Attachment2Tech_Specs_OPTION2_3-23-17.docx

DOCX document 129 KB Posted

Attached to
Nez Perce-Clearwater NFs - Crooked River Valley Rehabilitation - Option 2
Solicitation number
AG-02RC-S-17-0077
Issued by

About this file

Attachment J-2 Technical Specifications

View the file

Other files

File Type Posted
AttachmentJ6_Page1_temp_culvert_location.docx DOCX document
AttachmentJ6_Page2_Temp_culvert_location_2.docx DOCX document
AttachmentJ6_Page4_TreeStockpile.JPG JPG image
AttachmentJ6_Page3_Stockpile_areas.docx DOCX document
CrookedRiverAmend1.pdf PDF
AttachmentJ6_Page5_AerialOption2.jpg JPG image
SiteTourNotes.docx DOCX document
Attachment4CRVR_Construction_SWPPP_Option2.docx DOCX document
FinalConstructionRFP.docx DOCX document
Attachment3CRVR_Option2CoverSheet_signed.pdf PDF
Attachment3Crooked_RiverOption2Drawings.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA – Forest service and NEz Perce Tribe Crooked River Valley Rehabilitation Technical Specifications Option 2

Last Revision 3/13/2017

LIST OF TECHNICAL SPECIFICATIONS

Section 01200Measurement and Payment
Section 01201Pay Items
Section 01300Submittals
Section 01400Construction Staking
Section 01505Mobilization/Demobilization
Section 01560Environmental Controls
Section 01600Protection of Materials
Section 01640Government Supplied Materials
Section 01720Record Drawings
Section 02140Dewatering and Work Area Isolation
Section 02200Earthwork
Section 02900Seeding
Section 02930Vegetative Fill
Section 02931Vegetation Salvage and Transplant
Section 02932Tree Salvage
Section 05000Large Wood Structures

Section 05001 Streambank and Floodplain Fill

Section 05010 Floodplain Roughness i

SECTION 1200

MEASUREMENT AND PAYMENT

Measurement of Work Methods of Measurement One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM (Section 01201):

a) Actual Quantities (AQ).

b) Design Quantities (DQ).

c) Lump Sum Quantities (LSQ).

Measurement Terms and Definitions

1. Acre (AC). 43,560 square feet. Make longitudinal and transverse measurements for area computations horizontally unless specified on the ground surface. Do not make deductions from the area computation for individual fixtures having an area of 500 square feet or less.

2. Actual Quantities (AQ). These quantities are determined from measurements of completed work.

3. Design quantity (DQ). The quantity to be paid is the quantity shown in the bid schedule. The design quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity. If there is evidence that a quantity specified as a design quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request, in writing, that the quantity be adjusted. Design quantities will be adjusted only when there are errors in the original design of 15% or more. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:

a) Changes in the work authorized by the Contracting Officer.

b) A determination by the Contracting Officer that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

c) A written request submitted to the Contracting Officer showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

4. Cubic yard (CY).

a) Cubic yard in place. Measure solid volumes by a method approved by the Contracting Officer or by the average end area method as follows:

(a) Take cross-sections of the original ground and use with design or staked templates or take other comparable measurements to determine the end areas. Do not measure work outside of the established lines or slopes.

(b) If any portion of the work is acceptable but is not completed to the established lines and slopes, retake cross-sections or comparable measurements of that portion of the work. Deduct any quantity outside the designated or staked limits. Use these measurements to calculate new end areas.

(c) Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference lines between the end areas. Deduct any quantity outside the designed or staked limits.

b) Cubic yard in the hauling vehicle. Measure the cubic yard volume in the hauling vehicle using three-dimensional measurements at the point of delivery. Use vehicles bearing a legible identification mark with the body shaped so the actual contents may be readily and accurately determined. Before use, mutually agree in writing on the volume of material to be hauled by each vehicle. Vehicles carrying less than the agreed volume may be rejected or accepted at the reduced volume.

Level selected loads. If leveling reveals the vehicle was hauling less than the approved volume, reduce the quantity of all material received since the last leveled load by the same ratio as the current leveled load volume is to the agreed volume. Payment will not be made for material in excess of the agreed volume.

Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purposes if the conversion factors are mutually agreed to in writing.

c) Cubic yard in the structure. Measure according to the lines of the structure as shown on the plans except as altered by the Contracting Officer to fit field conditions. Make no deduction for the volume occupied by reinforcing steel, anchors, weep holes, piling, or pipes less than 8 inches in diameter.

d) Cubic yard by metering. Use an approved metering system.

5. Each (EA). One entire unit. The quantity is the actual number of units completed and accepted.

6. Hour. Measure the actual number of hours ordered by the Contracting Officer and performed by the contractor.

7. Linear foot. As applicable, measure the work along its length from end-to-end; parallel to the base or foundation; along the top; along the front face; or along the invert. Do not measure overlaps.

