RECOVERY-EVERGREEN ROAD REPAIR AND MAINTENANCE
Solicitation number
AG-0489-S-10-0142
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
VicinityMap.pdf PDF
Copy To Submit.pdf PDF
bid-guarantee-sf24.pdf PDF
Davis-Bacon Wage Rates.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

�"��
�
������������
� �����!"#��$%!&
�!$'&�������
�"�����
�����+�,������
�,�00�-���-00�,��������&.
���1���$��!'��#!��!$'*!�$��$!$��
*�23!4��.�$�56!7"���!���$!7

�4&4�"��� �!$1�� 8�������

�9����,�,*
���,��

�: ,�8 �

��,���
-���;,��,<=�����
����$��!7=��$��>��$�!�����!$��$�=!��!6!�;�-�<���.��-��?��-���� -����
�"!�7�#!��6!@>�2>�'26�

)����$"�$�A� ����"!�� �� B�����$ C���D��� !$' C-��D���2

������7����!���$��B��$1���6�'6$'������"!7736��$�����"#�������$���
8�"�$���!���$=��1�!"

�����./��0123#4203�5.#66�$/781�9/3:03;#14/��

#=#3>? 10284/�20�9304//>������./�9/3:03;#14/�9/380>�85� ;#1>#203@� 1/7028#$6/���&�//�------------------------------------------------�'

#���/#6/>�0::/35�81�038781#6�#1>

85�102�3/AB83/>�85?�$���1�0::/3�7B#3#12//�������

4���66�0::/35�#3/�5B$C/42�20�2./�&�'�=03D�3/AB83/;/125?�#1>�&�'�02./3�930E858015�#1>�46#B5/5�81403903#2/>�81�2./�5068482#2801�81�:B66�2/(2�03�$@�3/:/3/14/�������

:�2.85�85�#�5/#6/>�$8>�5068482#2801?�0::/35�=866�$/�9B$6846@�09/1/>�#2�2.#2�28;/����/#6/>�/1E/609/5�4012#81817�0::/35�5.#66�$/�

;#3D/>�20�5.0=�2./�0::/303F5�1#;/�#1>�#>>3/55?�2./�5068482#2801�1B;$/3?�#1>�2./�>#2/�#1>�28;/�0::/35�#3/�>B/�

>�� ::/35�930E8>817�6/55�2.#1

�� �-� 4#6/1>#3�>#@5�#1>�40;96/2/�82�=82.81�---------------- ---------------- 4#6/1>#3�>#@5�#:2/3�3/4/8E817

�������)G)�G���G ���

4098/5�20�9/3:03;�2./�=03D�3/AB83/>�#3/�>B/�#2�2./�96#4/�59/48:8/>�81�

2/;���$@�------------- �------------------- �$� ���604#6�28;/

4#6/1>#3�>#@5�:03��0E/31;/12�#44/92#14/�#:2/3�2./�>#2/�0::/35�#3/�>B/�=866�102�$/�40158>/3/>�#1>�=866�$/�3/C/42/>�������-----------------�

�"������&�/E���G��' �3/5438$/>�$@����

�'�� �� �G�&>'

�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>

$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������

�%(��
�)��
�������
���
����� �������������������
���

�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�

0��#������ ��2�

������������
H������

������� �)4��

3�2���%����

�����"��� � ��������
�������������
��" ��������������
�������������"���

����������3 4��� '5 '6 �--����7��

3�2���%���

�����������������������
H������

������� )4������ �$���� �� �4������

���:, �2 �:*

����2�� #��0 ��2�����

�)��������� )�&4' ������������ &4'

�"������&��*���G��'����, ��$��$6�'222

����������
����"������
������

�,�00�- ���-00�,� �

� ��,8 � ,�8 *,��� *�2 3!4��.�$�56!7"�� �!���$!7

�4&4�"����!$1��8�������
8�7����&0��/��/-���
8�7����&E��!���$��'�0��*�
��8,

8������� �,�)

�F:F�*��9�,�)
�8�������
�F:F�*��9%,��-����

�30 8����$!���$

���,8�
=,��,�8*,���
=��'6��/���������'�0:---
=��'6��/�������8�����#���$0
���������/9�)9%,:�.�8�.���.3�8)�.�,
�������)G)�G���G�)����
����
�"� ��&�G��'

