OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
AG-0398-S-10-0007
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
5-21-10
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
381681
6. PROJECT NO.
7. ISSUED BY CODE 0398 8. ADDRESS OFFER TO
Gallatin National Forest ATTN: Gary B. Stephens P.O. Box 130 Bozeman, MT 59771
Same as Item #7
9. FOR INFORMATION
CALL:
A. NAME
Gary B. Stephens – Contracting Peter G. Werner – Mining Engineer
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 406-587-6774 406-587-6962
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
McLaren Adit Closure, Road Reclamation and Revegtation Gallatin National Forest - Gardiner Ranger District
1. SF1442, SF1442 Back
2. Part I The Schedule, Section B: Supplies or Services and Prices/Costs
3. Section C: Project Description, Specifications and Statement of Work
4. Section E: Inspection and Acceptance
5. Section F: Deliveries or Performance
6. Section G: Contract Administration Data
7. Section H: Special Contract Requirements
8. Part II Contract Clauses, Section I: Contract Clauses
9. Part III List of Documents, Exhibits, and Other Attachments, Section J: List of Documents, Exhibits, and Other Attachments
10. Part IV Representations and Instructions, Section K: Representations, Certifications, and Other Statements of Bidders
11. Section L: Instructions, Conditions, and Notice to Offerors
12. Section M: Evaluation Factors for Award
COMPETED UNDER FAR 19.10, SMALL BUSINESS COMPETITIVENESS DEMONSTRATION
PROGRAM – NAICS CODE 237310
Price Range The Government's estimate is between $500,000 and $1,000,000.
11. The Contractor shall begin performance within 10 calendar days and complete it within (see Section F) calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable.
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 3 copies to perform the work required are due at the place specified in Item 8 by 2:00PM (hour) local time 6-21-10 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
CONSTRUCTION RFP SOL NO: AG-0398-S-10-0007
GALLATIN NAT’L FOREST – GARDINER RANGER DISTRICT
MCLAREN ADIT CLOSURE, ROAD RECLAMATION & REVEGETATION
PART I - THE SCHEDULE
SECTION B - SERVICES AND PRICES
McLaren Adit Closure, Road Reclamation and Revegetation
New World Mining District Response and Restoration Project
Gallatin and Custer National Forests
Park County, Montana
B-1 Schedule of Items (3 pgs)
Item No. Description Method of
Meas. Unit Estimated Quantity
Unit Price TOTAL
202 (06) Debris Disposal AQ ton 5
203 (02)
Excavation, placement Method 2 (Miller Creek & Lulu Pass Roads) DQ cy 456
(02)b
Excavation, placement Method 2 (Portal Area and Adit Clean-out) DQ cy 230
(02)c
Excavation, placement Method 2 (Infiltration Basin) DQ cy 145
(22)a
Type I Drain Dips without armor AQ ea 13
(22)b
Type I Drain Dips with armor AQ ea 28
(22)c
Type II Drain Dips with armor AQ ea 182
(23)a Armored Spillway AQ ft 1,605 (23)b Armored Fords AQ ft 380 (24)a
In-slope Road with ditch without armor AQ ft 4,330
(24)b
In-slope Road with armored ditch AQ ft 2,270
203 (25)
Excavation, placement Method 1 (Daisy Pass Cut and Fill Recl.) AQ sy 7,920
(19)b
Provide, Install, Maintain and Remove Temporary Erosion Control Measures (Daisy Pass Cut and Fill Recl.) LSQ ls 1
206(08) Adit Dewatering LSQ ls 1
Meas. Unit Estimated Quantity
Unit Price TOTAL
(01)a
Treatment of existing roadway, Method A AQ sy 8,279
(01)b
Treatment of existing roadway, Method D AQ sy 556
210 (05) Road Obstruction, place boulders AQ ea 28
(14)b
Culvert Aprons, Class I, Method A AQ ea 1
304 (23)
Surface Course Aggregate, grading Size 2, Compaction A AQ cy 1,634
304 (24)
Subgrade Aggregate, grading Class 1 Riprap, Compaction A AQ cy 164
306 (05)
Reconditioning of Roadbed, compaction Method A AQ sy 35,906
306 (06) J-Hole Turnaround AQ ea 3
311 (01) Define Roadway with local slash and logs AQ ft 5,175
601 (01) Mobilization LSQ ls 1
602 (02) Concrete Drain Pad, Method C LSQ ls 1
(01)a
24-inch dia., CMP, 0.079-inch thickness steel, Method C AQ ft 68
(01)b
36-inch dia., CMP, 0.109-inch thickness steel, Method C AQ ft 26
(01)c
70-inch x 40-inch CMP, Method C AQ ft 25
603B (01)a
18-inch dia., HDPE plastic pipe, TYPE S, Method C AQ ft 116
603B (01)b
24-inch dia., HDPE plastic pipe, TYPE S, Method C AQ ft 28
603B (01)c
30-inch dia., HDPE plastic pipe, TYPE S, Method C AQ ft 30
603B (01)d
8-inch dia, HDPE perforated plastic pipe, Method C AQ ft 72
603B (01)e
8-inch dia, HDPE plastic pipe, Method C AQ ft 585
624(02) Furnish and Place Topsoil AQ cy 150
Meas. Unit Estimated Quantity
Unit Price TOTAL
625 (01) Seeding, Method A (without mulch) AQ ac 15
625 (03)
Mulch, supplemental application (organic matter) AQ ton 171
625 (07) Erosion Control Blanket AQ sy 67,068
661 (01) Calcium Carbonate Amendment AQ ton 188
702 (02) Drop Inlet Bedding Gravel AQ cy 241
705 (01) Portal Plug Coarse Rock - Class 2 Riprap AQ cy 30
714 (01) Type IV-A Geotextile AQ sy 735
(01)a
Water Seal 70-inch x 40-inch CMP (Bentonite) LSQ ls 1
(01)b Drop Inlet Strucutre LSQ ls 1
TOTAL = $____________
DESIGNATED METHOD OF MEASUREMENT PAY UNIT ABBREVIATIONS
DQ Designated Quantities ls lump sum
AQ Actual Quantities ea each LSQ Lump Sum Quantities ac acre sy square yard cy cubic yard ft foot ton English ton = 2000 lbs
PART I - THE SCHEDULE
SECTION C - DESCRIPTION AND SPECIFICATIONS
C - 1 - PROJECT DESCRIPTION AND LOCATION
(a) Description of Work. Furnish all labor, materials, equipment, and supervision for the Road
Reclamation, Revegetation, and McLaren Adit Closure Project within the New World Mining District (District). Work includes the following:
McLaren Adit Closure – install concrete dam, adit drainage collection piping, infiltration basin, revegetate with project seed mix, and provide and install erosion control mat, Daisy Pass Road Cut and Fill Reclamation – regrade cut and fill slopes, provide and amend soil with compost, revegetate with project seed mix, and provide and install erosion control mat.
