE TREATMENT
All decking lumber shall be pressure treated in accordance with treating and drying requirements specified in the American Wood Preserver Bureau's AWPB-FDN Standard and meet the penetration and retention requirements of that standard.
It shall bear the AWPB Quality Mark of an approved inspection agency, which maintains inspection of the products as described in the AWPB standard.
All decking lumber will be treated with sealant on all end cuts.
All cedar railing material shall be treated with a preservative/sealant after installation.
2.3 FASTENERS
A. Fasteners used in wood decking and railings must be corrosion resistant.
Use heavy duty screw type fasteners such as FastenMater-Timberlok brand or equivalent.
1. 6 inch for decking material.
2. 4 inch for railing material.
3. 3 ½ inch for bench seating material
All drive heads run flush with decking and railing material
Electro-galvanized or mechanically plated fasteners will not be allowed.
PART 3 – EXECUTION
Cull any unsuitable lumber, such as excessively warped pieces.
END OF SECTION 06305
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
SECTION E--INSPECTION AND ACCEPTANCE
E-1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
E-2 52.246-12 Inspection of Construction (AUG 1996)
E-3 FINAL CLEANUP
Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all Contractor's rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.
http://www.usda.gov/procurement/policy/agar.html
SECTION F--DELIVERIES OR PERFORMANCE
F-1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
F-2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than July 1, 2010. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK
SECTION H--SPECIAL CONTRACT REQUIREMENTS
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I-1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
I-2 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (JUL 2004)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (APR 1984)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7 Anti-Kickback Procedures (JUL 1995)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007)
52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (MAY 2008)
52.211-18 Variation in Estimated Quantity (APR 1984)
52.219-6 Notice of Total Small Business Set-Aside (JUN 2003)
52.219-8 Utilization of Small Business Concerns (MAY 2004)
52.222-3 Convict Labor (June 2003)
52.222-6 Davis-Bacon Act (JUL 2005)
52.222-7 Withholding of Funds (FEB 1988)
52.222-8 Payrolls and Basic Records (FEB 1988)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (JUL 2005)
52.222-12 Contract Termination - Debarment (FEB 1988)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (FEB 1988)
52.222-20 Walsh-Healy Public Contracts Act (DEC 1996)
52.222-21 Prohibition of Segregated Facilities (Feb 1999)
52.222-26 Equal Opportunity (Mar 2007)
52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)
52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998)
52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and
Other Eligible Veterans (Sep 2006)
52.222-50 Combating Trafficking in Persons (SEP 2007)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction
Contracts (DEC 2007)
52.223-6 Drug-Free Workplace (MAY 2001) (Applicable if contract is awarded to an individual)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)
52.228-2 Additional Bond Security (OCT 1997)
52.228-11 Pledges of Assets (FEB 1992)
52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995)
52.228-14 Irrevocable Letter of Credit (DEC 1999)
52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002)
52.232-23 Assignment of Claims (JAN 1986)
52.232-27 Prompt Payment for Construction Contracts (OCT 2008)
52.232-33 Payment by Electronic Funds Transfer—Central Contractor Registration (Oct. 2003)
52.233-1 Disputes (JUL 2002)
52.233-3 Protest After Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-5 Material and Workmanship (APR 1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984)
52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991)
52.236-15 Schedules for Construction Contracts (APR 1984)
52.244-6 Subcontracts for Commercial Items (MAR 2009)
52.246-21 Warranty of Construction (MAR 1994)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short From) (APR 1984)
52.249-10 Default (Fixed-Price Construction) (APR 1984)
52.253-1 Computer Generated Forms (JAN 1991)
I-3 AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)
452.236-72 Use of Premises (NOV 1996)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
I-4 52.204-7 Central Contractor Registration (APR 2008)
(a) Definitions. As used in this clause—
“Central Contractor Registration (CCR) database” means the primary Government repository for
Contractor information required for the conduct of business with the Government.