�901503/>�$@����

PART I - SCHEDULE OF ITEMS

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

RECOVERY-EVERGREEN ROAD REPAIR AND MAINTENANCE

Mt. Baker-Snoqualmie National Forest

Skykomish Ranger District

B. 1 SCHEDULE OF ITEMS

NOTE: If Offeror does not intend to charge for an item, a price of “0” or “NO COST” should be shown. The Offeror must price all items. Only prices to the nearest cent will be accepted

ITEM

NO. DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101 Mobilization

Lump Sum 1

15702 Silt fence

Foot 310 $________ $________

20401 Roadway excavation, equipment compaction method

Cubic Yard 90 $________ $________

20701A Earthwork geotextile type IV-A

Square Yard 120 $________ $________

25101 Placed riprap, class III with welded wire mats

Cubic Yard 290 $________ $________

25104A Keyed riprap, class III

Cubic Yard 250 $________ $________

25104B Keyed riprap, class V

Cubic Yard 140 $________ $________

25503 Select granular backfill

Cubic Yard 34 $________ $________

30801 Roadway aggregate, no deflection compaction method

Cubic Yard 95 $________ $________

60602 Corrugated Metal Spillway assembly

Foot 20 $________ $________

62201A Dump Truck with minimum 10 CY capacity

Hour 100 $________ $________

62201B Hydraulic Mounted Excavator, 1.0 CY cap. Min. and thumb

Hour 100 $________ $________

62201C Smooth Drum Vibratory Compactor

Hour 2 $________ $________

62503 Seeding, dry method

Lump Sum 1 $________ $________

62901 Erosion Control mat type 5.C

Square Yard 333 $________ $________

63501 Temporary Traffic Control Lump Sum 1

63351 ARRA Sign (Includes post) Lump Sum 1 $________ $________

Total for all items on FSR 6554 from M.P. 0.86 to 3.75 TOTAL $______________

RECOVERY-EVERGREEN ROAD REPAIR AND MAINTENANCE

SCHEDULE OF ITEMS FOR BIDS

Name and address of offeror: _____________________________________________________________

Name and title of person authorized to sign offer:____________________________________________

Signature: ____________________________________________ Date: _________________________

TIN: __________________________ DUNS: ________________________

B. 2 NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price

Construction Contracts, shall not be in addition to the contract price. Include bond payments under

151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

Work includes but is not limited to the following: Roadway Excavation and Embankment with material haul to designated waste site, Riprap placement, Slope Stabilization with Geotextile, Road Reconditioning, Aggregate Surface Placement, Seeding and Mulching, Traffic control and Sign installation.

C.2 PROJECT LOCATION

Project is located 45 miles east of Monroe,WA on Forest Road 6554 in Snohomish County, Mount

Baker Snoqualmie Forest. The begins at MP 0.86 and ends at MP 3.75. The project is located in T 27 N, R 12 E Sections 5 and 8 and T 28 N, R 12 E Section 31.

a) Existing Conditions:

The indications of existing conditions on the drawings and specifications are the result of on-site facilities inspections, and reviews of incomplete construction and maintenance records.

b) Weather Conditions:

Weather conditions suitable for ground excavation are normally expected in May through October. Rain, sometimes heavy, is normal throughout the winter, with periods of light to moderate snowfall. Night freezing is common throughout the winter and several periods of weeklong freezes are likely.

c) Operating Season: Inclusive dates during which operations are permissible.

Activity Start Date End Date Restrictions Construction Season 06/01 09/30 Hand Tools 06/01 09/30 Power Tools / 2 Chainsaws 06/01 09/30 Machinery / Car Traffic 06/01 09/30 Heavy Machinery 06/01 09/30

d) Noise Limitation:

Power Tools/2 Chainsaws - any power tools with noise output is no more than two operating chainsaws.

Machinery/Car Traffic - any machinery with noise output is limited to normal vehicular traffic at site (e.g. small excavator/backhoe).

Helicopter/Heavy Machinery - any machinery with noise output is greater than normal vehicular traffic at site.