8. Mile. 5,280 linear feet. Measure horizontally along the centerline of each roadway, approach road, or ramp.

9. Lump sum quantity (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. Do not measure directly. The bid amount is complete payment for all work described.

10. Station. 100 linear feet. Measure horizontally along centerline or reference line of each roadway, approach road, or ramp.

Weighing Procedures and Devices

Batch masses may be acceptable for determination of pay quantities when an approved automatic weighing, cycling, and monitoring system is included as part of the batching equipment.

When a weighing device is determined to indicate less than true mass, no additional payment will be made for material previously weighed and recorded. When a weighing device is determined to indicate more than true mass, all material received after the last previously correct weighing accuracy test will be reduced by the percentage of error in excess of 0.5 percent.

When material is proportioned or measured and paid for by mass, provide one of the following:

(a) Commercial weighing system. Use permanently-installed and certified commercial scales.

(b) Invoices. If bulk material is shipped by truck or rail and is not passed through a mixing plant, furnish a supplier's invoice with net mass or volume converted to mass. Periodic check weighing may be required.

Receiving Procedures

When the method of measurement requires weighing or volume measurement in the hauling vehicle, furnish a person to direct the spreading and distribution of material and to record the location and placement of the material on the project. During the placement, maintain a record of each delivery and document it in an acceptable manner. Include the following information as applicable:

(a) Project identification;

(b) Contract pay item number and description;

(c) Location where placed;

(d) Date;

(e) Load number;

(f) Truck identification;

(g) Time of arrival;

(h) Mass or volume; and

(i) Spread person's signature.

Use an approved format for the delivery record(s). Furnish the original record(s) and a written certification of the delivery of the material at the end of each shift.

Scope of Payment

Payment for all contract work is provided, either directly or indirectly, under the pay items shown in the bid schedule.

1. Direct payment. Payment is provided directly under a pay item shown in the bid schedule when one of the following applies:

a. The work is measured in the Measurement Subsection of the Section ordering the work, and the bid schedule contains a pay item for the work from the Section ordering the work.

b. The Measurement Subsection, of the Section ordering the work, references another Section for measuring the work and the bid schedule contains a pay item for the work from the referenced Section.

2. Indirect payment. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items shown in the bid schedule. This includes instances when the Section ordering the work references another Section for performing the work and the work is not referenced in the Measurement Subsection of the Section ordering the work.

Compensation provided by the pay items included in the contract bid schedule is full payment for performing all contract work in a complete and acceptable manner. All risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the contract pay items.

Work measured and paid for under one pay item will not be paid for under any other pay item.

The quantities shown in the bid schedule (Section 01201) are approximate unless designated as a design quantity. Limit pay quantities to the quantities staked, ordered, or otherwise authorized before performing the work. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.

SECTION 01201

PAY ITEMS

General Individual pay items will be paid in accordance with Section 01200 and Section 01201. This section will outline the individual pay items and requirements of each.

Pay Items

Bid Item
Description
Est. Quantity
Method of Measure
Units
Unit Price
Total
1
Mobilization and Demobilization
1
Lump Sum
LS
2
Water Management and Environmental Controls
1
Lump Sum
LS
3
Staking
1
Lump Sum
LS
4
Tree and Brush Salvage
10.3
Design
AC
5
Wetland Sod and Shrub Salvage and Transplant
0.50
Design
AC
6
Large Wood Structure Type 1
7
Actual
EA
7
Large Wood Structure Type 3
3
Actual
EA
8
Earthwork- Excavate, Fill, and Grade Floodplain
11,800
Design
CY
9
Earthwork-Haul Excess to South Staging Area
16,300
Actual
CY
10
Salvage Vegetative Fill
3,000
Design
CY
11
Incorporate Wood Chips
1,000
Design
CY
12
Floodplain Roughness
10.3
Design
AC
13
Rate for Excavator and Operator
8
Actual
Hours
14
Rate for Dump Truck and Operator
8
Actual
Hours
15
Rate for Bulldozer and Operator
8
Actual
Hours

Item 1 Mobilization and Demobilization Payment for Bid Item 1- Mobilization and Demobilization will be based on the lump sum price bid as shown on the Bid Form. Fifty percent (50%) payment for this Bid Item will be allowed once the Contractor fully mobilizes to the Site and obtains approval on all submittals required before starting construction. Full Payment for this item will be allowed once the Contractor completes the specified Work and fully demobilizes equipment and materials from the Site. The lump sum bid price for this item must not exceed ten percent (10%) of the total bid price. Mobilization and Demobilization applies to Section 01300, 01505.

Incidental to Mobilization Maintenance of Road 233 is incidental to Mobilization and Demobilization. Road 233 shall be maintained in the condition that it was found upon mobilization to the site. The Contractor is responsible for documenting the existing condition of the road. The Contractor will be responsible for providing construction signs at Hwy 14 and at each used access road per Section 01505.