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and
Bradstreet, Inc. (D&B) to identify unique business entities.
“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds
Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
“Registered in the CCR database” means that—
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the
Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record ―Active‖. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
(b)
(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ―DUNS‖ or ―DUNS+4‖ followed by the DUNS or DUNS+4 number that identifies the offeror‘s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number—
(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and
Bradstreet office. The offeror should indicate that it is an offeror for a U.S.
Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business name.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
http://fedgov.dnb.com/webform
(iii) Company physical street address, city, state and Zip Code.
(iv) Company mailing address, city, state and Zip Code (if separate from physical).
(v) Company telephone number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the
Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering.
Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government‘s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g)
(1)
(i) If a Contractor has legally changed its business name, ―doing business as‖ name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart
42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day‘s written notification of its intention to:
(A) Change the name in the CCR database;
(B) Comply with the requirements of Subpart 42.12 of the FAR;
(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the
Contractor indicated in the contract will be considered to be incorrect information within the meaning of the ―Suspension of Payment‖ paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor‘s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the ―Suspension of payment‖ paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.
I-5 52.228-15 -- Performance and Payment Bonds – Construction (Nov 2006)
(a) Definitions. As used in this clause --
―Original contract price‖ means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $100,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance Bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the
Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid
Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier‘s check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of Treasury
Financial Management Service
Surety Bond Branch
3700 East West Highway, Room 6F01
Hyattsville, MD 20782
Or via the internet at http://www.fms.treas.gov/c570/ .
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
(End of Clause)
I-6 FAR 52.228-1 Bid Guarantee (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $100,000.00, whichever is less.
http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=http://www.fms.treas.gov/c570/
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
I-7 FAR 52.252-6 Authorized Deviations in Clauses
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of ―(DEVIATION)‖ after the date of the clause.
(b) The use in this solicitation or contract of any (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of ―(DEVIATION)‖ after the name of the regulation.
ARRA CLAUSES
I-8 52.215-2 -- Audit and Records -- Negotiation (Mar 2009) (Alt I)
(a) As used in this clause, ―records‖ includes books, documents, accounting procedures and practices, and other data, regardless of type and regardless of whether such items are in written form, in the form of computer data, or in any other form.
(b) Examination of costs. If this is a cost-reimbursement, incentive, time-and-materials, labor-hour, or price redeterminable contract, or any combination of these, the Contractor shall maintain and the
Contracting Officer, or an authorized representative of the Contracting Officer, shall have the right to examine and audit all records and other evidence sufficient to reflect properly all costs claimed to have been incurred or anticipated to be incurred directly or indirectly in performance of this contract. This right of examination shall include inspection at all reasonable times of the Contractor‘s plants, or parts of them, engaged in performing the contract.
(c) Cost or pricing data. If the Contractor has been required to submit cost or pricing data in connection with any pricing action relating to this contract, the Contracting Officer, or an authorized representative of the Contracting Officer, in order to evaluate the accuracy, completeness, and currency of the cost or pricing data, shall have the right to examine and audit all of the Contractor‘s records, including computations and projections, related to --
(1) The proposal for the contract, subcontract, or modification;
(2) The discussions conducted on the proposal(s), including those related to negotiating;
(3) Pricing of the contract, subcontract, or modification; or
(4) Performance of the contract, subcontract or modification.
(d) Comptroller General—
(1) The Comptroller General of the United States, an appropriate Inspector General appointed under section 3 or 8G of the Inspector General Act of 1978 (5 U.S.C. App.), or an authorized representative of either of the foregoing officials, shall have access to and the right to—
(i) Examine any of the Contractor‘s or any subcontractor‘s records that pertain to and involve transactions relating to this contract or a subcontract hereunder; and
(ii) Interview any officer or employee regarding such transactions.
