AttachmentJ2_ColletteB_TECHNICAL_SPECIFICATIONS.docx
DOCX document 203 KB Posted
- Solicitation number
- AG-02RC-S-17-0062
About this file
Attachment J2 - Technical Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend1.doc | DOC document | |
| SiteTourNotes.docx | DOCX document | |
| AttachmentJ3_DrawingsColletteB_Sheets4.1to5.1.pdf | ||
| ColletteConstructionRFP.docx | DOCX document | |
| AttachmentJ3_DrawingsColletteB_Sheets1to4.pdf | ||
| AttachmentJ3_DrawingsColletteB_Sheets5.2_7.1.pdf | ||
| AttachmentJ3_DrawingsColetteB_Sheets7.2_8.4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA – Forest service Collette Mine Rehabilitation Technical Specifications
Last Revision 3/10/2017
Contents
TECHNICAL SPECIFICATIONS
| SECTION 1200 | 3 |
| MEASUREMENT AND PAYMENT | 3 |
| SECTION 01201 | 8 |
| PAY ITEMS | 8 |
| SECTION 01300 | 11 |
| SUBMITTALS | 11 |
| SECTION 01400 | 15 |
| CONSTRUCTION STAKING | 15 |
| SECTION 01505 | 16 |
| MOBILIZATION AND DEMOBILIZATION | 16 |
| SECTION 01560 | 20 |
| ENVIRONMENTAL CONTROLS | 20 |
| SECTION 01600 | 23 |
| PROTECTION OF MATERIALS | 23 |
| SECTION 01640 | 24 |
| GOVERNMENT SUPPLIED MATERIALS | 24 |
| SECTION 01720 | 27 |
| RECORD DRAWINGS | 27 |
| SECTION 02140 | 28 |
| WATER MANAGEMENT | 28 |
| SECTION 02200 | 32 |
| EARTHWORK | 32 |
| SECTION 02910 | 37 |
| WOODY VEGETATION PLANTING | 37 |
| SECTION 02929 | 39 |
| VEGETATIVE CUTTINGS | 39 |
| SECTION 02930 | 41 |
| SOIL SALVAGE AND PLACEMENT | 41 |
| SECTION 02931 | 43 |
| VEGETATION SALVAGE AND TRANSPLANT | 43 |
| SECTION 02932 | 46 |
| TREE SALVAGE | 46 |
| SECTION 05000 | 48 |
| LARGE WOOD STRUCTURES | 48 |
| SECTION 05001 | 51 |
| CHANNEL AND FLOODPLAIN FILL | 51 |
| SECTION 05009 | 54 |
| VEGETATED WOOD AND BRUSH FASCINE | 54 |
| SECTION 05010 | 56 |
| FLOODPLAIN ROUGHNESS | 56 |
SECTION 06010……..………………………………………………………………………………………………………………………………58
RENTAL EQUIPMENT……………………………………………………………………………………………………………………………..58
ii | Page
SECTION 1200
MEASUREMENT AND PAYMENT
PART 1 – Measurement of Work Take and record measurements and perform calculations to determine pay quantities for invoicing for work performed. Take or convert all measurements of work according to United States customary measure.
Unless otherwise specified, measure when the work is in place, complete, and accepted (Section 01720). Measure the actual work performed, except do not measure work outside the design limits or other adjusted or specified limits (staked limits). Measure structures to the lines shown on the plans or approved lines adjusted to fit field conditions.
Take measurements as described in Part 2 unless otherwise modified by the Measurement Subsection of the Section controlling the work being performed.
Remeasure quantities if it has been determined that any portion of the work is acceptable but has not been completed to the lines, grades, and dimensions shown on the plans or established by the CO.
Submit measurement notes to the CO within 24 hours of completing the work. For ongoing work, submit measurement notes weekly. When work is not complete, identify the measurement as being an interim measurement. Submit the final measurement when the installation is completed. Measurement notes form the basis of the Government’s receiving report. For lump sum items, submit documentation to support invoiced progress payment on a monthly basis.
Use an acceptable format for measurement records. As a minimum, include the following information in all records of measurement:
(a) Project name and number;
(b) Contract item number;
(c) Date the work was performed;
(d) Location of the work;
(e) Measured quantity;
(f) Calculations made to arrive at the quantity;
(g) Supporting sketch and details as needed to clearly define the work performed and the quantity measured;
(h) Name of persons measuring the work;
(i) Identification as to whether the measurement is interim or final; and
(j) Signed certification statement by the persons taking the measurements, performing the calculations, and submitting them for payment that the measurement and calculations are correct to the best of their knowledge and that the quantity being measured is subject to direct payment for the identified item under the contract.
Methods of Measurement One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM (Section 01201):
As defined in Part 2 and supplemented above.
a) Actual Quantities (AQ).
b) Design Quantities (DQ).
c) Lump Sum Quantities (LSQ).
PART 2 – Measurement Terms and Definitions
1. Acre (AC). 43,560 square feet. Make longitudinal and transverse measurements for area computations horizontally unless specified on the ground surface. Do not make deductions from the area computation for individual fixtures having an area of 500 square feet or less.