C.3 FAR 52.210-3 AVAILABILITY OF SPECIFICATIONS OR PRODUCT DESCRIPTIONS NOT

LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS AND STANDARDS (APR

1984)

Specifications or product descriptions cited herein, but not attached to this solicitation nor listed in the General Services Administration Index of Federal Specifications and Standards (GSAIFSS), may be obtained from: Specification

Address

Standard Specifications For Construction of Roads and Bridges on Federal Highway Projects

FP-03

U.S. Customary Units

Superintendent of Documents U.S. Government Printing Office Washington, D.C. 20402 866-512-1800 http://bookstore.gpo.gov/ http://www.wfl.fhwa.dot.gov/design/specs/f p03.htm

ASTM Standards American Society for Testing and Materials P.O. Box C700 100 Bar Harbor Drive West Conshohocken, PA 19428-2959

(610) 832-9585 http://www.astm.org

AASHTO Standards American Association of State Highway and Transportation Officials 444 North Capitol Street, NW Suite 249 Washington, D.C., 20001

(206) 624- 5800 http://www.aashto.org

C.4 CONTRACT TIME

120 Calendar days.

C.5 SPECIFICATIONS

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03) and Forest Service Supplemental Specifications noted herein.

These Standard Specification can be viewed and printed from the following website:

http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm

Attached Supplemental specifications are in Section J.1

C.6 MATERIAL CERTIFICATIONS, INVOICES, AND TESTING REPORTS

Materials associated with the following Pay Items will require certifications and/or testing reports submitted to the Contracting Officer Representative.

Item 15702 Silt Fence Item 25101 Class 3 riprap placed Item 25104A Class 3 riprap keyed Item 25104B Class 5 riprap

Item 30801 Aggregate Surfacing Item 60602 24-inch HDPE downpipe Item 62500 Seed and Weed Free Straw Item 63551 Signs Refer to the Forest Service Specifications for required certification and reports for Pay Items mentioned above.

General Guidelines for Submittals:

Submittals are required by their corresponding specifications (basic reference & detailed requirement).

Work requiring submittals shall not begin until submittals have been approved.

Submittals shall include the following:

Date and Revision Dates.

Project Name and Contract Number.

Names of Contractor, Subcontractor, Supplier, and Manufacturers.

Field Dimensions and Relation to Adjacent Structures.

Contractor's stamp, initialed or signed, certifying review of submittal, verification of field measurement and compliance with contract documents.

Samples:

Physical samples shall illustrate materials, equipment, or workmanship, and establish standards by which completed work shall be judged. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of product or material, with integrally related parts and devices.

Manufacturer's requirements:

Supply manufacturer's catalog sheets or brochures with diagrams, schedules, or performance charts.

Illustrations shall be clearly marked to identify pertinent materials or models, dimensions, and clearances required. Supplement standard drawings to provide information unique to this project.

Approval or Rejection Time Allowance:

Submittals will be reviewed and either approved or rejected within 14 calendar days of their receipt by the Contracting Officer or COR

C.7 AMERICAN RECOVERY AND REINVESTMENT ACT

Sign Requirements and Specifications:

See Attached “Sign Layout Details and Specifications” in contract plans.

Use Sign Design For “Low Speed Roads”.

C.8 MATERIAL SOURCES

The Government will provide the following items of material sources to the Contractor for use in the performance of his contract.

Item No. Description Quantity Source Location

Item 25101 Class 3 riprap placed 290 Beckler Pit Item 25104A Class 3 riprap keyed 250 Beckler Pit Item 25104B Class 5 riprap 140 Beckler Pit

C.9 CONSTRUCTION WORK DAYS AND HOURS

No work is allowed on Federal Holidays.

C.10 WILDLIFE RESTRICTIONS (INCLUDING FISHERIES)

For fish and wildlife considerations, the following restrictions are applicable to this contract:

All work associated with in stream channels shall be done between July 15 and August 15.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 31st , 2010. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE

A. The Contracting Officer will designate an individual as Contracting Officer's Representative (COR) at time of award. The name will be on the purchase order or designated in a letter/form.

B. The Contracting Officer’s Representative is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by a proper contractual documents executed by the Contracting Officer prior to completion of the contract.

C. The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual assignments which were issued by the Contracting Officer’s Representative provided they do not affect the delivery schedule or performance period stated in the contract.)