(2) This paragraph may not be construed to require the Contractor or subcontractor to create or maintain any record that the Contractor or subcontractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(e) Reports. If the Contractor is required to furnish cost, funding, or performance reports, the
Contracting Officer or an authorized representative of the Contracting Officer shall have the right to examine and audit the supporting records and materials, for the purpose of evaluating --
(1) The effectiveness of the Contractor‘s policies and procedures to produce data compatible with the objectives of these reports; and
(2) The data reported.
(f) Availability. The Contractor shall make available at its office at all reasonable times the records, materials, and other evidence described in paragraphs (a), (b), (c), (d), and (e) of this clause, for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in Subpart 4.7, Contractor Records Retention, of the Federal Acquisition
Regulation (FAR), or for any longer period required by statute or by other clauses of this contract. In addition --
(1) If this contract is completely or partially terminated, the Contractor shall make available the records relating to the work terminated until 3 years after any resulting final termination settlement; and
(2) The Contractor shall make available records relating to appeals under the Disputes clause or to litigation or the settlement of claims arising under or relating to this contract until such appeals, litigation, or claims are finally resolved.
(g)(1) Except as provided in paragraph (g)(2) of this clause, the Contractor shall insert a clause containing all the terms of this clause, including this paragraph (g), in all subcontracts under this contract. The clause may be altered only as necessary to identify properly the contracting parties and the
Contracting Officer under the Government prime contract.
(2) The authority of the Inspector General under paragraph (d)(1)(ii) of this clause does not flow down to subcontracts.
(End of Clause)
I-9 52.203-15 – Whistleblower Protections Under the American Recovery and Reinvestment
Act of 2009 (Mar 2009)
(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111–5).
(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.
(End of clause)
I-10 52.204-11 – American Recovery and Reinvestment Act—Reporting Requirements (Mar
2009)
(a) Definitions. As used in this clause—
“Contract,‖ as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.
“First-tier subcontract” means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.
“Jobs created” means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United
States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ‗‗full-time equivalent‘‘ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
“Jobs retained” means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ‗‗full-time equivalent‘‘ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
“Total compensation” means the cash and noncash dollar value earned by the executive during the contractor‘s past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised
2004) (FAS 123R), Shared Based Payments.
(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.
(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.
(5) Above-market earnings on deferred compensation which is not tax-qualified.
(6) Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.
(b) This contract requires the contractor to provide products and/or services that are funded under the
American Recovery and Reinvestment Act of 2009 (Recovery Act). Section 1512(c) of the Recovery
Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.
(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to June 30, 2009, are due no later than July 10, 2009. Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.
(d) The Contractor shall report the following information, using the online reporting tool available at.
https://www.federalreporting.gov/federalreporting/home.do
(1) The Government contract and order number, as applicable.
(2) The amount of Recovery Act funds invoiced by the contractor for the reporting period. A cumulative amount from all the reports submitted for this action will be maintained by the government‘s on-line reporting tool.
(3) A list of all significant services performed or supplies delivered, including construction, for which the contractor invoiced in this calendar quarter.
(4) Program or project title, if any.
(5) A description of the overall purpose and expected outcomes or results of the contract, including significant deliverables and, if appropriate, associated units of measure.
(6) An assessment of the contractor‘s progress towards the completion of the overall purpose and expected outcomes or results of the contract (i.e., not started, less than 50 percent completed, completed 50 percent or more, or fully completed). This covers the contract (or portion thereof) funded by the Recovery Act.
(7) A narrative description of the employment impact of work funded by the Recovery
Act. This narrative should be cumulative for each calendar quarter and only address the impact on the contractor‘s workforce. At a minimum, the contractor shall provide— https://www.federalreporting.gov/federalreporting/home.do
(i) A brief description of the types of jobs created and jobs retained in the United
States and outlying areas (see definition in FAR 2.101). This description may rely on job titles, broader labor categories, or the contractor‘s existing practice for describing jobs as long as the terms used are widely understood and describe the general nature of the work; and
(ii) An estimate of the number of jobs created and jobs retained by the prime contractor, in the United States and outlying areas. A job cannot be reported as both created and retained.