2. Actual Quantities (AQ). These quantities are determined from measurements of completed work.
3. Design quantity (DQ). The quantity to be paid is the quantity shown in the bid schedule. The design quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity. If there is evidence that a quantity specified as a design quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request, in writing, that the quantity be adjusted. Design quantities will be adjusted only when there are errors in the original design of 15% or more. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:
a) Changes in the work authorized by the CO.
b) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.
c) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.
4. Cubic yard (CY).
a) Cubic yard in place. Measure solid volumes by a method approved by the CO or by the average end area method as follows:
(a) Take cross-sections of the original ground and use with design or staked templates or take other comparable measurements to determine the end areas. Do not measure work outside of the established lines or slopes.
(b) If any portion of the work is acceptable but is not completed to the established lines and slopes, retake cross-sections or comparable measurements of that portion of the work. Deduct any quantity outside the designated or staked limits. Use these measurements to calculate new end areas.
(c) Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference lines between the end areas. Deduct any quantity outside the designed or staked limits.
b) Cubic yard in the hauling vehicle. Measure the cubic yard volume in the hauling vehicle using three-dimensional measurements at the point of delivery. Use vehicles bearing a legible identification mark with the body shaped so the actual contents may be readily and accurately determined. Before use, mutually agree in writing on the volume of material to be hauled by each vehicle. Vehicles carrying less than the agreed volume may be rejected or accepted at the reduced volume.
Level selected loads. If leveling reveals the vehicle was hauling less than the approved volume, reduce the quantity of all material received since the last leveled load by the same ratio as the current leveled load volume is to the agreed volume. Payment will not be made for material in excess of the agreed volume.
Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purposes if the conversion factors are mutually agreed to in writing.
c) Cubic yard in the structure. Measure according to the lines of the structure as shown on the plans except as altered by the CO to fit field conditions. Make no deduction for the volume occupied by reinforcing steel, anchors, weep holes, piling, or pipes less than 8 inches in diameter.
d) Cubic yard by metering. Use an approved metering system.
5. Each (EA). One entire unit. The quantity is the actual number of units completed and accepted.
6. Gallon. The quantity may be measured by any of the following methods:
a) Measured volume container.
b) Metered volume. Use an approved metering system.
c) Commercially packaged volumes.
7. Hour. Measure the actual number of hours ordered by the CO and performed by the contractor.
8. Linear foot. As applicable, measure the work along its length from end-to-end; parallel to the base or foundation; along the top; along the front face; or along the invert. Do not measure overlaps.
9. Lump sum quantity (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. Do not measure directly. The bid amount is complete payment for all work described.
10. Mile. 5,280 linear feet. Measure horizontally along the centerline of each roadway, approach road, or ramp.
11. Pound. Measure according to Part 3. If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.
12. Square foot. Measure on a plane parallel to the surface being measured.
13. Square yard. 9 square feet. Longitudinal and transverse measurements for area computations will be made horizontally. No deductions from the area computation will be made for individual fixtures having area of 9 square feet or less.
14. Station. 100 linear feet. Measure horizontally along centerline or reference line of each roadway, approach road, or ramp.
15. Ton. 2,000 pounds avoirdupois. Measure according to Part 3. No adjustment in a contract unit price will be made for variations in quantity due to differences in the specific gravity or moisture content.
PART 3 – Weighing Procedures and Devices.
Batch masses may be acceptable for determination of pay quantities when an approved automatic weighing, cycling, and monitoring system is included as part of the batching equipment.
When a weighing device is determined to indicate less than true mass, no additional payment will be made for material previously weighed and recorded. When a weighing device is determined to indicate more than true mass, all material received after the last previously correct weighing accuracy test will be reduced by the percentage of error in excess of 0.5 percent.
When material is proportioned or measured and paid for by mass, provide one of the following:
(a) Commercial weighing system. Use permanently-installed and certified commercial scales.
(b) Invoices. If bulk material is shipped by truck or rail and is not passed through a mixing plant, furnish a supplier's invoice with net mass or volume converted to mass. Periodic check weighing may be required.
PART 4 – Receiving Procedures.
When the method of measurement requires weighing or volume measurement in the hauling vehicle, furnish a person to direct the spreading and distribution of material and to record the location and placement of the material on the project. During the placement, maintain a record of each delivery and document it in an acceptable manner. Include the following information as applicable:
(a) Project identification;
(b) Contract pay item number and description;
(c) Location where placed;
(d) Date;
(e) Load number;
(f) Truck identification;
(g) Time of arrival;
(h) Mass or volume; and
(i) Spread person's signature.
Use an approved format for the delivery record(s). Furnish the original record(s) and a written certification of the delivery of the material at the end of each shift.
PART 5 – Scope of Payment Payment for all contract work is provided, either directly or indirectly, under the pay items shown in the bid schedule.
1. Direct payment. Payment is provided directly under a pay item shown in the bid schedule when one of the following applies:
a. The work is measured in the Measurement Subsection of the Section ordering the work, and the bid schedule contains a pay item for the work from the Section ordering the work.
b. The Measurement Subsection, of the Section ordering the work, references another Section for measuring the work and the bid schedule contains a pay item for the work from the referenced Section.
2. Indirect payment. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items shown in the bid schedule. This includes instances when the Section ordering the work references another Section for performing the work and the work is not referenced in the Measurement Subsection of the Section ordering the work.