Item 2 Water Management and Environmental Controls Payment for Bid Item 2- will be based on the lump sum price bid as shown on the Bid Form This Work includes but is not limited to, modification to the Storm Water and Pollution Prevention Plan, control turbidity during large wood installation and floodplain construction, install erosion control devices, and meet turbidity standards. Work may occur in the wet, however, erosion control devices and pumps, as specified in Section 01560, shall be onsite prior to Work commencing. The Contractor may need to install coffer dams and pump water out of excavations if turbidity approaches 50 NTUs and cannot be controlled through other measures. The bid item amount is complete payment for all work described in the contract in Specification 01560 and necessary to complete the work for this pay item.

Item 3 Staking Payment for Bid Item 3- will be based on the lump sum price bid as shown on the Bid Form. This work includes, but is not limited to, staking large woody debris features, access routes, preservation areas, vegetation salvage and placement, floodplain features such as depressions and swales, and river bank stations. The Government will provide survey control and grading surfaces for equipment with GPS machine control capability, however, the Contractor will need to provide initial surveying of existing survey control points. Additional surveys may be necessary if the Contractor is unable to use equipment with GPS machine control capability. The bid item amount is complete payment for all work described in the contract in Specification 01400 and necessary to complete the work for this pay item.

Item 4 Tree and Brush Salvage The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. The entire project area is approximately 10.3 acres, however, not all of the acreage is covered by trees and brush. Payment will be full compensation for the Tree and Brush Salvage work prescribed in Sections 02391, 02932. This includes cutting trees to length, hauling to designated staging area, and sorting and stockpiling.

Incidentals: Protection of government materials during and after the completion of work is incidental to Tree and Brush salvage. Methods of materials protection is prescribed in Section 01600.

Item 5 Wetland Sod and Shrub Salvage and Transplant The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. The entire project area is approximately 10.3 acres, however, approximately .50 acres of this total area have sod mats and brush meeting specification. This bid item includes all labor, equipment necessary to salvage and transplant this material. Payment will be in full compensation for the work as prescribed in Sections 02931, 01300.

Item 6 Large Wood Structure Type 1 The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation for the Large Wood Structure construction as prescribed in Section 05000, using backfill material as specified in Section 01640. These structures will utilize tree material salvaged in under Pay item 4 and streambank material under Item 9. This includes hauling all materials from within Option 2 construction limits or potentially large wood from the south end staging area in the event a shortage of materials is encountered, and all labor and equipment necessary to construct these features to the planned dimensions.

Item 7 Large Wood Structure Type 3 The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation for Type 3 Large Wood Structure construction as prescribed in Section 05000 using backfill material as specified in Section 01640. These structures will utilize tree material salvaged under Pay Item 4 and using backfill material specified in Section 01640. This includes hauling all materials from within Option 2 construction limits or potentially large wood from the south end staging area in the event a shortage of materials is encountered, and all labor and equipment necessary to construct these features to the planned dimensions.

Item 8 Earthwork- Excavate, Fill and Grade Floodplain The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to regrade the tailings piles within the floodplain and complete floodplain grading including construction of depressions and swales, as per Drawing Sheet Numbers 5.0, 6.0 and 7.0. It is anticipated that floodplain fill will be available within Option 2 construction limits. Payment will be full compensation for the Earthwork work prescribed in Sections, 02200, 05000, 05001.

Item 9 Earthwork- Excavate and Haul Excess to South Staging Area The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work shall include, but is not limited to, cutting and removal of excess material from floodplain grading work (Pay Item 8) and haul to South End Staging Area. Payment will be full compensation for the excavation and hauling of excess material work prescribed in Sections 02200, 05010.

Item 10 Earthwork- Vegetative Fill The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation for Vegetative Fill salvage from within Option 2 construction limits. This material will be stockpiled to be used as specified in Bid Item 12. Payment will be in full compensation for the work prescribed in Section 02930.

Item 11 Mix Wood Chips into Floodplain

The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Wood chips shall be mixed into vegetative fill prior to placement on floodplain. Payment will be in full compensation for the wood chip work prescribed in Section 02930.

Incidentals: Contractor shall coordinate material delivery with a separate Forest Service contract.

Item 12 Floodplain Roughness The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work utilizes brush and small logs salvaged from within Option 2 construction limits under Pay Item 3. This work includes, but is not limited to, all materials, equipment, and labor necessary to place floodplain roughness features and complete floodplain roughness finish grading as shown on Drawing Sheet Number 8.3. Payment will be full compensation for the Floodplain Roughness work prescribed in Section 05010.

Incidentals: Contractor shall seed the entire 10.3 acre project area in accordance with Section 02900.