Miscellaneous County and Forest Service Road Improvements and Reclamation – road reclamation, culvert installation, drain dip installation, recondition existing roads, and other road improvements. Roads include Alice E, Black Warrior, Bull of the Woods, Crown Butte, Daisy Pass, Fisher Mountain, Fisher Mountain Admin, Henderson Mountain, Lake Abundance, Lower County Connector, Lower Crown Butte, Lulu Pass, McLaren View, Miller Creek, Scotch Bonnet, Sheep Mountain, South Henderson Mountain, Upper County Connector, and Upper Lady of the Lake Trailhead.
This work requires handling of mine waste in the McLaren Adit area which contains metals that are listed as hazardous substances under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) 42 U.S.C. 9601 and 9602. The following are the highest concentrations of certain metals measured in waste material (milligrams per kilogram) at the mine sites:
Arsenic (As)
Cadmium (Cd) Copper (Cu) Lead (Pb) Zinc (Zn)
Highest Concentration (milligrams/kilogra m)
105 24 995 204 150
The CONTRACTOR shall provide written documentation that all on site personnel engaged in the Work have received the Occupational Safety and Health Administration 40 hour Hazardous Waste Operations and Emergency Response (HAZWOPER) Training required under 29 CFR 1910.120.
The CONTRACTOR assumes full and sole responsibility for the means and methods necessary to complete the work in accordance with the project specifications. Conventional construction equipment and techniques may not be appropriate for this project, and the CONTRACTOR shall consider these factors when preparing the bid and planning and scheduling the work.
(b) Project Location. The New World Mining District is located north of Cooke City, Montana in the Beartooth Mountains. The District falls within the boundaries of the Gallatin and Custer National Forests and abuts Yellowstone National Park’s northeast corner. The Absaroka-Beartooth Wilderness Area bounds the District to the north and east. The District lies entirely within Park County, Montana.
The work sites to be addressed by this CONTRACT lie at elevations ranging from about 8,350 feet to 9,500 feet above mean sea level.
The project sites can be reached from two access points off U.S. Highway 212 about 0.6 and 1.5 miles east of Cooke City. A map showing the locations of the work is included in the DRAWINGS. Cooke City is accessible by paved roads from the east over Highway 212 and from the west through Yellowstone Park.
Access to Cooke City through Yellowstone National Park may be permitted, depending on vehicle weight and size limitations, with the following restrictions:
• a commercial permit is required
• special restrictions apply to commercial loads
• special restrictions apply if hauling petroleum products
• special restrictions apply to hauling other hazardous materials
Specific inquiries concerning hauling materials and equipment through the park should be directed to:
Tammy Wert Visitor Services Office P. O. Box 168 Yellowstone National Park, WY 82190 tel: (307) 344-2115
FAX: (307) 344-2104
(c) Price Range. Between $500,000 and $1,000,000
(d) Start Work. It is estimated that work will begin on July 1, 2010 and continue until the contract ending date of September 30, 2010. All work under this contract must be completed before the contract ending date.
(e) Period of Performance. [see Part I, Section F, Clause 52.211-10]
(f) Noxious Weed Control. In order to prevent the potential spread of noxious weeds, the CONTRACTOR is required to furnish weed-free equipment. The CONTRACTOR’S equipment shall be cleaned to remove all dirt and plant parts and material that may carry noxious weed seeds into the construction area. Only construction equipment so cleaned and inspected by the Forest Service will be allowed to operate on the project. All subsequent move-ins shall be treated the same as the initial move-
in. Prior to move-in, the CONTRACTOR shall make equipment available for Forest Service inspection at an agreed location. "Construction equipment" does not include personal vehicles or support equipment that remains on the main travel route. Provide the Contracting Officer (CO) with at least 48 hours advance notification when the equipment is ready for inspection.
(g) Maintenance of Roads. Lulu Pass and Daisy Pass Roads are County roads that must be open at all times in a condition that standard passenger vehicles must be able to reasonably pass. The Upper County Connector Road is a Forest Road that also must be left open to passenger vehicles. To insure safe and reasonable access on these roads, the CONTRACTOR shall periodically water, apply road base, as necessary, and blade these roads for maintenance and dust suppression. In addition, all other roads where construction will occur are high clearance roads that must remain passable for high clearance and all-terrain vehicle (ATV) traffic. Road maintenance shall be conducted to the satisfaction of the CO and in such a manner to facilitate vehicular traffic and to minimize excessive construction disturbance to all roads affected by required work and all roads used by construction traffic.