Compensation provided by the pay items included in the contract bid schedule is full payment for performing all contract work in a complete and acceptable manner. All risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the contract pay items.
Work measured and paid for under one pay item will not be paid for under any other pay item.
The quantities shown in the bid schedule (Section 01201) are approximate unless designated as a design quantity. Limit pay quantities to the quantities staked, ordered, or otherwise authorized before performing the work. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.
SECTION 01201
| ITEM NO. |
| ITEM |
| METHOD OF MEASUREMENT |
| PAY UNIT |
| EST. QUANTITY |
| 1-001 |
| MOBILIZATION AND DEMOBILIZATION |
| LSQ |
| LS |
| 1 |
| 1-002 |
| CONSTRUCTION STAKING |
| LSQ |
| LS |
| 1 |
| 1-003 |
| WATER MANAGEMENT |
| LSQ |
| LS |
| 1 |
| 1-004 |
| SHRUB SALVAGE |
| DQ |
| AC |
| 0.9 |
| 1-005 |
| SOD SALVAGE |
| DQ |
| AC |
| 0.1 |
| 1-006 |
| SOIL SALVAGE FOR VEGETATIVE FILL |
| DQ |
| CY |
| 2060 |
| 1-007 |
| EARTHWORK |
| DQ |
| CY |
| 11,342 |
| 1-008 |
| HAUL EXCESS MATERAIL |
| AQ |
| CY |
| 7340 |
| 1-009 |
| VEGETATED WOOD AND BRUSH FASCINE |
| AQ |
| LF |
| 1030 |
| 1-010 |
| LARGE WOOD STRUCTURE |
| AQ |
| LF |
| 210 |
| 1-011 |
| RIFFLE CONSTRUCTION |
| DQ |
| CY |
| 1800 |
| 1-012 |
| FLOODPLAIN ROUGHNESS |
| DQ |
| AC |
| 2.0 |
| 1-013 |
| EXCAVATOR AND OPERATOR |
| AQ |
| HR |
| 20 |
| 1-014 |
| DUMP TRUCK AND OPERATOR |
| AQ |
| HR |
| 20 |
| 1-015 |
| BULLDOZER AND OPERATOR |
| AQ |
| HR |
| 20 |
PAY ITEMS
PART 1 – General Individual pay items will be paid in accordance with Section 01200 and Section 01201. Pay items and quantities are listed in the table below and in the contract package Bid Sheet. This section will outline the individual pay items and requirements of each.
PART 2 – Pay Items
Item 1-001 Mobilization and Demobilization The accepted quantity will be paid at the contract price per unit of measurement for Pay Item 1-001 shown in the bid schedule. Payment will be full compensation for the work prescribed in Section 01300, 01505. Progress payments for mobilization lump sum will be paid as follows:
(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 75 percent of the mobilization item will be paid.
(d) The remaining 25 percent of the mobilization bid item will be paid upon final acceptance of the project to include, the cleaning, sorting and restocking of the temporary bridge materials in the Missoula yard.
Item 1-002 Construction Staking The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-002. Payment will be full compensation for Construction Staking prescribed in Sections 01400 and others.
Item 1-003 Water Management The accepted quantities will be paid at the contract price per unit of measurement for pay item 1-003. Payment will be full compensation for the Water Management and Erosion Control work prescribed in Sections 01300, 01560, 02140.
Item 1-004 Shrub Salvage The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-004 Payment will be full compensation for the Shrub Salvage work prescribed in Sections 01300, 01400, 02931.
Item 1-005 Sod Salvage The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-005.Payment will be full compensation for the Sod Salvage work prescribed in Sections 01300, 01400, 02931.
Item 1-006 Soil Salvage for Vegetative Fill The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-006. Payment will be full compensation for the Soil Salvage for Vegetative Fill work prescribed in Sections 01400, 02200, 02930.
Item 1-007 Earthwork The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-007. Payment will be full compensation for the Earthwork work prescribed in Sections 01400, 01560, 02140, 02200, 02930, 05000, 05001, 05009, 05010.
Item 1-008 Haul Excess Material The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-008. Payment will be full compensation for the Haul Excess Material work prescribed in Sections 01300, 01400, 01560, 01600, 01640, 02140, 02200, 02910, 02929, 02931, 02932, and 05009.
Item 1-009 Vegetated Wood and Brush Fascine The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-009. Payment will be full compensation for the Vegetated Wood and Brush Fascine work prescribed in Sections 01300, 01400, 01560, 01600, 01640, 02140, 02200, 02910, 02929, 02931, 02932, and 05009.
Item 1-010 Large Wood Structure The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-010. Payment will be full compensation for the Large Wood Structure work prescribed in Sections 01300, 01400, 01560, 01600, 01640, 02140, 02200, 02929, 02931, 02932, and 05000.
Item 1-011 Riffle Construction The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-011. Payment will be full compensation for the Riffle Construction work prescribed in Sections 01300, 01400, 01560, 01600, 01640, 02200, 02900, 05001 and 05010.
Item 1-012 Floodplain Roughness The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-012. Payment will be full compensation for the Floodplain Roughness work prescribed in Sections 01300, 01400, 01560, 01600, 01640, 02200, 02900, 05001 and 05010.