(8) Names and total compensation of each of the five most highly compensated officers of the Contractor for the calendar year in which the contract is awarded if—
(i) In the Contractor‘s preceding fiscal year, the Contractor received—
(A) 80 percent or more of its annual gross revenues from Federal contracts
(and subcontracts), loans, grants (and subgrants) and cooperative agreements; and
(B) $25,000,000 or more in annual gross revenues from Federal contracts
(and subcontracts), loans, grants (and subgrants) and cooperative agreements; and
(ii) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the
Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.
(9) For subcontracts valued at less than $25,000 or any subcontracts awarded to an individual, or subcontracts awarded to a subcontractor that in the previous tax year had gross income under $300,000, the Contractor shall only report the aggregate number of such first tier subcontracts awarded in the quarter and their aggregate total dollar amount.
(10) For any first-tier subcontract funded in whole or in part under the Recovery Act, that is over $25,000 and not subject to reporting under paragraph 9, the contractor shall require the subcontractor to provide the information described in (i), (ix), (x), and (xi) below to the contractor for the purposes of the quarterly report. The contractor shall advise the subcontractor that the information will be made available to the public as required by section 1512 of the Recovery Act. The contractor shall provide detailed information on these first-tier subcontracts as follows:
(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor‘s parent company, if the subcontractor has a parent company.
(ii) Name of the subcontractor.
(iii) Amount of the subcontract award.
(iv) Date of the subcontract award.
(v) The applicable North American Industry Classification System (NAICS) code.
(vi) Funding agency.
(vii) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.
(viii) Subcontract number (the contract number assigned by the prime contractor).
(ix) Subcontractor‘s physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.
(x) Subcontract primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.
(xi) Names and total compensation of each of the subcontractor‘s five most highly compensated officers, for the calendar year in which the subcontract is awarded if—
(A) In the subcontractor‘s preceding fiscal year, the subcontractor received—
(l) 80 percent or more of its annual gross revenues in Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and
(2) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and
(B) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C.
78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.
(End of clause)
CONSTRUCTION CLAUSES
I-11 52.225-21 -- Required Use of American Iron, Steel, and Other Manufactured Goods--Buy
American Act--Construction Materials (Mar 2009)
(a) Definitions. As used in this clause—
“Construction material” means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States; or
(2) A construction material manufactured in the United States.
“Foreign construction material” means a construction material other than a domestic construction material.
“Manufactured construction material” means any construction material that is not unmanufactured construction material.
“Steel” means an alloy that includes at least 50 percent iron, between .02 and 2 percent carbon, and may include other elements.
“United States” means the 50 States, the District of Columbia, and outlying areas.
“Unmanufactured construction material” means raw material brought to the construction site for incorporation into the building or work that has not been—
(1) Processed into a specific form and shape; or
(2) Combined with other raw material to create a material that has different properties than the properties of the individual raw materials.
(b) Domestic preference.
(1) This clause implements—
(i) Section 1605 of the American Recovery and Reinvestment Act of 2009 (Recovery Act) (Pub. L. 111-
5), by requiring, unless an exception applies, that all iron, steel, and other manufactured goods used as construction material in the project are produced in the United States; and
(ii) The Buy American Act (41 U.S.C. 10a-10d) by providing a preference for unmanufactured domestic construction material.
(2) The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraph (b)(3) and (b)(4) of this clause.
(3) This requirement does not apply to the construction material or components listed by the
Government as follows:
NONE
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable.
(A) The cost of domestic iron, steel, or other manufactured goods used as construction material is unreasonable when the cumulative cost of such material will increase the cost of the contract by more than 25 percent;
(B) The cost of unmanufactured construction material is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available quantities and of a satisfactory quality; or
(iii) The application of the restriction of section 1605 of the Recovery Act or the Buy American Act to a particular construction material would be inconsistent with the public interest.
(c) Request for determination of inapplicability of Section 1605 of the Recovery Act or the Buy
American Act.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including—