Water for road maintenance is available from Fisher Creek at the Fisher Creek Bridge (MP 2.28). The use at the Fisher Creek bridge water source is limited to a maximum pumping rate of 200 gallons/min with a maximum seasonal use of 156,800 ft3 (3.6 acre-feet). Road maintenance is incidental to other work items.
(h) Control of Work. Contractor shall be responsible for laying out road work using the road logs provided in this contract. The Forest Service will mark the boundaries for the areas to be treated in the McLaren Adit area and along the Daisy Pass Road. The CONTRACTOR shall develop and make all detailed surveys needed for construction of the work involved. The CONTRACTOR shall be held responsible for the preservation of all primary and other control. If control markings are destroyed or disturbed by the CONTRACTOR, the cost for replacement will be deducted from the payment for the work.
The CONTRACTOR shall stake all staging areas, culvert locations, disturbance limits, and all other features of the work and receive approval from the CO before proceeding with the work on these items.
Staking and surveying by the CONTRACTOR is considered incidental to other work items and no separate measurement or payment for this item will be made
(i) Rock Sources. Other than government provided rock described in Section C-2, rock for riprap and drainage gravel shall be furnished by the CONTRACTOR.
(j) Restoration by CONTRACTOR. All areas disturbed by the CONTRACTOR’S operations such as, but not limited to, access roads, staging areas, stockpiles, haul roads, loading operations, and disposal operations, shall be restored by grading to the original contours, seeding, fertilizing, and installing erosion control mat. During the course of the work, the CONTRACTOR shall periodically or as directed by the CO remove and dispose of all surplus construction materials and debris and keep the project area and public right-of-way reasonably clean. Upon completion of the work, the CONTRACTOR shall remove all temporary construction facilities, debris, and unused materials, leaving the project sites in a neat and clean condition. All debris shall be disposed off-site in a state-licensed landfill.
C - 2 - GOVERNMENT-FURNISHED PROPERTY.
The Forest Service will provide the following Government-furnished property for use on this project:
1. Boulders for blocking reclaimed roads are available at the end of FR 3215 (Gold Dust Access
Road) at the ford crossing of Fisher Creek. This road is currently reclaimed to permit ATV use only (six feet wide travel width). The CONTRACTOR may choose to improve access in this area but must restore to existing conditions when finished. Additional boulders are found at select locations throughout the work area, and may be used at the direction of the CO. If boulders are removed for use under the terms of this contract, all disturbances associated with their removal will be reclaimed to the satisfaction of the CO. Reclamation of disturbed areas associated with boulder selection is incidental to the work.
2. CONTRACTOR may choose to incorporate stockpiled materials located at the quarry site as SHOW ON THE DRAWINGS (Sheet 1) into CONTRACTOR supplied materials. Material and estimated quantities are described in Table C-2. The CO shall approve all quarry materials prior to project use.
TABLE C-2
QUARRY MATERIALS
MATERIAL ESTIMATED QUANITIY (CY)
10-inch Minus Material 3,500
½” Washed Chips 1000
½” Chips 3000
C - 3 - SUBMITTALS
The CONTRACTOR shall submit three (3) copies of the following plans 14 days prior to beginning work. In addition, the CONTRACTOR shall supply the CO all required submittals for each Item at least 14 days prior to commencing work on the corresponding item.
(a) Health and Safety Plan (S-001).
The CONTRACTOR shall submit to the CO a Health and Safety Plan before work commences.
Minimum items to be included in the safety plan are:
1) Proposed Equipment
2) Proposed Competent Person and Qualifications
3) Proposed Traffic Control Plan (including position of warning signs)
4) Proposed Communication System
5) Proposed Personnel Protective Equipment (PPE)
6) First Aid Station
7) Employee Training (40-hour HAZWOPER with 8-hour refresher a minimum)
In accordance with OSHA (29 CFR 1926), the CONTRACTOR is responsible for the safety of all work activities at the sites and shall ensure that proper safety requirements are followed. The CONTRACTOR shall be aware that areas of the site are located on steep slopes with minimum working clearances and that construction activities may require special safety precautions.
(b) Traffic Control Plan (S-002).
All roads included in this contract are used by the general public. All roads must remain open to traffic throughout the contract. The CONTRACTOR may request specific roads to be closed for limited times with the approval of the CO. The CONTRACTOR shall prepare and submit a Traffic Control Plan prior to any construction activities. The plan shall include at a minimum:
1) Locations of all signs, markers, barricades, and other traffic control devices to be used.
2) Specifications for signs, markers, and barricades including references to Manual of Uniform
Traffic Control Devices (MUTCD).
3) Locations for flag-persons, if used, along with anticipated dates and hours of use.
4) Requested road closures with period of closures and time when closures are anticipated.
5) Alternate routes for public access around temporary closures.
The Traffic Control Plan shall be subject to review and approval, in writing, by the CO. No work may commence until the Traffic Control Plan has been approved by the CO. Traffic control shall be provided in full compliance with the MUTCD standards. At the conclusion of daily and weekly construction activities, the CONTRACTOR shall ensure that proper traffic control measures remain in effect overnight and through the weekend.
(c) Erosion Control Plan (S-003).
The CONTRACTOR shall submit an Erosion Control Plan for construction activities associated with this project. The plan shall be written in accordance with the Montana Department of Environmental Quality Montana Sediment and Erosion Control Manual, May 1996, and the U.S. Environmental Protection Agency’s Storm Water Management for Construction Activities; Developing Pollution Prevention Plans and Best Management Practices, September, 1992. The submitted plan is expected to be specific to the project site and shall detail locations and types of best management practices that will be used during construction. The Erosion Control Plan shall also address McLaren Adit discharge water during construction.