Item 1-013 Rate for 300 Class Excavator and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-012. Payment will be full compensation for work performed in support of Pay Items 1-001 through 1-012.
Item 1-014 Rate for Dump Truck and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-013. Payment will be full compensation for work performed in support of Pay Items 1-001 through 1-012.
Item 1-015 Rate for Bulldozer and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay item 1-014. Payment will be full compensation for work performed in support of Pay Items 1-001 through 1-012.
SECTION 01300
SUBMITTALS
PART 1 – GENERAL
1.1 SCOPE
Submittals covered by these requirements include manufacturers’ information, test procedures, test results, samples, requests for substitutions, and miscellaneous work-related submittals. Submittals shall also include, but not be limited to, rock sources, and fabricated items. The Contractor shall furnish all drawings, specifications, descriptive data, certificates, samples, tests, methods, and schedules and other instructions as specifically required in the contract documents to demonstrate fully that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the contract documents.
1.2 CONTRACTOR’S RESPONSIBILITIES
The Contractor shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment or method of work shall be as described in the submittal. The Contractor shall verify that all features of all products conform to the specified requirements. Submittal documents shall be clearly edited to indicate only those items which are being submitted for review. All extraneous materials shall be crossed out or otherwise removed. The Contractor shall ensure that there is no conflict with other submittals and notify the Contracting Officer in each case where his submittal may affect the work of another contractor. The Contractor shall coordinate submittals among his subcontractors and suppliers including those submittals complying with unit responsibility requirements specified in applicable technical sections.
The Contractor shall coordinate submittals with the work so that work will not be delayed. The Contractor shall coordinate and schedule different categories of submittals, so that one will not be delayed for lack of coordination with another. No extension of time will be allowed because of failure to properly schedule submittals. The Contractor shall not proceed with work related to a submittal until the submittal process is complete. This requires that submittals for review and comment shall be returned to the Contractor stamped “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED.”
The Contractor shall certify on each submittal document that he has reviewed the submittal, verified field conditions, and complied with the contract documents.
The Contractor may authorize in writing a material or equipment supplier to deal directly with the Contracting Officer with regard to a submittal. These dealings shall be limited to contract interpretations to clarify and expedite the work.
1.3 STANDARD COMPLIANCE
1. When materials or equipment must conform to the standards of organizations such as, but not limited to, the American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), National Electrical Manufacturers Association (NEMA) and Underwriter’s Laboratories (UL) documents showing, or proving, conformance shall be submitted.
2. If an organization uses a label or listing to indicate compliance with a particular standard, the label or listing will be acceptable evidence, unless otherwise specified in the individual Sections. In lieu of the label or listing, the Contractor shall submit a certificate from an independent testing organization, which is competent to perform acceptable tests, and is approved by the Contracting Officer. The certificate shall state that the item has been tested in accordance with the specified organization’s standard. For materials and equipment whose compliance with organizational standards or specifications is not regulated by an organization using its own listing or label as proof of compliance, a certificate of compliance from the manufacturer shall be submitted for approval. The certificate shall identify the manufacturer, the product, and the referenced standard and shall state that the manufacturer certifies that the product conforms to all requirements of the project Specification and of the referenced standards listed.
1.4 REVIEW OF CONTRACTOR’S INFORMATION
A. When review and checking for acceptance is required of any drawing or information regarding materials and equipment, the Contractor shall prepare or secure, and submit for review, two (2) copies. The Contracting Officer, after taking appropriate action, will return (1) marked copies to the Contractor.
Within 7 calendar days after receipt of said submittal copies, the Contracting Officer will return the marked copies indicating one of the following four (4) actions:
a. If review and checking indicates no exceptions, copies will be returned marked “NO EXCEPTIONS TAKEN” and work may begin immediately on incorporating the material and equipment covered by the submittal into the work.
b. If review and checking indicates limited corrections are required, copies will be returned marked “MAKE CORRECTIONS NOTED”. Work may begin immediately on incorporating into the work the material and equipment covered by the corrected submittal.
c. If review and checking indicates insufficient, or incorrect data, has been submitted, copies will be returned marked, “AMEND AND RESUMIT”. No work may begin on incorporating the material and equipment covered by this submittal into the work until the submittal is revised, resubmitted, and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.
d. If review and checking indicates the material and equipment submittal is unacceptable, copies will be returned marked “REJECTED-RESUBMIT”. No work may begin on incorporating the material and equipment into the work until a new submittal is made and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.
Approval by the Contracting Officer shall not relieve Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with requirements of this Contract.
1.5 EFFECT OF REVIEW OF CONTRACTOR’S SUBMITTALS
Review of contract drawings, methods of work, or information regarding materials or equipment the Contractor proposes to provide, shall not relieve the Contractor of his responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Contracting Officer, or by any officer or employee thereof, and the Contractor shall have no claim under the contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. A mark of “NO EXCEPTIONS TAKEN or MAKE CORRECTIONS NOTED” shall mean that the Contracting Officer has no objection to the Contractor, upon his own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.
PART 2 – PRODUCTS
2.1 MANUFACTURER’S DATA
Submittals for each manufactured item shall be comprised of manufacturer’s descriptive literature, drawings, diagrams, performance and characteristic curves, and catalog cuts. Manufacturer’s name, trade name, model or catalog number, nameplate data, size, layout dimensions, capacity, project specification references, and any other additional information necessary to establish contract compliance shall be clearly indicated.
PART 3 – EXECUTION
| 3.1 | SUBMITTAL PROCEDURE | |||
| 1. | At least 7 calendar days prior to the Contractors need for approval, contractor shall forward to the Contracting Officer all submittals required by the individual Sections of the Specifications. | |||
| 2. | All submittals shall be identified by submittal number and specification section number on the letter of transmittal. Submittals shall be numbered consecutively and resubmittals shall have a letter suffix. For example: | |||
| a. | 1st submittal: | 05001 | ||
| b. | 1st resubmittal: | 05001A | ||
| c. | 2nd resubmittal: | 05001B, etc. | ||
| 3.2 | CONTRACTOR SUBMITTALS |
Items to be submitted are specified in individual Sections of these Specifications. Submittals for each Section shall be bound together in one book. Book shall have numbered tab dividers for each item. Submittals that are related to, or affect, each other shall be forwarded simultaneously as a package to facilitate coordinated review. Uncoordinated submittals will be rejected. Do not combine unrelated materials in the same submittal. Submittals shall be arranged in same order as they appear in the Specification Section. Items shall be clearly marked with the same identification number as indicated on the drawings. The Contractor shall include submittal time appropriate within each item of work on the Construction Schedule. The Contracting Officer will receive submittals at the preconstruction meeting.
At a minimum, the Contractor shall provide project submittals as shown on the following Submittal Log. Submittal requirements are listed in the Technical Specifications and Drawings.
Submittal Log
| Submittal # |
| Item |
| Type of Submittal |
| Requirement Location |
| Incidental to Bid Item |
| 1 |
| Construction Staking |
| Narrative and notification |
| Specification 01400 |
| Construction Staking 1-002 |
| 2 |
| Equipment Inspection |
| Notification |
| Specification 01505 |
| Mobilization |
1-001
| 3 |
| Stormwater Pollution Prevention Plan |
| Drawing and narrative/EPA permit process |
| Specification 01560 |
| Mobilization |
1-001
| 4 |
| Access and Staging Plan |
| Drawing and Narrative |
| Specification 01505 and Drawing 4.2 |
| Mobilization |
1-001
| 5 |
| Water Management Plan |
| Drawing and narrative |
| Specification 02140 |
Drawing 4.3 Water Management 1-003
| 6 |
| Turbidity Monitoring |
| Notification |
| Specification 01560 |
Drawing 4.3 Water Management 1-003
| 7 |
| Vegetation Cuttings and Transplants |
| Notification |
| Specification 02929 |
Drawing 8.1 Vegetated Wood and Brush Faschine 1-009
| 8 |
| Plant Nursery Care Plan |
| Narrative |
| Specifications 02910, 02929 and 02931 |
Drawing 4.4 Shrub Salvage 1-004
| 9 |
| Large Wood Structures |
| Notification |
| Specification 05000 |
Drawing 8.2 Large Wood Structure 1-010
| 10 |
| Rock Gradation |
| Data or example product and |
notification
| Specification 05001 |
| Mobilization |
1-001
| 11 |
| Vegetated Wood and Brush Fascine |
| Notification |
| Specification 05009 |
Drawing 8.1 Vegetated Wood and Brush Fascine 1-009
| 12 |
| Riffle and streambed Construction |
| Drawing and Narrative |
| Specification 05001 Drawing 8.4 |
| Riffle Construction 1-011 |
Regrading/ filling of old channel
| Notification |
| Specification 02200 |
Drawings 5.0 to 5.3 Earthwork 1-007
| 14 |
| Floodplain Roughness |
| Notification |
| Specification 05010 |
Drawing 8.3 Floodplain Roughness 1-012
***END OF SECTION***
SECTION 01400
CONSTRUCTION STAKING
PART 1 – GENERAL
1.1 CONSTRUCTION STAKING
The Contractor shall provide survey staking for construction. The Contracting Officer will provide survey control and grading surfaces for equipment with GPS machine control capability. When the Contractor requires horizontal and vertical control the contractor shall notify the Contracting Officer of this requirement a minimum of three working days in advance of this need.
1.2 STAKEOUT AND MEASUREMENT TO BE PERFORMED BY CONTRACTOR
The Contracting Officer will provide an initial layout of the restoration design in consultation with the Contractor. After the initial layout, the Contractor shall be responsible for staking reference points/markers to complete the work from the initial control points and grading surfaces provided by the Contracting Officer, and shall be responsible for all measurements required for the execution of the work. The Contractor shall protect all stakes and shall pay for the time and materials required to replace stakes that have been disturbed or obliterated if necessary.
The Contractor shall use information provided by the Contracting Officer to stake the boundaries of construction extents, access roads, staging areas, heritage resources, materials salvage areas, vegetation preservation areas, grading extents and structure locations. The Contracting Officer shall approve staking boundaries prior to commencement of work. New channel stationing shall be staked every 100’ with offsets as necessary. In addition, the Contactor shall stake reference points outside the construction extents of any existing survey control points (see Sheet 4.0 on project drawings). Upon completion of the project, the original survey control points will be restaked.
The Contractor shall furnish at the Contractor’s own expense, such stakes, equipment, tools, materials, and all labor as required in stakeout of any parts of the work from the control points and grading surfaces provided by the Contracting Officer.
The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
SECTION 01505
MOBILIZATION AND DEMOBILIZATION
PART 1 – GENERAL
1.1 MOBILIZATION
Mobilization shall consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the site; for the establishment of all facilities necessary for work on the project; and for all other work and operations which must be performed, or costs incurred prior to beginning work, on the various items on the project site. Mobilization includes obtaining project-specific bonds and obtaining any permits, including the EPA’s Construction General Permit NOI (electronic NOI system, “eNOI”) for stormwater runoff, not provided by the Contracting Officer.
Mobilization shall also include the construction of temporary ramps and access ways, temporary bridge(s), staging areas, temporary roads, grading, temporary fencing, and the necessary preparatory work required to allow for the safe and stable movement of all vehicles that are required to construct the improvements outlined in the Contract Documents.
| 1. | Notify the Contracting Officer in writing at least 72 hours before moving any construction equipment onto the National Forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Subsequent move-ins of equipment shall be treated the same as the initial move-in and will require notification. |
| 2. | All equipment shall be washed prior to mobilization to the Forest to minimize the introduction of foreign materials and fluids to the project site. All equipment shall be free of oil, hydraulic fluid, and diesel fuel leaks. To prevent invasion of noxious weeds or the spread of whirling disease spores, all equipment shall be power washed or cleaned to remove all dirt, plant parts and material prior to mobilization. Truck beds and dump boxes hauling to the project site shall also be cleaned prior to entering the Forest. It will be the contractor's responsibility to insure that adequate measures have been taken. Equipment shall be inspected by the designated COR or Inspector prior to mobilizing to the Forest. Only construction equipment inspected by the Forest Service will be allowed to operate within the project area. |
| 3. | Equipment shall be in a well-maintained condition to minimize the likelihood of a fluid leak. Any leaks or accumulations of grease would be corrected before entering the project area. If a fluid leak does occur, the project inspector and COR shall be notified immediately, and all work ceased until the leak has been rectified. At all times during the construction phase, fluid spill containment equipment adequately sized for specific quantities of fuel shall be present on-site and ready for deployment should an accidental spill occur. Fuel spill kit shall include an oil-absorbing floating boom and absorbent pads. Contractor and Contractor’s representatives shall be knowledgeable on use of the spill containment equipment. Project inspector reserves the right to refuse equipment that does not meet criteria. |
| 4. | Equipment that will be used in live water shall utilize hydraulic fluid that is non-toxic to salmonids[footnoteRef:1]. [1: The following criteria should be met to determine if a hydraulic fluid is nontoxic to salmonids during acute exposure: (a) The test species used should be a salmonid (most often this will be rainbow trout, but occasionally Chinook salmon or coho salmon are tested); (b) The test duration should be 96 hours; (c) The test should be conducted using the water accommodated fraction (WAF) (the WAF is used in testing hydrophobic materials to provide a "worst case scenario" for exposure to aquatic organisms); and (d) The value of the LC50 should be >1000 mg/L. Several products on the market meet these specifications. |
| 5. | All construction equipment shall be staged in a location and manner to minimize air, soil and water pollution. Storage of fuel and lubricants - all fuel and lubricants shall be stored in containers and areas that are in conformance with the Idaho State Department of Environmental Quality, NMFS and USFWS biological opinion terms and conditions, and local regulations. |
| 6. | Servicing and refueling equipment - all fuel and lubricants used in the servicing of construction equipment shall be done in a manner that avoids spills and over filling and shall be at least 150 feet from all waterbodies. Stationary power equipment, such as generators, within 150 feet of the water shall be diapered to prevent leaks. All power equipment within 150 feet of the water shall be inspected daily for fluid leaks and repaired. The contractor must keep daily inspection reports in a diary. |
| 7. | The Idaho State Department of Environmental Quality shall be notified immediately of any spill and the operator shall contain the spillage. If a spill of chemical pollutants such as fuel or hydraulic fluid should occur, immediately attempt to contain the spilled material. The following procedures shall be followed: |
a. for spillage on land, construct earthen berms or use other suitable barricade material of sufficient size to contain the spell and keep it from spreading.
b. for spillage on water, attempt to isolate and contain the spilled material. Commercial booms or other suitable materials shall be kept on site during construction to contain fuel and oil spills on water.
| 8. | Sanitary facilities - sanitary facilities such as chemical toilets shall be located at least 150 feet from water bodies to prevent contamination of surface or subsurface water. |
| 9. | A description of hazardous materials that will be used including inventory, storage and handling procedures will be available on site. |
1.2 SITE PREPARATION
1. Existing Conditions The Contractor shall determine the actual condition of the site as it affects this portion of the work.
2. Protection of Existing Facilities Site preparation shall not damage existing structures, landscaping, fencing, gates, or vegetation adjacent to the areas designated for site preparation. The Contractor shall repair or replace any and all damaged property.
3. Vegetation Preservation Preservation of existing vegetation and trees is of utmost importance. The Contractor will stake and walk the entire site with the Contracting Officer to clearly mark the clearing limits and vegetation to be saved or salvaged.
4. Clearing and Grubbing All areas comprising the work shall be cleared and grubbed to a depth necessary to remove objectionable material of any kind.
| 1.3 | DEMOBILIZATION AND SITE RECLAMATION |
| 1. | Demobilization shall consist of work and operations necessary to disband all mobilized items and clean up the site. The removal of all temporary ramps, access ways, roads, signs, temporary fencing, construction debris including rock chips, wood debris, construction stakes, and other construction-related refuse, and temporary facilities or works and the restoration of surfaces to an equal or better than existing condition shall also be included as part of demobilization. |
| 2. | Site reclamation is included under demobilization. Site reclamation includes reclamation of areas disturbed during construction, including staging areas, permanent fencing, and temporary access roads. Staging areas shall be decompacted and graded to match elevation specified on the plan sheets. |
| 3. | All damaged or disturbed streambanks are to be restored to a natural slope pattern and profile for establishment of permanent woody vegetation. Rock, woody materials and other natural construction materials used for the project shall be obtained beyond the bankfull elevation and at least 150 feet from any waters of the state, except for native materials obtained from within the project footprint to be stockpiled and reused on site. Leave native materials, e.g., down wood, where they are found, if possible. If native materials (e.g., downed wood) are destroyed, replace them with a functional equivalent during site restoration. |
| 4. | Stockpiled materials (i.e. trees, vegetation, topsoil, and other excavated material from restoration project areas) shall be used as specified in the plan sheets. Short-term stabilization measures will be implemented until permanent erosion control measures (plant restoration) are effective, and include placement of brush and small logs on recently graded surfaces, as specified in the plan sheets. |
| 1.4 | SUBMITTALS |
The Contractor shall submit a project access and staging plan for approval by the Contracting Officer. The plan shall identify temporary access route locations, stream crossing locations and number of crossings needed.
Stormwater Pollution and Prevention Plan The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government prepared Stormwater Pollution Prevention Plan (SWPP). Once the SWPP modifications are approved, the Contractor shall file for coverage under EPA's Construction General Permit using the “eNOI” system. Refer to http://water.epa.gov/polwaste/npdes/stormwater/EPA-Construction-General-Permit.cfm. The SWPP describes sediment and erosion controls and pollution prevention practices, and includes the following requirements:
1. Post public notice of permit coverage in close proximity to the project site. At a minimum, the notice must include the NPDES Permit tracking number and a contact name and phone number for obtaining additional project information.
2. Ensure that all required erosion and sediment controls are in place and remain in effective operating condition during permit coverage. Including:
a) Ground disturbance will not occur during wet conditions (i.e., during or immediately following rain events). Ground disturbance will not occur until erosion control materials are on site. Such materials include pumps, sand bags, silt fence and other materials listed in Stormwater Pollution Prevention Plan. Sequence or schedule work to reduce exposed bare soil subject to wind erosion. Water may be used to control dust.
b) Sediment will be removed from erosion controls once the sediment has reached one-third of the exposed height of the control.
3. Implement a spill prevention and response plan which includes procedures for stopping, containing, and cleaning up accidental spills, leaks, and other releases as well as procedures for notification. Including:
a) Control and cleanup instructions for products on site.
b) Equipment and measures to be stored on site and used to contain spills.
4. Inspect all erosion and sediment controls and document findings according to EPA’s Construction General Permit requirements. If inspections show that the pollution controls are ineffective, the Contractor will immediately mobilize work crews to repair, replace, or reinforce controls as necessary.
5. The Contractor shall submit information on Rock Gradation including material source location, size, description, and gradation.
6. Submit in accordance with Section 01300.
| 1.5 | RELATED WORK: |
| A. | Section 01300, Submittals |
| B. | Section 01560, Environmental Controls |
| C. | Section 01600, Protection of Materials |
| D. | Section 02160, Site Preparation |
| E. | Section 05001, Rock Gradation |
PART 2 – PRODUCTS
Materials and product specifications are included on drawings and in related specifications.
PART 3 - EXECUTION
Not used.
SECTION 01560
ENVIRONMENTAL CONTROLS
PART 1 – GENERAL
1.1 SITE MAINTENANCE
The Contractor shall keep the work site, staging areas, and Contractor’s facilities clean and free from rubbish and debris. The Contractor staging area is noted on the drawings. Materials and equipment shall be removed from the site when they are no longer necessary. Upon completion of the work and before final acceptance, the work site shall be cleared of equipment, unused materials, and rubbish to present a clean and neat appearance. Staging areas and machine access areas created for project use will be decompacted and receive appropriate treatments (i.e. placement of small logs and brush).
1. CLEAN-UP:
a) Waste material of any kind will not be permitted to remain on the site of the work or on adjacent roads. Immediately upon such materials becoming unfit for use in the work, they shall be collected, carried off the site, and properly disposed of by the Contractor.
b) The Contractor may provide temporary restroom and cleanup facilities for Contractor’s employees and shall keep these areas clear of all refuse, rubbish, and debris that may accumulate from any source and shall keep them in a neat condition to the satisfaction of the Contracting Officer.
c) In the event that waste material, refuse, debris, and/or rubbish are not so removed from the work by the Contractor, the Contracting Officer reserves the right to have the waste material, refuse, debris, and/or rubbish removed and the expense of the removal and disposal charged to the Contractor.
1.2 AIR POLLUTION CONTROL
The Contractor shall not discharge smoke, dust, and other contaminants into the atmosphere that violate the air pollution regulations for the area. The Contractor shall maintain construction vehicles and equipment in good repair. Exhaust emissions that are determined to be excessive by the Contracting Officer shall be repaired or replaced. If determined to be necessary by the Project Inspector, Contractor shall provide a water truck to manage project area dust.
1.3 NOISE CONTROL
1. The Contractor shall comply with all local controls and noise level rules, regulations, and ordinances which apply to any work performed pursuant to the Contract. If the requirements of this Section are more restrictive than those of the local regulations, the requirements of this Section shall govern.
2. Each internal combustion engine, used for any purpose related to this Contract, shall be enclosed and be equipped with a muffler of a type recommended by the manufacturer. No internal combustion engine shall be operated on the project without said muffler and enclosure.
1.4 STORMWATER AND EROSION CONTROL
1. A Stormwater Pollution Prevention Plan (SWPP) for construction activities has been prepared by the Forest Service. The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government’s SWPP. Once the SWPP modifications are approved, the Contractor shall file for coverage under EPA's Construction General Permit using the “eNOI” system at least 14 calendar days prior to commencing earth-disturbing activities. Refer to http://water.epa.gov/polwaste/npdes/stormwater/EPA-Construction-General-Permit.cfm. The Contractor shall keep the SWPP on site; publicly post notice of permit coverage at the site; and shall follow all appropriate measures to implement the SWPP including:
a) Practices to prevent erosion and sedimentation associated with access roads, stream crossings, construction sites, borrow pit operations, haul roads, equipment and material storage sites, fueling operations and staging areas.
b) A spill containment and control plan with notification procedures, specific clean up and disposal instructions for different products, quick response containment and clean up measures that will be available on the site, proposed methods for disposal of spilled materials, and employee training for spill containment. A list of potential contaminants on the project site will be provided in the SWPP.
c) Practices to prevent construction debris from dropping into any stream or water body, and to remove any material that does drop with a minimum disturbance to the streambed and water quality.
2. Erosion control measures shall be in place prior to commencing construction. During construction, all erosion controls shall be inspected by the contractor daily to ensure they are working adequately.
a) Erosion Control Materials including pumps, straw bales and other materials as listed in the SWPP will be onsite before the work commences.
b) If inspection shows that the erosion controls are ineffective, work crews will be mobilized immediately to make repairs, install replacements, or install additional controls as necessary.
c) Sediment must be removed from erosion controls once it has reached 1/3 of the exposed height of the control.
3. The Contractor shall not perform any excavation or earthwork of any type on the project until a written acceptance of the “Water Management Plan” has been received from the Contracting Officer. If in the opinion of the Contracting Officer, the plan does not sufficiently address the objectives (Section 02140); the Contractor shall revise the plan accordingly to the satisfaction of the Contracting Officer.
4. When working instream, activities shall be staged so that only one area would be isolated and worked at a time.
5. Contractor shall provide measures to prevent movement of soil into waterways or wetlands, e.g. filter bags, sediment traps or catch basins, vegetative strips, berms, jersey barriers, fiber blankets, bonded fiber matrices, geotextiles, mulches or compost, wattles and sediment fences.
a) Turbidity monitoring including personnel and equipment will be provided by the Contracting Officer.
b) If turbidity levels exceed 50 NTUs over background levels 600 feet downstream of the point of discharge, the Contractor must stop work and take measures to reduce turbidity before continuing.
6. Contractor shall provide measures to prevent stockpile erosion during rain events or when the stockpile site is not moved or reshaped for more than 48 hours, by surrounding piles with compost berms, covering piles with impervious materials or other equally effective methods.
7. Contractor shall provide measures to prevent construction vehicles from tracking sediment offsite or onto roadways where it is subject to washing into storm drains, waterways, or wetlands; including gravel access pads, wheel wash stations, or other equally effective methods.
8. Contractor shall install removable pads or mats to prevent soil compaction in all temporary construction access points and staging areas in riparian or wetland areas.
9. Contractor shall only cross live water with excavator at designated locations. Stream crossing shall be perpendicular to the stream channel and will employ mats or logs in the channel for the excavator to cross over to avoid disturbing stream channel bottom.
a) Total number of excavator stream crossings is limited to 10 times (5 round trips) for entire project duration.
1.5 MERCURY MITIGATION
1. If elemental mercury is found during project work, Contractor shall stop work in the immediate vicinity and make every reasonable effort to contain the material in such a manner that it will not reach surface or groundwater. The CO shall be notified immediately.
1.6 SUBMITTALS
1. The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government prepared Stormwater Pollution Prevention Plan (SWPP). Once the SWPP modifications are approved, the Contractor shall file for coverage under EPA's Construction General Permit using the “eNOI” system (http://water.epa.gov/polwaste/npdes/stormwater/EPAs-Electronic-Construction-General-Permit-Notice-of-Intent-eNOI-Home-Page.cfm).