D. On all matters that pertain to the contract terms the Contractor must communicate with the

Contracting Officer. Whenever, in the opinion of the Contractor, the Contracting Officer’s Representative requests effort outside the scope of the contract, the Contractor should so advise the Contracting Officer’s Representative. If the Contracting Officer’s Representative persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

E. The Contracting Officer’s Representative's major duties and responsibilities are contained in the Forest Service Handbook of Contract Administration. The Contracting Officer’s Representative is delegated full authority under this contract except for the following actions which are reserved for the Contracting Officer:

1. Approve Change Orders and Modifications

2. Take action to terminate the contract for default or Government convenience.

3. Make contract adjustments under the Differing Site Conditions clause.

4. Grant extensions of contract time.

5. Approve assignment of claims.

6. Make final decisions under the Disputes clause.

7. Make final acceptance under the contract.

8. Make final decisions under the Suspension of Work clause.

9. Make equitable adjustments.

10. Authorize change in amount of Payment Retention.

11. Approve subcontractors.

12. Approve payments with deductions or final payment.

13. Approve use and possession prior to completion.

14. Enforce the warranty provisions.

G.2 NOTIFICATION OF SUBCONTRACTING

The Contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. The written notification shall include as a minimum:

A. The name, address and telephone number of the subcontractor.

B. The date upon which the subcontract was entered into and its duration.

C. A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate.

D. Documentation of the subcontractor's representative authority.

Subcontracting any portion of the contract shall not relieve the Prime Contractor of any responsibility under this contract. Any subcontract agreement shall contain all terms and conditions of the prime contract.

G.3 PUBLIC OFFICIALS NOT PERSONALLY LIABLE

There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them, by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.

G.4 PRE-WORK CONFERENCE

The Contractor shall meet with the Government to discuss contract terms and work performance requirements, Work Progress Schedule, and Fire Prevention and Suppression Plans. Contractor designated representative or foreman (whomever the Contractor will have on the site) shall be present at the prework conference. The time and place will be scheduled and held within approximately 10 days after the date of contract award. The conference will be held at: Darrington Ranger Station, WA.

G.5 PROJECT INSPECTORS

The COR may designate project inspectors to secure compliance with the terms and conditions of the contract.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 FAR 52.236-4 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Forest Personnel.

Weather conditions: Normal.

Elevation of this project averages 1000’ Transportation facilities: Road access is good Other Physical Data: None.

H.2 WA USE TAX CLAUSE FOR CONSTRUCTION CONTRACTS

The Contractor is liable for Use Tax, in accordance with State of Washington Code 458-20-173, Subparagraph (8), which states: “Thus the use tax applies to all property provided by the federal Government to the Contractor for installation or inclusion in the contract work as well as to all Government provided tooling”.

H.3 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

H.4 USE OF PREMISES

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless provided otherwise, the Contractor shall: (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State, and local regulations.

H.5 ARCHAEOLOGICAL OR HISTORIC SITES (AGAR 452.236-73) (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

H.6 AGAR 452.236-74 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION

(NOV 1996)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or near rivers, streams, and impoundments; or into natural or manmade channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H.7 RIGHTS IN AND USE OF MATERIALS

(a) The Contractors, with the written approval of the Contracting Officer, may use on the project suitable stone, gravel, and sand or other material found in the excavation. Payment will be made both for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. The Contractor shall replace without additional compensation sufficient suitable materials to complete the portion of work which was originally contemplated to be constructed with such material.

(b) Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to reimburse the Contractor for the cost of their production.

H.8 STORAGE AND STOCKPILING OF MATERIALS

Material shall be stored to assure the preservation of quantity and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment.

All storage sites provided by the Forest Service shall be restored at Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered land.

H.9 AGAR 452.236-77 EMERGENCY RESPONSE (NOV 1996)

(a) Contractor's Responsibility for Fighting Fire. (1) The Contractor, under the provision of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish, all fires on the work site other than those fires in use as a part of the work. (2) The contractor may be held liable for all damages and for all costs incurred by the Government for labor subsistence, equipment, supplies, and transportation deemed necessary to suppress a fire set or caused by the Contractor or the Contractor's agent or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergency. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.

H.10 LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products onsite, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states.

Servicing of all equipment shall be done only in the area approved by the Contracting Officer.

If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

The Contractor will be required to make reasonable attempts to preserve the scenic and natural environment along this construction project.

(c) Trash and Refuse - Contractor shall remove all of his own trash and refuse from the contract area. Material to be removed includes, but is not limited to; used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper, garbage, etc. This material must be removed to a State, County, or Municipality-designated solid waste disposal area.

