Special_Project_Spec.pdf

PDF 24 KB Posted

Attached to
Highwood-Hoover Trails Phase II Federal contract opportunity
Solicitation number
AG-03K0-S-09-0023
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

Special Project Specs

View the file

Other files for this federal contract opportunity

Other files attached to Highwood-Hoover Trails Phase II, newest first.
File Type Posted
Experience_Questionnaire.doc DOC document
Survey_Log.pdf PDF
SF24_Bid_Bond.pdf PDF
AG-03K0-S-09-0023 Highwood OHV Grant Trails and Hoover Complex Phase II Trails.pdf PDF
J-1HighwoodHooverDrawings.pdf PDF
Construction_Log.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROJECT SPECIFICATION

Section 904 – Maintenance for Traffic

904.01 General – Add the following:

Contractor’s access to the project over existing national forest system roads and trails to the project will be limited to the modes of transportation allowed in the current Lewis and Clark National

Forest Travel Plan. Two-wheeled motorized vehicles are authorized for use by contractor for access on the Highwood Trails and on Trails 734 & 736 & a portion of Trail No. 732 in the Hoover complex -

ATVs are prohibited. Trail 732 from its junction with Trail 736 and westward into North Fork Hoover

Creek drainage is closed to motorized use. Trail excavators and motorized wheelbarrows are not considered access vehicles and are allowed & encouraged for construction. Trail excavators and construction equipment that can be operated within the confines of the trailbed width are authorized.

SPS 904-1 (06/06)

Section 907 – Quality Assurance and Quantity Measurement

Description

907.01 Work – Add the following:

Work will also include providing noxious weed control.

Construction

907.02 Certification and Measurements – Add the following:

To mitigate the anticipated impacts of spreading noxious weed species, the following precautions will be used:

All equipment and vehicles to be used at the job site will be steam cleaned and free of noxious weeds and their seeds prior to entrance onto Federal lands. The restriction will include equipment and vehicles intended for off-road as well as on-road use, whether they are owned, leased, or borrowed by the Contractor or any subcontractor.

Cleaning will consist of the removal of all dirt, grease, debris and materials that may harbor noxious weeds and their seeds. Cleaning will occur off Federal lands.

Equipment, materials and vehicles will be visually inspected by the Engineer or other designated

Forest Service official at a location agreed to by the Engineer and the Contractor in advance of delivery to the job site. Delivery is expected to proceed directly to the job site.

Equipment that leaves the job site will need to be re-inspected before being allowed to return.

SPS 907 – 1 (06/06)

Section 908 – Staking, Flagging, and Cleanup

908.02 General – First paragraph, add the following:

In addition to the provided survey staked P Line (preliminary line), Forest Service will also provide construction slope stakes for Switchbacks. Contractor will be responsible for preserving the original location of Switchback construction stakes, by off-setting or agreed methods, until final acceptance of the construction.

SPS 908-1 (06/06)

Section 912 – Excavation and Embankment

912.03 Use and Disposal of Excavated Material – Add the following:

When transporting material for construction of Switchbacks, move material longitudinally on the trail so as to not destroy vegetation outside of clearing limits and inside the radius of the Switchback.

SPS 912-1 (06/06)

Section 914 – Switchbacks

914.03 Excavation and Embankment – Add the following:

Contractor will notify Contracting Officer’s Representative (COR) 2 days in advance of when construction of Switchbacks will occur. Construction of Switchbacks will not begin until excavation and hauling equipment is on site and the COR or their designated representative is present.

SPS 914 – 1 (06/09)

Section 954 – Obliteration of Abandoned Trailways

Description

954.01 Work – Delete this paragraph and replace with the following:

This work consists of obliteration of abandoned trail by constructing drainage structures and placing logs, brush, rock & debris.

954.03 Trail Closure – Delete this paragraph and replace with the following:

Obliterate trailways by placing logs, branches, rocks & debris in the trailway. Place obliteration materials to a thickness and density sufficient to conceal the trailway below and so that raindrops cannot directly impact the soil surface. When there is an eroded channel, place logs of 6 inches minimum diameter longitudinally in the bottom of the eroded channel and in contact with the soil as practically attainable. Use materials from nearby, but do not cut live trees closer than 30 feet from the trailway.

954.04 Drainage Structures – Delete this paragraph and replace with the following:

Construct Native Log Waterbars or Rock Waterbars at intervals of approximately 50 feet on the abandoned trailway. Construct waterbars in accordance with Section 922, except that native logs do not have to be peeled. Use the type of waterbar that best fits the situation & materials available. Check dams are not appropriate – water must be directed off the trailway.

954.05 through 954.08 – Delete these subsections.

Measurement

954.09 Method – Add the following:

Measurement for Obliteration is for all of the work described in this Section including native log and rock waterbars.

954-1 (06/06)