Item 13 Rate for 300 Class Excavator and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item 12.

Item 14 Rate for Dump Truck and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item 13.

Item 15 Rate for Bulldozer and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item 14.

SECTION 01300

SUBMITTALS

GENERAL

Submittals covered by these requirements include manufacturers’ information, test procedures, test results, samples, requests for substitutions, and miscellaneous work-related submittals. Submittals shall also include, but not be limited to, rock sources, and fabricated items. The Contractor shall furnish all drawings, specifications, descriptive data, certificates, samples, tests, methods, and schedules and other instructions as specifically required in the contract documents to demonstrate fully that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the contract documents.

CONTRACTOR’S RESPONSIBILITIES

The Contractor shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment or method of work shall be as described in the submittal. The Contractor shall verify that all features of all products conform to the specified requirements. Submittal documents shall be clearly edited to indicate only those items which are being submitted for review. All extraneous materials shall be crossed out or otherwise removed. The Contractor shall ensure that there is no conflict with other submittals and notify the Contracting Officer in each case where his submittal may affect the work of another contractor. The Contractor shall coordinate submittals among his subcontractors and suppliers including those submittals complying with unit responsibility requirements specified in applicable technical sections.

The Contractor shall coordinate submittals with the work so that work will not be delayed. The Contractor shall coordinate and schedule different categories of submittals, so that one will not be delayed for lack of coordination with another. No extension of time will be allowed because of failure to properly schedule submittals. The Contractor shall not proceed with work related to a submittal until the submittal process is complete. This requires that submittals for review and comment shall be returned to the Contractor stamped “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED.”

The Contractor shall certify on each submittal document that he has reviewed the submittal, verified field conditions, and complied with the contract documents.

The Contractor may authorize in writing a material or equipment supplier to deal directly with the Contracting Officer with regard to a submittal. These dealings shall be limited to contract interpretations to clarify and expedite the work.

STANDARD COMPLIANCE

1. When materials or equipment must conform to the standards of organizations such as, but not limited to, the American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), National Electrical Manufacturers Association (NEMA) and Underwriter’s Laboratories (UL) documents showing, or proving, conformance shall be submitted.

2. If an organization uses a label or listing to indicate compliance with a particular standard, the label or listing will be acceptable evidence, unless otherwise specified in the individual Sections. In lieu of the label or listing, the Contractor shall submit a certificate from an independent testing organization, which is competent to perform acceptable tests, and is approved by the Contracting Officer. The certificate shall state that the item has been tested in accordance with the specified organization’s standard. For materials and equipment whose compliance with organizational standards or specifications is not regulated by an organization using its own listing or label as proof of compliance, a certificate of compliance from the manufacturer shall be submitted for approval. The certificate shall identify the manufacturer, the product, and the referenced standard and shall state that the manufacturer certifies that the product conforms to all requirements of the project Specification and of the referenced standards listed.

REVIEW OF CONTRACTOR’S INFORMATION

1. When review and checking for acceptance is required of any drawing, or information regarding materials and equipment, the Contractor shall prepare or secure, and submit for review, two (2) copies. The Contracting Officer, after taking appropriate action, will return (1) marked copies to the Contractor.

Within 7 calendar days after receipt of said submittal copies, the Contracting Officer will return the marked copies indicating one of the following four (4) actions:

a. If review and checking indicates no exceptions, copies will be returned marked “NO EXCEPTIONS TAKEN” and work may begin immediately on incorporating the material and equipment covered by the submittal into the work.

b. If review and checking indicates limited corrections are required, copies will be returned marked “MAKE CORRECTIONS NOTED”. Work may begin immediately on incorporating into the work the material and equipment covered by the corrected submittal.

c. If review and checking indicates insufficient, or incorrect data, has been submitted, copies will be returned marked, “AMEND AND RESUMIT”. No work may begin on incorporating the material and equipment covered by this submittal into the work until the submittal is revised, resubmitted, and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.

d. If review and checking indicates the material and equipment submittal is unacceptable, copies will be returned marked “REJECTED-RESUBMIT”. No work may begin on incorporating the material and equipment into the work until a new submittal is made and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.

Approval by the Contracting Officer shall not relieve Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with requirements of this Contract.

EFFECT OF REVIEW OF CONTRACTOR’S SUBMITTALS

Review of contract drawings, methods of work, or information regarding materials or equipment the Contractor proposes to provide, shall not relieve the Contractor of his responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Contracting Officer, or by any officer or employee thereof, and the Contractor shall have no claim under the contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. A mark of “NO EXCEPTIONS TAKEN or MAKE CORRECTIONS NOTED” shall mean that the Contracting Officer has no objection to the Contractor, upon his own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.