H.11 CONTROL OF NOXIOUS WEEDS--CLEANING OF EQUIPMENT (March 2004)

To prevent the introduction and control the spread of seeds of noxious weeds onto and around National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. When the Contractor is working in an area that has been identified as a noxious weed infestation area, the Contractor shall ensure equipment is cleaned of weed seeds prior to moving to another work area on the Forest. The Contractor shall employ whatever cleaning methods necessary to ensure compliance with the terms of this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forestland, unless otherwise agreed in writing. Notification will include identifying the location of the equipment's most recent operations.

The Contractor shall certify, in writing, compliance with the terms of this clause prior to each start-up of operations. For the purposes of this clause, "equipment" includes all motorized equipment operated off system roads, transport vehicles, and all motorized equipment used in road maintenance. Not included are log trucks, chip vans, pickup trucks, cars, or other vehicles used to daily transport personnel.

H.12 FIRE PROTECTION REQUIREMENTS

The following fire requirements are attached in Section J and are applicable:

Fire Protection and Suppression, R6-FS-6300-52 (5/97)

Additional Fire Precautionary Measures - Tank Truck, R6-FS-6300-53 (5/89)

Additional Fire Precautionary Measures - Communications, R6-FS-6300-54 (5/89)

H.13 WDFW-USFS INTERIM MOU PROVISIONS (January 2005)

A copy of this MOU must be on site at all times when work is conducted under the provisions of Appendix A. Copy of the WDFW-USFS will be made available at the prework.

The following provisions are applicable to this contract:

GENERAL PROVISIONS APPLICABLE TO ALL APPENDIX A PROJECTS

Timing

1. Freshwater hydraulic projects shall normally be implemented only during the work periods outlined in Appendix D. Other timing will be allowed on a site-specific basis if the Forest Service fish biologist and WDFW Area Habitat Biologist agree that implementing the activity outside of the normal period would be unlikely to cause negative impacts to fish. Any agreements to modify the work periods in Appendix D for specific projects or specific sites shall be documented by WDFW.

2. Those portions of hydraulic project work that occur outside or above the bankfull channel and have little or no potential to negatively affect fish or fish habitat are not subject to the work periods specified in Appendix D. Examples of such work include replacing bridge decking, constructing a bridge superstructure after footings are in place, and building up the fill of a culvert that is in place. These projects are still bound the other provisions in Appendix A. The Forest Service shall notify the appropriate WDFW Regional Habitat Program Manager prior to implementing work on these hydraulic projects outside the work periods specified in Appendix D.

3. Hydraulic projects conducted in intermittent non-fish-bearing streams that are dry during the proposed work are not subject to the work periods specified in Appendix D unless USFS fish biologist determine the activities are likely to negatively affect fish life, in which case the work periods specified in Appendix D apply.

4. Hydraulic projects conducted in wetted non-fish-bearing streams that are greater than ¼ mile from fish-bearing water are not subject to the work periods specified in Appendix D unless USFS fish biologist determine the activities are likely to negatively affect fish life, in which case the work periods specified in Appendix D apply.

Fish Protection

5. Any pump used for diverting water from a fish-bearing waterbody shall be equipped with a fish guard to prevent passage of fish into the pump. The pump intake shall be screened with 3/32 inch or smaller mesh. Screen maintenance shall be adequate to prevent injury or entrapment to juvenile fish and shall remain in place whenever water is withdrawn from the water body through the pump intake.

6. Fish within construction sites that will be dewatered or isolated from the main water body will be captured and safely moved from the job site. Fish capture and transportation equipment shall be available on the job site during all in water activities.

7. If at any time, as a result of project activities, a fish kill occurs, fish are observed in distress, or water quality problems develop that may present a threat to fish life, the Forest Service shall immediately notify the appropriate WDFW Regional Habitat Program Manager. Outside of business hours, notification shall be made to the Washington State Emergency Management Division of the Department of Ecology at 1-800-258-5990.

Erosion and Wastewater Control

8. Alteration or disturbance of the bed, banks, and vegetation of waterbodies shall be minimized and limited to that necessary to construct the project.

9. Erosion prevention and control methods shall be used as necessary during and immediately after project implementation to minimize loss or displacement of soils and to prevent delivery of sediment into waterbody. These may include, but are not limited to, operational techniques, straw bales, silt fencing, erosion control blankets, temporary sediment ponds, and/or immediate mulching of exposed areas. Disturbed ground with the potential to deliver sediment into waterbodies shall be revegetated or protected from surface erosion by seeding, mulching, other methods prior to the fall rainy season.