The project site is located in an area of high precipitation, and frequent thunderstorms and occasional snowstorms occur during the construction season. The CONTRACTOR shall include in the erosion control plan the measures that will be taken for controlling precipitation and stormwater runon and runoff at the site.
(d) Other Submittals.
The following is a listing of other submittals required under this contract. This list summarizes the requirements shown under each item in the special project specifications; however, the list may not be all-inclusive. The CONTRACTOR is responsible for identifying all required submittals.
Submittal
• Limestone Calcium Carbonate Equivalent and gradation
• Fertilizer and seed certifications
• Compost source, total organic carbon to total nitrogen ratio, biosolids, maximum temperature achieved, organic matter content, and percent moisture
• Erosion control mat manufacturer’s cut sheet
C - 4 - STANDARD SPECIFICATIONS
Forest Service Specifications for Construction of Roads & Bridges (August 1996) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. Copies of this document are available upon request from the Gallatin National Forest Supervisor’s Office (contact Peter Werner (406) 587-6962).
The CONTRACTOR shall perform any testing necessary to ensure materials used in this contract meet specifications. Quality control is also the CONTRACTOR’s responsibility (Standard Specification 160 and Special Project Specification 160). The CONTRACTOR is responsible for all staking required on this project (Section C-1, Control of Work).
C - 5 - DRAWINGS
The following drawings are part of this solicitation and any resulting contract:
Sheet Cover, Road Reclamation Key and Index Estimated Quantities McLaren Pit Area Reclamation Plan McLaren Adit Closure Plan and Profile Adit Closure Details Adit Drainage Infiltration Basin Details Road Reclamation Plans Road Reclamation Plan Panel A ............................................................................................. 7A Road Reclamation Plan Panel B .............................................................................................. 7B Road Reclamation Plan Panel C .............................................................................................. 7C Road Reclamation Plan Panel D ............................................................................................. 7D Road Reclamation Plan Panel E ............................................................................................... 7E Road Reclamation Plan Panel F ............................................................................................... 7F Road Reclamation Plan Panel G ............................................................................................. 7G Road Tables Sheet A .................................................................................................................... 8A Road Tables Sheet B .................................................................................................................... 8B Road Reclamation Details Type I Drainage Dip Without Armor ...................................................................................... 9A
Type I Drainage Dip With Armor ........................................................................................... 9B Type II Drainage Dip With Armor .......................................................................................... 9C Armored Ditch, Spillway & Typical Reconditioned Road ..................................................... 9D Armored Ford, J-Hole Turnaround & Daisy Pass Road Reclamation ..................................... 9E Turnout and Culvert ................................................................................................................. 9F Temporary Erosion Control
C - 6 - SPECIAL PROJECT SPECIFICATIONS
Special Project Specifications are applicable to the following items and are included in their entirety in this section and in Appendix A. Within these Special Project Specifications, standard specifications are referenced. This reference is not intended to exclude other sections of the standard specifications. All general and standard specifications not referenced are still applicable.
Road Logs for work described under Item 5.0, Miscellaneous County and Forest Road Improvement and Reclamation, are included in Appendix B. The Road Logs are included by reference into Item 5.0, Forest Road Improvements and Reclamation descriptions of work and should be consulted for specific locations of the work based on milepost (MP) measurements. Specific details of the road work are AS SHOWN ON THE DRAWINGS. References to 6” minus base rock on the road logs is superseded by detailed work descriptions presented in the Special Project Specifications. Specifically, 6” minus base rock has been changed for the majority of road aggregate applications to Surface Course and to Class 1 Riprap for subgrade required between MP 3.31 and MP 3.33 and between MP 3.53 and MP 3.70 on the Miller Creek Road #3228.
(a) Estimated Quantities
Estimated quantities of materials that will be needed for the project are shown on Sheet 2 of the Construction Drawings. All estimated quantities are approximate and are to be used only as a basis for estimating the probable cost of the work and for the purpose of comparing the bids submitted for the work. The actual amounts of work done and materials furnished under unit price items may differ from the estimated quantities. All estimated quantities designated as cubic yards shall be considered bank cubic yards unless otherwise noted. Excavated “bank” cubic yards is the quantity of material removed as measured in its original position.
Forest Service Specifications Section 106, Measurement and Payment, applies to work items throughout this design. Section 106 applies inclusively with exception to the following modifications:
“Forest Service Specifications for Construction of Roads and Bridges, August 1996, are based on Modern Metric units of measurement. The dimensions and units of measure SHOWN ON THE DRAWINGS and used to develop SPECIAL PROJECT SPECIFICATIONS for this contract utilize U.S.
Standard English units of measure. All measurements referenced in the August 1996 Forest Service Standard Specifications (EM-7720-100) shall be converted to U.S. Standard English units of measure.
Conversion factors are included in Appendix A (Engineering Conversion Factors) and Appendix B (SI (Modern Metric) Conversion Factors) (pages 611 through 614 of the Standard Specification Appendices) to assist with any required conversions.”
(b) Sequence of Work
The project is expected to be completed in one construction season. The CONTRACTOR will determine the actual sequence of work. Access to Lulu Pass and Daisy Pass is generally not feasible until the middle of July due to persistent snowdrifts that prevent travel along the road. The CONTRACTOR may plow snow to expedite access to the sites provided a snow plowing plan is approved by the CO. The plowing plan shall describe equipment, timing and traffic control of the snow plowing operations. Snow plowing is considered incidental to the work.
(c) Work Items:
Page
ITEM 1.0 MOBILIZATION
ITEM 2.0 MCLAREN ADIT AREA REVEGETATION
ITEM 2.1 AMEND SOIL
ITEM 2.2 REVEGETATION
ITEM 3.0 MCLAREN ADIT DRAINAGE COLLECTION AND CLOSURE
ITEM 3.1 ADIT COLLECTION SYSTEM
ITEM 3.2 Adit Drainage Piping System ITEM 3.3 Infiltration Basin ITEM 3.4 Portal closure and Adit Area Reclamation
ITEM 4.0 DAISY PASS ROAD CUT AND FILL RECLAMATION
ITEM 4.1 PROVIDE, INSTALL, MAINTAIN AND REMOVE TEMPORARY EROSION CONTROL
MEASURES
ITEM 4.2 CUT AND FILL REGRADING
ITEM 4.3 AMEND SOIL
ITEM 4.4 REVEGETATION
ITEM 5.0 FOREST ROAD IMPROVEMENTS AND RECLAMATION
ITEM 5.1 ROAD RECLAMATION
ITEM 5.2 ALICE E. ROAD (FR# 7006) IMPROVEMENT
ITEM 5.3 BLACK WARRIOR ROAD (FR# 3226B) RECLAMATION
ITEM 5.4 BULL OF THE WOODS ROAD (FR# 3225) IMPROVEMENTS AND RECLAMATION ... 26
ITEM 5.5 CROWN BUTTE ROAD (FR# 3226) IMPROVEMENT
ITEM 5.6 DAISY PASS COUNTY ROAD (P16C-WEST) IMPROVEMENT
ITEM 5.7 FISHER MOUNTAIN ROAD (FR# 3214) IMPROVEMENT
ITEM 5.8 HENDERSON MOUNTAIN ROAD (FR# 3223) IMPROVEMENT
ITEM 5.9 LAKE ABUNDANCE ROAD (FR# 3219) IMPROVEMENTS AND RECLAMATION
ITEM 5.10 LOWER COUNTY CONNECTOR ROAD (FR# 3227) IMPROVEMENTS
ITEM 5.11 LOWER CROWN BUTTE ROAD (FR# 3226A) IMPROVEMENTS
ITEM 5.12 LULU PASS COUNTY ROAD (P16C-EAST) IMPROVEMENTS
ITEM 5.13 MCLAREN VIEW ROAD (FR# 3219A) IMPROVEMENTS
ITEM 5.14 MILLER CREEK ROAD (FR# 3228) IMPROVEMENTS
ITEM 5.15 SCOTCH BONNET ROAD (FR# 3229) IMPROVEMENTS AND RECLAMATION
ITEM 5.16 SHEEP MOUNTAIN ROAD (FR# 3224) IMPROVEMENTS AND RECLAMATION
ITEM 5.17 SOUTH HENDERSON ROAD IMPROVEMENTS AND RECLAMATION
ITEM 5.18 UPPER COUNTY CONNECTOR ROAD (FR# 3236) IMPROVEMENTS
ITEM 5.19 UPPER LADY OF THE LAKE TRAILHEAD ROAD (FR# 3218) IMPROVEMENTS
ITEM 6.0 REVEGETATION
APPENDIX A SPECIAL PROJECT SPECIFICATIONS
106 Measurement and Payment 160 Quality Control and Quantity Measurement 311 Local Slash and Logs
661 Calcium Carbonate Amendment 705 Riprap
APPENDIX B ROAD LOGS
ITEM 1.0 MOBILIZATION
The following Forest Service Specifications apply to this item:
Section 601 Mobilization
ITEM 2.0 MCLAREN ADIT AREAT REVEGETATION
The following Forest Service Specifications apply to this item:
Section 625 Seeding and Mulching The following Special Project Specification contained in Appendix A applies to this item:
Section 661 Calcium Carbonate Amendment
The area directly below the McLaren Adit receives seepage from the adit and groundwater discharge.
As a result, soils in the area below the adit will contain high moisture content well into the month of August. The CONTRACTOR shall delay any work directly below the adit until September 1, 2010, to ensure reclamation work can be completed according to the specifications. This date may be modified at the direction of the CO. Revegetation areas located directly above the McLaren View Road may dry out sooner and can be worked on prior to September 1 if travel on these areas with the CONTRACTOR’s equipment does not cause rutting deeper than three (3) inches. Prior approval of the CO is required.
Item 2.1 Amend Soil
Section 202, Removal of Structures and Obstructions (Subsection 202.01) Add the following:
This work includes removing and disposing dilapidated erosion control mat and wooden stakes located within the reclamation boundary. Dispose of debris at a Class II licensed landfill. Reuse of wooden stakes to hold down erosion mat is acceptable.
Section 202, Removal of Structures and Obstructions (Subsection 202.06) Add the following:
202 (06) Debris Disposal ....................................................................................................... ton
Section 625, Seeding and Mulching (Subsection 625.01) Add the following:
This work includes amending soil with organic matter and calcium carbonate.
Section 625, Seeding and Mulching (Subsection 625.02 - Materials) Add the following:
Section 713.05, (g) Mature Compost
The CONTRACTOR shall supply organic material in the form of compost. Compost must be weed seed free, have reached an ambient temperature of at least 140 degrees Fahrenheit, and must be supplied by a source that uses a suitable method of composting. The CO shall approve the source of compost that the CONTRACTOR proposes to use. Contractor shall submit the proposed compost source 14 days prior to shipping.
Delete specifications (g)(1) through (g)(6) and replace with the following:
Organic matter (dry weight), total nitrogen content (dry weight), and moisture content must be verified by testing for every 200 cubic yards delivered. The dry weight of organic matter shall be determined by ASTM D 2974 using a LECO furnace (preferably) or loss on ignition at 750ºF for 16 hours. Total nitrogen shall be determined by ASA Method 31-3 (Table 160). Percent moisture shall be determined by ASTM D 2216. Compost shall meet the specifications listed in Table 2.1.
TABLE 2.1
COMPOST SPECIFICATION
PARAMETER SPECIFICATION
Total Carbon to Total Nitrogen Ratio Less than or equal to 40:1
Biosolids Must Meet 40 CFR part 503 regulations for composting of biosolids Class A
Minimum Temperature 140 degrees Fahrenheit
Section 625, Seeding and Mulching (Subsection 625.06) Replace with the following:
Compost shall be applied to the upper six (6) inches of soil at a rate of 20 tons organic matter/per acre.
Acceptable compost incorporation methods shall include disking or mixing with a stabilizer or other approved methods. ‘Ripping’ is not an acceptable compost incorporation method. All areas will require ripping or chisel plowing of the soil following compost mixing.
SPS 661 Calcium Carbonate Amendment Work includes providing, spreading and incorporating limestone or equivalent neutralizing product into the areas AS SHOWN ON THE DRAWINGS. Special Project Specification 661 (Appendix A) applies to amending soil material with a calcium carbonate amendment. Calcium carbonate amendment shall be incorporated into the upper six (6) inches of soil using an appropriate mixing method that results a homogenous mixture Amendment rates AS SHOWN ON THE DRAWINGS shall be adjusted if the CCE differs from 1.0.
Item 2.2 Revegetation
Section 625, Seeding and Mulching (Subsection 625.02) Add the following:
See Item 6.0 for seeding and mulching requirements.
ITEM 3.0 MCLAREN ADIT DRAINAGE COLLECTION AND CLOSURE
All work associated with this item is described in subsequent sections and supported as SHOWN ON THE DRAWINGS. The following Forest Service Specifications apply to this item:
Section 203 Excavation, Embankment, & Haul Section 206 Structural Excavation for Major Structures Section 602 Minor Concrete Structures Section 603 Metal Pipe Section 603B Plastic Pipe Section 624 Topsoiling Section 625 Seeding and Mulching Section 704 Soil Section 705 Rock Section 707 Metal Pipe Section 725 Miscellaneous Material
Item 3.1 Adit Collection System
3.1.1 PORTAL AREA AND ADIT CLEAN-OUT EXCAVATION
Section 203 Excavation, Embankment and Haul (Subsection 203.2) Add the following:
The portal entrance shall be excavated to allow opening of the adit and to expose the existing CMP culvert as directed by the CO. Excavated portal materials may be saturated and shall be stockpiled to allow materials to dry prior to backfilling. Saturated materials shall be stockpiled at a location approved by the CO.
Section 203, Excavation, Embankment, and Haul (Subsection 203.20) Add the following:
203 (02)b Excavation, placement method 2 (Portal Area and Adit Clean-out Excavation)Cubic Yard
3.1.2 ADIT DEWATERING
Section 206 Structural Excavation for Major Structures (Subsection 206.08) Add the following:
Approximately 3 feet deep, by 400 feet of water exists behind a cave in the adit. Following initial adit excavation dewatering shall be necessary until Adit Collection System is complete.
Section 206, Structural Excavation for Major Structures (Subsection 203.20) Add the following:
206 (08) Adit Dewatering ......................................................................................... Lump Sum
3.1.3 PROVIDE AND INSTALL70” X 40” CMP CULVERT
Section 603 Metal Pipe (Subsection 603.02) Add the following:
Work includes furnishing and installing 70-inch x 40-inch CMP Culvert as SHOWN ON THE
DRAWINGS.
Section 603, Metal Pipe (Subsection 603.10) Add the following:
603 (01) 70-inch x 40-inch, CMP Method C ....................................................................... Foot
3.1.4 WATER SEAL 70-INCH X 40-INCH CMP CULVERT
Section 725 Miscellaneous Material (Subsection 725.20) Add the following:
Work includes sealing the inside edge of the 70-inch x 40-inch CMP Culvert with Bentonite to prevent adit drainage from flowing beneath the culvert.
Section 725, Miscellaneous Material (Subsection 725.20) Add the following:
725 (01) Water Seal 70-inch x 40-inch CMP Culvert .............................................. Lump Sum
3.1.5 8-INCH HDPE PERFORATED PIPE
Section 603B Plastic Pipe (Subsection 603B.02) Add the following:
Work includes furnishing and installing perforated 8-inch ADS N-12 HDPE or equivalent as
SHOWN ON THE DRAWINGS.
Section 603B, Plastic Pipe(Subsection 603.08)
603B (01)d .................................................................................... 8-inch HDPE Perforated Pipe Foot
3.1.6 8-INCH HDPE PIPE (ADIT TO DROP INLET)
Section 603B Plastic Pipe (Subsection 603B.02) Add the following:
Work includes furnishing and installing 8-inch ADS N-12 HDPE or equivalent as SHOWN ON THE
DRAWINGS.
Section 603B, Plastic Pipe(Subsection 603.08) Add the following:
603B (01)e ................................................................................... 8-inch HDPE Pipe, Method C
3.1.7 BEDDING GRAVEL
Section 704 Soil (Subsection 704.09)
Work includes furnishing and installing bedding gravel as SHOWN ON THE DRAWINGS. Gravel gradation may be substituted as approved by the CO.
Section 704, Soil (Subsection 704.02) Add the following:
704 (02)a Drop Inlet Bedding Gravel ....................................................................... Cubic Yard
3.1.8 DROP INLET STRUCTURE / ADIT CLEANOUT
Section 725 Miscellaneous Material (Subsection 725.11) Add the following:
Work includes furnishing and installing drop inlet structure, drop inlet risers, riser lid, metal grate, and adit cleanout materials as SHOWN ON THE DRAWINGS. Deviations to the drop inlet structure shall be approved by the CO prior to construction.
Section 725, Miscellaneous Material (Subsection 725.11) Add the following:
725 (01)b Drop Inlet Structure ................................................................................... Lump Sum
3.1.9 CONCRETE DRAIN PAD, METHOD C
Section 602 Minor Concrete Structure (Subsection 602.05) Add the following:
Work includes furnishing and placing concrete as SHOWN ON THE DRAWINGS. The concrete drain pad shall tie the drop inlet to the portal CMP culvert as SHOWN ON THE DRAWINGS.
Section 602, Minor Concrete Structure (Subsection 602.10)
602( (02) Concrete Drain Pad, Method C ................................................................. Lump Sum
Item 3.2 Adit Drainage Piping System
Work includes furnishing labor and materials for installation of Type IV-A Geotextile, 8-inch HDPE Pipe, and bedding gravel.
3.2.1 8-INCH DIAMETER HDPE
Section 603B, Plastic Pipe (Subsection 603B.01)
Work includes furnishing and installation of one 8-inch diameter ADS N-12 HDPE or equivalent culvert. The adit drainage trench shall be excavated as SHOWN ON THE DRAWINGS to accommodate the adit drain line which runs from the drop inlet structure to the infiltration basin.
Section 603B, Plastic Pipe (Subsection 603B.0) Add the following:
Bedding gravel shall meet the specification as SHOWN ON THE DRAWINGS. Gravel gradation may be substituted as approved by the CO.
Section 603B, Plastic Pipe(Subsection 603.08) Add the following:
603B (01)e 8-inch HDPE Pipe, Method C ............................................................................ Foot
Section 603B, Plastic Pipe (Subsection 603B.10)
Excavation, backfill, and compaction are considered incidental to the installation of the HDPE pipe.
3.2.2 TYPE IV-A GEOTEXTILE
Section 714 Geotextile, Geocomposite Drain Material, and Geogrids (Subsection 714.01) Add the following:
Work includes furnishing and installing Type IV-A Geotextile as SHOWN ON THE DRAWINGS.
Section 714, Geotextile, Geocomposite Drain Material, and Geogrids (Subsection 714.01)
714 (01) Type IV-A Geotextile .............................................................................. Square Yard
Item 3.3 Infiltration Basin
3.3.1 INFILTRATION BASIN EXCAVATION
Section 203 Excavation, Embankment and Haul (Subsection 203.2) Add the following:
The infiltration basin shall be excavated as SHOWN ON THE DRAWINGS.
Section 203, Excavation, Embankment, and Haul (Subsection 203.20) Add the following:
203 (02)c Excavation, placement method 2 (Infiltration Basin Excavation) ............ Cubic Yard
3.3.2 TYPE IV-A GEOTEXTILE
Section 714 Geotextile, Geocomposite Drain Material, and Geogrids (Subsection 714.01) Add the following:
Work includes furnishing and installing Type IV-A Geotextile as SHOWN ON THE DRAWINGS.
Section 714, Geotextile, Geocomposite Drain Material, and Geogrids (Subsection 714.01)
714 (01) Type IV-A Geotextile .............................................................................. Square Yard
3.3.3 BEDDING GRAVEL
Section 704 Soil (Subsection 704.09) Add the following:
Work includes furnishing and installing bedding gravel as SHOWN ON THE DRAWINGS. Gravel gradation may be substituted as approved by the CO.
Section 704, Soil (Subsection 704.02)
704 (02) Bedding Gravel ......................................................................................... Cubic Yard
3.3.4 PROVIDE AND INSTALL 8-INCH HDPE PERFORATED PIPE
Section 603B Plastic Pipe (Subsection 603B.02) Add the following:
Work includes furnishing and installing perforated 8” ADS N-12 HDPE or equivalent as SHOWN
ON THE DRAWINGS.
Section 603 B Plastic Pipe (Subsection 603B.06) Add the following:
Backfilling shall be accomplished using excavated materials, following the placement of the bedding gravel.
Section 603B, Plastic Pipe(Subsection 603.08)
603B (01)d 8-inch HDPE Perforated Pipe ............................................................................. Foot
Item 3.4 Portal Closure and Adit Area Reclamation
3.4.1 PROVIDE AND INSTALL PORTAL PLUG COARSE ROCK
Section 705 Rock (Subsection 705.02) Add the following:
Work includes furnishing and installing Class 2 Rip Rap as SHOWN ON THE DRAWINGS.
Section 705, Rock (Subsection 705.02) Add the following:
705 (01) Class 2 Rip Rap ........................................................................................ Cubic Yard
3.4.2 TYPE IV-A GEOTEXTILE
Section 714 Geotextile, Geocomposite Drain Material, and Geogrids (Subsection 714.01) Add the following:
Work includes furnishing and installing Type IV-A Geotextile as SHOWN ON THE DRAWINGS.
Section 714, Geotextile, Geocomposite Drain Material, and Geogrids (Subsection 714.01) Add the following:
714 (01) Type IV-A Geotextile .............................................................................. Square Yard
3.4.3 ADIT COVER SOIL
Section 704 Soil (Subsection 704.03) Add the following:
Work includes placing excavated Adit Clean-out material to approximate pre-mining topography as SHOWN ON THE DRAWINGS. Adit cover soils shall exceed 95 percent of maximum density, as determined by AASHTO T99, method C or D. Backfill and compaction are considered incident to the adit reclamation.
Section 603B, Plastic Pipe (Subsection 603B.10) Replace with the following:
Excavation, backfill, and compaction are considered incidental to the installation of the HDPE pipe.
3.4.4 TOPSOIL COVER
Section 624 Topsoiling (Subsection 624.02) Add the following:
Work includes furnishing and spreading the topsoil to the depth and at the locations as SHOWN ON THE DRAWINGS. Topsoil shall be available at the repository area as SHOWN ON THE DRAWINGS or other source as approved by CO. Topsoil shall exceed 95 percent of maximum density, as determined by AASHTO T99, method C or D. Topsoil compaction is considered incident to the furnishing and spring the topsoil.
Section 624, Topsoiling (Subsection 624.08) Add the following:
624 (02) Furnishing and Placing Topsoil ................................................................ Cubic Yard
3.4.5 REVEGETATE DISTURBED AREAS, METHOD A
Section 625, Seeding and Mulching (Subsection 625.02)
See Item 6.0 for seeding and mulching requirements.
ITEM 4.0 DAISY PASS ROAD CUT AND FILL RECLAMATION
This section describes improvements to cut and fill areas along Daisy Pass Road generally between MP
2.2 and MP 3.1 AS SHOWN ON THE DRAWINGS (Sheet 9E). The following Forest Service Specifications apply to this item:
Section 203 Excavation, Embankment, & Haul Section 204 Soil Erosion & Water Pollution Control Section 625 Seeding and Mulching
Item 4.1 Provide, Install, Maintain and Remove Temporary Erosion Control Measures
Section 204, Soil Erosion and Water Pollution Control (Subsection 204.01)
Provide, install, and maintain temporary erosion control measures as indicated by the CONTRACTOR’s erosion control plan submittal. Remove silt fence and straw bales upon completion and as approved by the CO.
Item 4.2 Cut and Fill Regrading
Section 203, Excavation, Embankment, and Haul (Subsection 203.01) Add the following:
Regrade only those portions of cuts and fills where rills and gullies have formed, generally between MP
2.2 and 3.1 as directed by CO.
Section 203, Excavation, Embankment, and Haul (Subsection 203.06 (a)) Add the following:
Salvage and preserve topsoil and existing vegetation at the direction of the CO. Blend excess material into surrounding area.
Section 203, Excavation, Embankment, and Haul (Subsection 203.20) Add the following:
203 (25) Daisy Pass Road Cut and Fill Regrading .................................................. square yard
Item 4.3 Amend Soil
Section 625, Seeding and Mulching (Subsection 625.02 - Materials) Add the following:
Section 713.05, (g) Mature Compost
The CONTRACTOR shall supply organic material in the form of compost. Compost must be weed seed free, have reached an ambient temperature of at least 140 degrees Fahrenheit, and must be supplied by a source that uses a suitable method of composting. The CO shall approve the source of compost that the CONTRACTOR proposes to use. Contractor shall submit the proposed compost source 14 days prior to shipping.
Delete specifications (g)(1) through (g)(6) and replace with the following:
Organic matter (dry weight), total nitrogen content (dry weight), and moisture content must be verified by testing for every 200 cubic yards delivered. The dry weight of organic matter shall be determined by ASTM D 2974 using a LECO furnace (preferably) or loss on ignition at 750ºF for 16 hours. Total nitrogen shall be determined by ASA Method 31-3 (Table 160). Percent moisture shall be determined by ASTM D 2216. Compost shall meet the specifications listed in Table 3.1.
TABLE 4.1
COMPOST SPECIFICATION
PARAMETER SPECIFICATION
Total Carbon to Total Nitrogen Ratio Less than or equal to 40:1
Biosolids Must Meet 40 CFR part 503 regulations for composting of biosolids Class A
Minimum Temperature 140 degrees Fahrenheit
Section 625, Seeding and Mulching (Subsection 625.06)
Compost shall be applied to the upper three (3) inches of soil at a rate of 10 tons organic matter/per acre.
Compost incorporation method shall be approved by the CO.
Item 4.4 Revegetation
Section 625, Seeding and Mulching (Subsection 625.02) Add the following:
See Item 6.0 for seeding and mulching requirements.
ITEM 5.0 FOREST ROAD IMPROVEMENTS AND RECLAMATION
All work associated with this item is described on Road Logs presented in Appendix B, as further detailed in subsequent sections, and supported with details AS SHOWN ON THE DRAWINGS. The following Forest Service Specifications apply to this item:
Section 201 Clearing and Grubbing Section 202 Removal of Structures and Obstructions Section 203 Excavation, Embankment, & Haul Section 204 Soil Erosion & Water Pollution Control Section 210 Closing Obliteration or Treatment of Existing Roads Section 251 Riprap Section 304 Aggregate Base or Surface Course Section 305 Stockpile Aggregates Section 306 Reconditioning Existing Road Section 603 Metal Pipe Section 603B Plastic Pipe Section 625 Seeding and Mulching Section 713 Roadside Improvement Material
Item 5.1 Road Reclamation
Subsection 210, Closing, Obliteration, or Treatment of Existing Roads (Subsection 210.05) Add the following:
Scarify, fertilize and seed disturbed areas outside the traveled way. Revegetation of all areas of disturbance associated with improvements and/or reclamation presented in this Item are addressed in Section 6.0.
Item 5.2 Alice E. Road (FR# 7006) Improvement
Work includes furnishing labor and materials for installation of one culvert, associated regrading, and revegetation of areas along road.
5.2.1 36-INCH DIAMETER CMP
Section 603, Metal Pipe (Subsection 603.01) Add the following:
Work includes furnishing and installing one 36-inch diameter corrugated metal pipe (CMP) as
SHOWN ON THE DRAWINGS.
Section 603, Metal Pipe (Subsection 603.03) Add the following:
Reduce cut slopes 50 feet either side of the culvert to less than 2H:1V before excavating for culvert.
Excavate sufficiently below existing surface to place culvert and drainage gravel (bedding).
Section 603, Metal Pipe (Subsection 603.10) Replace with the following:
Reducing cut slopes, excavation, backfill, and compaction are considered ancillary to the installation of the CMP; no separate pay item will be made for these efforts.
5.2.2 ROAD IMPROVEMENTS
Section 304, Aggregate Base or…