PRODUCTS

MANUFACTURER’S DATA

Submittals for each manufactured item shall be comprised of manufacturer’s descriptive literature, drawings, diagrams, performance and characteristic curves, and catalog cuts. Manufacturer’s name, trade name, model or catalog number, nameplate data, size, layout dimensions, capacity, project specification references, and any other additional information necessary to establish contract compliance shall be clearly indicated.

At a minimum, the Contractor shall provide project submittals as shown on the following Submittal Log. Submittal requirements are listed in the Technical Specifications and Drawings.

Submittal Log 01300

Submittal #
Item
Type of Submittal
Notification
Requirement Location
Incidental to Bid Item
1
Construction Staking
Narrative and notification
24 hours
Specification 01400
Mobilization
2
Equipment Inspection
Notification
72 hours
Specification 01505
Mobilization
3
Weed Free Certifications
Certificates
72 hours
Specification 01560
Water Management and Environmental Controls
4
Stormwater Pollution Prevention Plan
Drawing and narrative/EPA permit process
20 days
Specification 01560
Mobilization
5
Dewatering and Work Area Isolation Plan
Drawing and narrative
10 days
Specification 02140

Mobilization

7
Nursery Care Plan
Narrative
72 hours
Specifications 02930 and 02931

Wetland Sod and Shrub Salvage and Transplant

8
Large Wood Structures
Notification
24 hours each structure
Specification 05000

Drawings 8.0 and 8.1 Large Wood Structure 1 and 3

10
Floodplain Roughness
Notification
72 hours
Specification 05010

Drawing 8.3 Floodplain Roughness

11
Seed Mix
Mix Information and Broadcast Equipment- weed free certification
48 Hours
Specification 02900
Floodplain Roughness

EXECUTION

1.At least 7 calendar days prior to the Contractors need for approval, contractor shall forward to the Contracting Officer all submittals required by the individual Sections of the Specifications.
2.All submittals shall be identified by submittal number and specification section number on the letter of transmittal. Submittals shall be numbered consecutively and resubmittals shall have a letter suffix. For example:
a.1st submittal:05001
b.1st resubmittal:05001A
c.2nd resubmittal:05001B, etc.

Items to be submitted are specified in individual Sections of these Specifications. Submittals for each Section shall be bound together in one book. Book shall have numbered tab dividers for each item. Submittals that are related to, or affect, each other shall be forwarded simultaneously as a package to facilitate coordinated review. Uncoordinated submittals will be rejected. Do not combine unrelated materials in the same submittal. Submittals shall be arranged in same order as they appear in the Specification Section. Items shall be clearly marked with the same identification number as indicated on the drawings. The Contractor shall include submittal time appropriate within each item of work on the Construction Schedule. The Contracting Officer will receive submittals at the preconstruction meeting.

***END OF SECTION***

SECTION 01400

CONSTRUCTION STAKING

GENERAL

CONSTRUCTION STAKING

The Contractor shall provide survey staking for construction. The Government will provide survey control and grading surfaces for equipment with GPS machine control capability. This file will include a surface with the grades shown on Drawing Sheet Number 6.0. The Contractor, even if using the GPS equipment, is responsible for marking, with stakes, design features such as large wood locations, swales and depressions, preservation areas, and access areas.

METHODS

STAKEOUT AND MEASUREMENT TO BE PERFORMED BY CONTRACTOR

The Contracting Officer will provide an initial layout of the restoration design in consultation with the Contractor. After the initial layout, the Contractor shall be responsible for staking reference points/markers to complete the work from the initial control points and grading surfaces provided by the Contracting Officer, and shall be responsible for all measurements required for the execution of the work. The Contractor shall protect all stakes and shall pay for the time and materials required to replace stakes that have been disturbed or obliterated if necessary.

The Contractor shall use information provided by the Contracting Officer to stake the boundaries of construction extents, access roads, staging areas, heritage resources, and materials salvage areas, vegetation preservation areas, grading extents and structure locations. The extent of disturbance is shown on the Site Plan (Sheet 3.0). The Contracting Officer shall approve staking boundaries prior to commencement of work. In addition, the Contactor shall stake reference points outside the construction extents of any existing survey control points (see Sheet 4.0 on project drawings). Upon completion of the project, the original survey control points will be restaked.

Contractor shall stake river stationing every 100 feet as a reference.

The Contractor shall furnish at the Contractor’s own expense, such stakes, equipment, tools, materials, and all labor as required in stakeout of any parts of the work from the control points and grading surfaces provided by the Contracting Officer.

The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

***END OF SECTION***

SECTION 01505

MOBILIZATION AND DEMOBILIZATION

GENERAL

MOBILIZATION

Mobilization shall consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the site; for the establishment of all facilities necessary for work on the project; and for all other work and operations which must be performed, or costs incurred prior to beginning work, on the various items on the project site. Mobilization includes obtaining project-specific bonds and obtaining any permits, including the EPA’s Construction General Permit NOI (electronic NOI system, “eNOI”) for stormwater runoff, not provided by the Contracting Officer. The Contractor shall have erosion control devices on site, including, but not limited to, a 6 inch pump, silt fence, stakes, waddles, and straw bales, in accordance with Section 02140 prior to any ground disturbance.

Mobilization shall also include the construction of temporary ramps and access ways, temporary bridges, if proposed, staging areas, temporary roads, grading, and the necessary preparatory work required to allow for the safe and stable movement of all vehicles that are required to construct the improvements outlined in the Contract Documents.

1. Notify the Contracting Officer in writing at least 72 hours before moving any construction equipment onto the National Forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Nez Perce Tribe or Forest Service. Subsequent move-ins of equipment shall be treated the same as the initial move-in and will require notification.

2. All equipment shall be washed prior to mobilization to the Forest to minimize the introduction of foreign materials and fluids to the project site. All equipment shall be free of oil, hydraulic fluid, and diesel fuel leaks. To prevent invasion of noxious weeds or the spread of whirling disease spores, all equipment shall be power washed or cleaned to remove all dirt, plant parts and material prior to mobilization. Truck beds and dump boxes hauling to the project site shall also be cleaned prior to entering the Forest. It will be the contractor's responsibility to insure that adequate measures have been taken. Equipment shall be inspected by the Inspector prior to mobilizing to the Forest. Only construction equipment inspected by the Nez Perce Tribe or Forest Service will be allowed to operate within the project area.

3. Equipment shall be in a well-maintained condition to minimize the likelihood of a fluid leak. Any leaks or accumulations of grease would be corrected before entering the project area. If a fluid leak does occur, the project Inspector and COR shall be notified immediately, and all work ceased until the leak has been rectified. At all times during the construction phase, fluid spill containment equipment adequately sized for specific quantities of fuel shall be present on-site and ready for deployment should an accidental spill occur. Fuel spill kit shall include an oil-absorbing floating boom and absorbent pads. Contractor and Contractor’s representatives shall be knowledgeable on use of the spill containment equipment. The Contracting Officer reserves the right to refuse equipment that does not meet criteria.

4. Equipment that will be used in live water shall utilize hydraulic fluid that is non-toxic to salmonids. The following criteria should be met to determine if a hydraulic fluid is nontoxic to salmonids during acute exposure: (a) The test species used should be a salmonid (most often this will be rainbow trout, but occasionally Chinook salmon or coho salmon are tested); (b) The test duration should be 96 hours; (c) The test should be conducted using the water accommodated fraction (WAF) (the WAF is used in testing hydrophobic materials to provide a "worst case scenario" for exposure to aquatic organisms); and (d) The value of the LC50 should be >1000 mg/L. Several products on the market meet these specifications.

According to the guidance provided by the National Oceanic and Atmospheric Administration, the following products meet the required criteria:

· Chevron Clarity Hydraulic Oil A W

· Ecoterra Hydraulic Oil

· GreesCare Plus

· Mobil EAL 224H

· ENVIRONTM AW Hydraulic Fluids These products and companies are not endorsed by the government and the contractor should perform independent research regarding the performance characteristics of each product.

5. All construction equipment shall be staged in a location and manner to minimize air, soil and water pollution. Storage of fuel and lubricants - all fuel and lubricants shall be stored in containers and areas that are in conformance with the Idaho State Department of Environmental Quality, NMFS and USFWS biological opinion terms and conditions, and local regulations.

6. Servicing and refueling equipment - all fuel and lubricants used in the servicing of construction equipment shall be done in a manner that avoids spills and over filling and shall be at least 150 feet from all waterbodies. Stationary power equipment, such as generators, within 150 feet of the water shall be diapered to prevent leaks. All power equipment within 150 feet of the water shall be inspected daily for fluid leaks and repaired. The contractor must keep daily inspection reports in a diary.

7.The Idaho State Department of Environmental Quality shall be notified immediately of any spill and the operator shall contain the spillage. If a spill of chemical pollutants such as fuel or hydraulic fluid should occur, immediately attempt to contain the spilled material. The following procedures shall be followed:
(a)for spillage on land, construct earthen berms or use other suitable barricade material of sufficient size to contain the spell and keep it from spreading.

(b) for spillage on water, attempt to isolate and contain the spilled material. Commercial booms or other suitable materials shall be kept on site during construction to contain fuel and oil spills on water.

8. Sanitary facilities - sanitary facilities such as chemical toilets shall be located at least 150 feet from water bodies to prevent contamination of surface or subsurface water.

9. A description of hazardous materials that will be used including inventory, storage and handling procedures will be available on site.

10. If elemental mercury is found during project work, work in the immediate vicinity will stop and every reasonable effort will be made to contain the material in such a manner that it will not reach surface or groundwater. The COR shall be contacted immediately.

SITE PREPARATION

1. Existing Conditions The Contractor shall determine the actual condition of the site as it affects this portion of the work.

2. Protection of Existing Facilities and Improvements Site preparation shall not damage existing structures, landscaping, or vegetation adjacent to the areas designated for site preparation. The Contractor shall repair or replace any and all damaged property.

3. Vegetation Preservation and Salvage Preservation of existing vegetation and trees is of utmost importance. The Contractor will stake and walk the entire site with the Inspector and Contracting Officer to clearly mark the clearing limits and vegetation to be saved or salvaged. Additional salvage areas may be identified during construction by the designated Inspector that may be preserved.

4. Clearing and Grubbing The Contractor shall clear the work area of trees, brush, and excess material in order to construct the floodplain and floodplain features to grade. This may include removing stumps, brush, and rock material and hauling or stating to use for floodplain roughness features. Clearing limits are shown on the Site Plan (Sheet 3.1).

5. Road Maintenance and Signage Road 233 shall be maintained to its original condition upon mobilization to the site. It is the responsibility of the contractor to document the condition of the road upon mobilization.

It is anticipated that the following type and number of signs will be required on Road 233 to denote construction traffic:

Location
Designation
Quantity
At beginning of Road 233 and at the Junction of Road 233 and Deadwood Road 522
HEAVY TRUCK TRAFFIC
2
On Road 233, on either side of temporary access road
TRUCKS ENTERING ROADWAY
2

DEMOBILIZATION AND SITE RECLAMATION

1. Demobilization shall consist of work and operations necessary to disband all mobilized items and clean up the site. The removal of all temporary ramps, access ways, roads, signs, temporary fencing, construction debris including rock chips, wood debris, construction stakes, and other construction-related refuse, and temporary facilities or works and the restoration of surfaces to an equal or better than existing condition shall also be included as part of demobilization. All 1-ton straw bales shall be removed from the site or smaller straw bales are to be scattered on site and above the ordinary high water mark. No erosion control debris, including brush mats used to control erosion, may be left in the channel upon completion of work.

2.Site reclamation is included under demobilization. Site reclamation includes reclamation of areas disturbed during construction, including staging areas, and temporary access roads. Staging areas shall be decompacted and graded to match elevation specified on the plan sheets.
3.All damaged or disturbed streambanks are to be restored to a natural slope pattern and profile for establishment of permanent woody vegetation. Rock, woody materials and other natural construction materials used for the project shall be obtained from within the project footprint to be stockpiled and reused on site or from designated sites identified by the Contracting Officer. Leave native materials, e.g., down wood, where they are found, the floodplain is at grade. If native materials (e.g., downed wood) are destroyed, replace them with a functional equivalent during site restoration.
4.Stockpiled materials (i.e. trees, vegetation, topsoil, and other excavated material from restoration project areas) salvaged under Option 2 as well as prior phases of this project, shall be used as specified in the plan sheets. Short-term stabilization measures will be implemented until permanent erosion control measures (plant restoration) are effective, and include placement of brush and small logs on recently graded surfaces, as specified in the plan sheets. Stockpiled material that will be used in future Phases will be stabilized to reduce erosion and protected from theft.
5.All brush mats, straw bales, and erosion control devices shall be removed from below the ordinary high water mark upon completion of the project. Small straw bales may be scattered upon the project site above the ordinary high water mark.

SUBMITTALS

Stormwater Pollution Plan

The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government prepared Stormwater Pollution Prevention Plan (SWPP). Once the SWPP modifications are approved, the Contractor shall file for coverage under EPA's Construction General Permit using the “eNOI” system. Refer to http://water.epa.gov/polwaste/npdes/stormwater/EPA-Construction-General-Permit.cfm.

SECTION 01560

ENVIRONMENTAL CONTROLS

GENERAL

SITE MAINTENANCE

The Contractor shall keep the work site, staging areas, and Contractor’s facilities clean and free from rubbish and debris. The Contractor staging area is noted on the drawings. Additional staging areas may be identified by the Contracting Officer and Inspector. Materials and equipment shall be removed from the site when they are no longer necessary. Upon completion of the work and before final acceptance, the work site shall be cleared of equipment, unused materials, and rubbish to present a clean and neat appearance. Staging areas and machine access areas created for project use will be decompacted and receive appropriate treatments (i.e. placement of small logs and brush).

CLEAN-UP:

a) Waste material, such as used erosion control devices, camping refuse, old culverts or found materials, of any kind will not be permitted to remain on the site of the work or on adjacent roads. Immediately upon such materials becoming unfit for use in the work, they shall be collected, carried off the site, and properly disposed of by the Contractor. There is the potential to find old mining refuse such as cables, culverts, and small garbage. This becomes the property of the Contractor and shall be removed from the site.

b) The Contractor may provide temporary restroom and cleanup facilities for Contractor’s employees and shall keep these areas clear of all refuse, rubbish, and debris that may accumulate from any source and shall keep them in a neat condition to the satisfaction of the Contracting Officer.

c) In the event that waste material, refuse, debris, and/or rubbish are not removed from the work by the Contractor, the Contracting Officer reserves the right to have the waste material, refuse, debris, and/or rubbish removed and the expense of the removal and disposal charged to the Contractor.

AIR POLLUTION CONTROL

The Contractor shall not discharge smoke, dust, and other contaminants into the atmosphere that violate the air pollution regulations for the area. The Contractor shall maintain construction vehicles and equipment in good repair. Exhaust emissions that are determined to be excessive by the Contracting Officer shall be repaired or replaced. If determined to be necessary by the Project Inspector, Contractor shall provide a water truck to manage project area dust.

NOISE CONTROL

The Contractor shall comply with all local controls and noise level rules, regulations, and ordinances which apply to any work performed pursuant to the Contract. If the requirements of this Section are more restrictive than those of the local regulations, the requirements of this Section shall govern.

Each internal combustion engine, used for any purpose related to this Contract, shall be enclosed and be equipped with a muffler of a type recommended by the manufacturer. No internal combustion engine shall be operated on the project without said muffler and enclosure.

STORMWATER AND EROSION CONTROL

1. A Stormwater Pollution Prevention Plan (SWPP) for construction activities has been prepared by the Forest Service. The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government’s SWPP 20 days prior to mobilizing to the site. Once the SWPP modifications are approved, the Contractor shall file for coverage under EPA's Construction General Permit using the “eNOI” system at least 14 calendar days prior to commencing earth-disturbing activities. Refer to http://water.epa.gov/polwaste/npdes/stormwater/EPA-Construction-General-Permit.cfm. The Contractor shall keep the SWPP on site; publicly post notice of permit coverage at the site; and shall follow all appropriate measures to implement the SWPP including:

a. Practices to prevent erosion and sedimentation associated with access roads, stream crossings, construction sites, borrow pit operations, haul roads, equipment and material storage sites, fueling operations and staging areas.

b. A spill containment and control plan with notification procedures, specific clean up and disposal instructions for different products, quick response containment and clean up measures that will be available on the site, proposed methods for disposal of spilled materials, and employee training for spill containment. A list of potential contaminants on the project site will be provided in the SWPP.

c. Practices to prevent construction debris from dropping into any stream or water body, and to remove any material that does drop with a minimum disturbance to the streambed and water quality.

2. Erosion control measures shall be in place prior to breaking ground. During construction, all erosion controls shall be inspected by the contractor daily to ensure they are working adequately.

a. If inspection shows that the erosion controls are ineffective, work crews will be mobilized immediately to make repairs, install replacements, or install additional controls as necessary.

b. Sediment must be removed from erosion controls once it has reached 1/3 of the exposed height of the control.

3. The Contractor shall not perform any excavation or earthwork of any type on the project until a written acceptance of the “Dewatering and Work Area Isolation Plan” and SWPP has been received and approved from the Contracting Officer and erosion control devices are on site. If in the opinion of the Contracting Officer, the plan does not sufficiently address the objectives (Section 02140); the Contractor shall revise the plan accordingly to the satisfaction of the Contracting Officer.

4. Contractor shall provide measures to prevent movement of soil into waterways or wetlands, e.g. filter bags, sediment traps or catch basins, vegetative strips, berms, jersey barriers, fiber blankets, bonded fiber matrices, geotextiles, mulches or compost, wattles and sediment fences, unless approved by the inspector.

a. Turbidity monitoring including personnel and equipment will be provided by the Forest Service.

b. If turbidity levels approach 50 NTUs over background levels 300 feet downstream of the point of discharge, the Contractor shall take measures to reduce turbidity before continuing.

5. Contractor shall provide measures to prevent stockpile erosion during rain events or when the stockpile site is not moved or reshaped for more than 48 hours, by surrounding piles with compost berms, covering piles with impervious materials or other equally effective methods.

6. Contractor shall provide measures to prevent construction vehicles from tracking sediment offsite or onto roadways where it is subject to washing into storm drains, waterways, or wetlands; including gravel access pads, wheel wash stations, or other equally effective methods.

7. Contractor shall not cross live water with heavy equipment.

MERCURY

If elemental mercury is found during project work, Contractor shall stop work in the immediate vicinity and make every reasonable effort to contain the material in such a manner that it will not reach surface or groundwater. The Contractor will contact the COR immediately.

SUBMITTALS

The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government prepared Stormwater Pollution Prevention Plan (SWPPP) as described in Section 01560.

Before starting work on the project, the Contractor shall submit, for acceptance by the Contracting Officer, a “Dewatering and Work Area Isolation Plan” that conforms to the provided…