10. After project completion, disturbed streambanks and lakeshores shall be revegetated with site-appropriate vegetation to maintain soil stability and provide shade and future sources of large wood.

11. Wastewater from project activities shall be routed to an area outside the bankfull channel to allow removal of fine sediment and other contaminants prior to infiltrating back into waterbodies.

Heavy Equipment

12. The use of heavy equipment within the bankfull channel in streams and below the ordinary high water line in lakes is discouraged. If such work is necessary, operation of heavy equipment in these areas shall be minimized.

13. Accumulations of soil or debris shall be removed from drive mechanisms (wheels, tires, tracks, etc.) and undercarriage of all heavy equipment prior to its working within the bankfull channel in streams or below the ordinary high water line in lakes.

14. To prevent contamination, equipment used around waterbodies shall be free of external petroleum-based products. Equipment shall be checked daily for leaks and any necessary repairs shall be completed prior to commencing work activities. All machinery fueling and maintenance involving petroleum products shall occur at a sufficient distance from stream channels, waterbodies, or wetlands to prevent delivery of potential contaminants. Spill containment equipment and material shall be on site.

Concrete and Treated Wood

15. Fresh concrete, concrete by-products, or other chemical contaminants shall not be allowed to enter waterbodies. Structures containing concrete shall be sufficiently cured to prevent leaching prior to contact with the waterbody.

16. Treated wood used for hydraulic projects shall meet or exceed the standards established in the most current edition of "Best Management Practices For the Use of Treated Wood in Aquatic Environments” developed by the Western Wood Preservers Institute. At the time of the signing of this MOU, the most current version is the July 1996 edition.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

52.202-1 Definitions (JUL 2004) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (JUL 1995) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007) 52.203-13 Contractor Code of Business Ethics and Conduct. (DEC 2008) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000) 52.204-10 Reporting Subcontract Awards. (SEP 2007) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEP 2006) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.219-14 Limitations on Subcontracting (DEC 1996) 52.219-16 Liquidated Damages --Subcontracting Plan (JAN 1999) (Applicable if > $1 Million) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (FEB 1988) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and other

Eligible Veterans (SEP 2006) 52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998)

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2006)

52.222-50 Combating Trafficking in Persons (FEB 2009) 52.223-5 Pollution Prevention and Right-to-Know Information (AUG 2003) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-14 Toxic Chemical Release Reporting (AUG 2003) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (SEP 2009) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.228-15 Performance and Payment Bonds – Construction (NOV 2006) 52.229-3 Federal, State, and Local Taxes (APR 2003) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-17 Interest (OCT 2008) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JULY 2002) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by The Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate II (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUNE 2007) 52.245-1 Government Property (JUN 2007) 52.246-21 Warranty of Construction (MAR 1994)

Alternate I (APR 1984) 52.248-3 Value Engineering – Construction (SEP 2006) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

I.2 FAR 52.204-7 CENTRAL CONTRACTOR REGISTRATION (APR 2008)

(a) Definitions. As used in this clause—

“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

“Registered in the CCR database” means that—

(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b)

(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.

The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering.

Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(g)

(1)

(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:

(A) Change the name in the CCR database;

(B) Comply with the requirements of Subpart 42.12 of the FAR;

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.

(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.

I.3 FAR 52.228-1 BID GUARANTEE (SEP 1996) (Applicable over $100,000)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $ 1,000.000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.4 FAR 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least 25 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

I.5 AGAR 452.228-70 ALTERNATIVE FORMS OF SECURITY (NOV 1996)

If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.

I.6 ORDER OF PRECEDENCE-CONSTRUCTION

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The Schedule (excluding the specifications)

(2) Representations and Other Instructions

(3) Contract Clauses

(4) Other Documents, Exhibits, and Attachments

(5) The Specifications

(6) Drawings

ARRA CONTRACT CLAUSES

T he following American Recovery and Reinvestment Act Clauses are added for this contract. Contractors are hereby notified of the reporting requirements as specified herein.

I.7 FAR 52.204-11 AMERICAN RECOVERY AND REINVESTMENT ACT-REPORTING

REQUIREMENTS (MAR 2009)

(a) Definitions. As used in this clause— “Contract”, as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.

“First-tier subcontract” means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.

“Jobs created” means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101).

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .