| CONSTRUCTION RFP thru FAC 86_1 – 01/01/2016 | AG-02RC-S-16-0100 |
| Quartz Creek AOP Culvert Replacement |
| CONSTRUCTION RFP thru FAC 2005-86_1 – 01/01/2016 | AG-02RC-S-16-0100 |
| Quartz Creek AOP Culvert | |
| Page 25 of 73 |
OFFEROR'S COPY
NOTE: Attached forms must be completed and submitted intact.
Issuing Office:
U.S. Department of Agriculture; Forest Service Region 1 Acquisition Management North Fork Office
12730 HWY 12
Orofino, ID 83544
Offers Are Solicited For:
QUARTZ CREEK AOP CULVERT
REPLACEMENT
Priest River RD; Idaho Panhandle NF Bonner County, Idaho
| Solicitation No. RFP AG-02RC-S-16-0100 |
| HELP PREVENT FOREST FIRES |
IMPORTANT - NOTICE TO OFFEROR
1. This is a complete copy. Information and instructions for submission of proposals as well as contract provisions and specifications are contained in this OFFEROR REFERENCE COPY. This copy should be retained by offerors.
2. Note: If the offeror expects the total value of $150,000, an offer guarantee (Bid Bond) IS REQUIRED. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.)
FS-6300-45 (11/79)
| CONSTRUCTION RFP thru FAC 86_1 – 01/01/2016 | AG-02RC-S-16-0100 |
| Quartz Creek AOP Culvert Replacement |
TABLE OF CONTENTS
Page(s)
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM 1 - 2
SECTION B - SUPPLIES OR SERVICES AND PRICES 4 - 5
| B- 1 - Schedule of Items |
| B- 2 – Price Proposal Instructions |
| B- 3 – Payment for Bond Premiums |
| B- 4 – Offer Submittal |
| B- 5 – Additional Classification Required – Davis-Bacon General Wage Decision |
| B- 6 – Idaho Use Tax |
SECTION C - DESCRIPTION/SPECIFICATIONS 6 - 11
| C- 1 – Project Description and Location |
| C- 2 – Government Furnished Material |
| C- 3 - Standard Specifications |
| C- 4 – Forest Service Supplemental Specifications |
| C- 5 – Construction Plans |
| C- 6 - Biobased Product Utilization |
SECTION E - INSPECTION AND ACCEPTANCE 12 - 13
E- 1 – Inspection of Construction
SECTION F - DELIVERIES OR PERFORMANCE 14
| F- 1 - Clauses Incorporated by Reference |
| F- 2 - Commencement, Prosecution, and Completion of Work Alt I |
SECTION G – CONTRACT ADMINISTRATION DATA 15
| G- 1 – Post Award Conference |
| G- 2 – Contracting Officer’s Representative |
| G-3 – Contractor Quality Control |
SECTION H - SPECIAL CONTRACT REQUIREMENTS 16 - 26
| H- 1 - Clauses Incorporated by Reference |
| H- 2 - Physical Data |
| H- 3 – Key Personnel |
| H- 4 – Barricades, Warning Signs, and Other Devices |
| H- 5 – Environmental Protection |
| H- 6– Noxious Weed Control |
| H- 7 – Fire Control |
| H- 8 – Landscape Preservation |
H- 9 - Invoice Processing Platform (IPP)
| H-10 - Contractor Performance Assessment Reporting System |
| H- 11 – Contractor Workforce Certification |
H- 12 – Idaho Worker’s Compensation Law H- 13 - Loss, Damage, or Destruction H- 14 - Incidental Payment Items
| H- 15 - Conformity with Drawings and Specifications |
| H- 16 - Local Material Sources |
| H- 17 - Samples, Tests, Cited Specifications |
H- 18 – Conditions on Use of Presmises
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES 27 - 41
| I- 1 - Clauses Incorporated by Reference |
| I- 2 – Variation in Estimated Quantities |
I- 3 – Minimum Wages Under Executive Order 13658 I- 4 - Affirmative Procurement of Biobased Products Under Service and Construction Contracts
| I- 5 - Buy American - Construction Materials |
| I-6 - Bid Guarantee |
| I-7 - Performance and Payment Bonds - Construction |
| I-8 - Alternative Forms of Security |
| I-9 – Federal, State and Local Taxes |
| I-10 - Reimbursement For Bond Premiums - Fixed Price Construction Contracts |
| I-11 – Permits and Responsibilities |
| I-12 - Alterations In Contract |
| I-13 - Order of Precedence - Construction |
PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS 42 - 57
| J- 1 - Wage Determination - ID160040 04/01/2016 ID40 |
| J- 2 - Forest Service Supplemental Specifications entitled “Quartz Creek AOP Culvert_334-0.1_FSSS_Specifications.pdf” (Separate www.FBO.gov upload file) |
| J- 3 - Construction Plans entitled “Quartz Creek AOP Culvert Plans_Drawings.pdf” (Separate www.FBO.gov upload file) |
| J- 4 - State of Idaho Certificate of Verification of Workers’ Compensation Insurance |
PART IV - REPRESENTATIONS AND INSTRUCTIONS
| SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER | 57 - 64 |
| STATEMENTS OF OFFERORS AND RESPONDENTS |
K- 1 - Annual Representations and Certifications K- 2 - Commercial and Government Entity Code Reporting K- 3 – Information Regarding Responsibility Matters K- 4 - Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction Alternate I
| SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS | 65 – 71 |
| AND RESPONDENTS |
| L- 1 - Solicitation Provisions Incorporated by Reference |
| L- 2 - System for Award Management |
| L- 3 - Inquiries |
| L- 4 - Instructions for the Preparation of Technical and Business Proposals |
| L- 5 - Amendments to Proposals |
| L- 6 - Type of Contract |
| L- 7 – Construction Wage Rate Requirements – Secondary Site of Work |
| L- 8 - Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity |
for Construction
| L- 9 - Notice of Buy American Requirements - Construction Materials |
| L-10 - Service of Protest |
| L-11 - Site Visit (Construction) |
| L-12 - Preparation of Proposals – Construction |
| L -13 – Authorized Deviation in Provisions |
SECTION M - EVALUATION FACTORS FOR AWARD 71-73
| M- 1 - Evaluation Factors |
| M- 2 - Award Statement |
| CONSTRUCTION RFP thru FAC 86_1 – 01/01/2016 | AG-02RC-S-16-0100 |
| Quartz Creek AOP Culvert Replacement |
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
RFP AG-02RC-S-16-0100
2. TYPE OF SOLICITATION
|_| SEALED BID (IFB)
|_| NEGOTIATED (RFP)
3. DATE ISSUED
07/12/2016
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
804601
6. PROJECT NO.
| 7. ISSUED BY | CODE |
| 8. ADDRESS OFFER TO |
USDA, Forest Service
IMAT
North Fork Office
12730 HWY 12
Orofino, ID 83544
USDA, Forest Service
IMAT
North Fork Office
12730 HWY 12
Orofino, ID 83544
| 9. FOR INFORMATION |
| CALL: |
| a. NAME |
DARREN ZYCHEK: zychek@fs.fed.us
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(208) 476-8224
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
QUARTZ CREEK AOP CULVERT REPLACEMENT
Priest Lake Ranger District Idaho Panhandle National Forests Bonner County, Idaho
Price Range: The Government’s estimate is between $50,000 and $150,000.
**FAXED OFFERS ARE NOT ACCEPTABLE. ORIGINAL BID BONDS ARE REQUIRED. OFFERS MUST BE MAILED OR HAND-CARRIED AND RECEIVED BY FRIDAY, AUGUST 12, 2016 AT 2:30 PM LOCAL TIME.
11. The Contractor time shall begin upon receipt of contract |_| notice to proceed and shall be completed no later than October 15, 2016. This performance period is |_| mandatory, |_| negotiable. (See Section F, Clause 52.211-10, Alt I)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12b.)
| |_| YES | |_| NO | |
| 12b. CALENDAR DAYS |
| 13. ADDITIONAL SOLICITATION REQUIREMENTS: | |||
| a. | Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 2:30 pm local time Friday, August 12, 2016. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due. | ||
| b. | An offer guarantee | |_| is, | |_| is not required. (If “is required” see AGAR Clause 452.228-70) |
| c. | All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference. | ||
| d. | Offers providing less than 28 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. |
OMB APPROVAL NO. 2700-0042
| NSN 7540-01-155-3212 | 1442-101 | STANDARD FORM 1442 (REV. 4-85) |
| Computer Generated | Prescribed by GSA |
FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
Duns No. ______________________________________ Email: ________________________________________
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
Please complete this block.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
| AMENDMENT NO. |
| DATE |
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
| 24. SUBMIT INVOICES TO ADDRESS SHOWN IN |
| (4 copies unless otherwise specified) |
| ITEM |
| 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO | |
| |_| 10 U.S.C. 2304(c)( ) | |_| 41 U.S.C. 253(c)( ) |
| 26. ADMINISTERED BY | CODE |
| 27. PAYMENT WILL BE MADE BY |
USDA – Forest Service
IMAT
12730 HWY 12
Orofino, ID 83544
All invoices will be processed using the Department of Treasury’s Invoice Processing Platform (IPP), visit http://www.ipp.gov to learn more. Contractors must follow the instructions on how to register and submit invoices via IPP.
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
| |_| | 28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract. |
| |_| | 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary. |
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
DARREN M. ZYCHEK
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES
QUARTZ CREEK AOP CULVERT REPLACEMENT
Priest Lake Ranger District Idaho Panhandle National Forests Bonner County, Idaho B-1– Schedule of Items
ITEM
NO.
| DESCRIPTION |
| METHOD of MEAS. |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101 |
| Mobilization |
| LSQ |
| Lump Sum |
| 1 |
| 15220 |
| Construction Survey and Staking |
| LSQ |
| Lump Sum |
| 1 |
| 15401 |
| Contractor Testing |
| LSQ |
| Lump Sum |
| 1 |
| 15713 |
| Soil Erosion and Pollution Control |
| LSQ |
| Lump Sum |
| 1 |
| 15730 |
| Dewatering |
| LSQ |
| Lump Sum |
| 1 |
| 20301 |
| Removal of Existing Culvert |
| AQ |
| Each |
| 2 |
| 20806 |
| Crushed Aggregate, Select Culvert Backfill (contractor furnished) |
| CQ |
| Cubic Yard |
| 275 |
| 20812 |
| Structure Excavation & Backfill |
| LSQ |
| Lump Sum |
| 1 |
| 25101 |
| Placed Riprap, Class 4 Machine Placed (contractor furnished) |
| CQ |
| Cubic Yard |
| 90 |
| 27201 |
| Geocell Abutment Stabilization, 6 Inch Depth |
| CQ |
| Square Yard |
| 98 |
| 30801 |
| Crushed Aggregate, Surfacing, Compaction Method 2 (contractor furnished) |
| CQ |
| Cubic Yard |
| 55 |
| 553A02 |
| Precast Concrete Member, Stemwall/Footings |
| CQ |
| Linear Foot |
| 142 |
| 60304 |
| Steel Structural Plate Arch, 18'-0" Span, 7'-8" Rise, 6x2 corrugations 0.111" Thickness |
| CQ |
| Linear Foot |
| 70 |
| 62201 |
| Equipment Rental, Hydraulic Excavator with Thumb |
| AQ |
| Hour |
| 8 |
xxxxxx
| 62202 |
| Equipment Rental, Large Dump Truck |
| AQ |
| Hour |
| 8 |
xxxxxx
| 62503 |
| Seeding with Mulch, Dry Method |
| LSQ |
| Lump Sum |
| 1 |
| 64801 |
| Grade Control, Rock Weir (contractor furnished) |
| Each |
| Each |
| 7 |
| 64810 |
| Streambed Simulation Material (Available on Site) |
| LSQ |
| Lump Sum |
| 1 |
TOTAL FOR ALL ITEMS BELOW
* Designated Method of Measurement:
AQ - Actual Quantities; LSQ - Lump Sum Quantities; CQ – Contract Quantities B-2 PRICE PROPOSAL INSTRUCTIONS: Unit prices and total item amounts must be submitted for all items within the schedule in order to be considered for award. Do not round the extended item amounts or the total prices and provide prices to the nearest cent.
Contractor shall give a price per hour under Items 62201 & 62202 (Hourly Equipment Rental) for additional work above the estimated quantities that is encountered during the contract performance. Work contained in Items 62201 and 62202 is for work within any of the project areas contained in this bid schedule including access roads to the project. The Government does not guarantee that any hourly work shall be ordered and reserves the right to reduce or eliminate entirely the work under these items with no adjustment in contract unit price.
B-3– PAYMENT FOR BOND PREMIUMS: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
B-4 OFFER SUBMITTAL: As your offer, submit a completed and signed Standard Form 1442, a completed Schedules of Items (Sections B-1), a Technical Proposal, an original bid bond [if total offer exceeds $150K], a completed Section K and a completed Verification of Worker’s Compensation Insurance Form (provided in Section J). Technical and price proposals are required for evaluation of offers. See Section L for proposal instructions and Section M for evaluation/award information.
Electronic or facsimile proposals are NOT acceptable.
B-5 ADDITIONAL CLASSIFICATION REQUIRED – DAVIS-BACON GENERAL WAGE DECISION ID160040 04/01/2016 ID40: A wage rate for an Excavator Operator shall be conformed after award in accordance with FAR 52.222-6 Construction Wage Rate Requirements (MAY 2014) and direction provided in the subject Wage Decision. To obtain the prevailing wage determination for this item of equipment, incumbent must complete Standard Form 1444 and submit to www.dol.gov local agent post award.
B-6 IDAHO USE TAX Under Clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. Questions regarding assessment of Idaho Use Tax on Government Furnished Property should be directed to the Idaho State Tax Commission at (208) 799-3491.
SECTION C - DESCRIPTION/SPECIFICATIONS
C- 1 - PROJECT DESCRIPTION AND LOCATION
(a) - Description of Work This project includes removal two existing culverts and replacing them with a 18’-0” x 7’-8” x 70’-0” Structural Plate Arch with precast concrete footings. This work will consist of constructing a stream channel through the pipe and installing grade control structures within the culvert and potentially outside the culvert near the inlet and outlet. Additionally a segment of road shall be reconstructed and shaped to provide adequate approaches over the new structure together with commercial source surface aggregate placed on the reconstructed segment of road. This work will include placing commercial source riprap material at the inlet and outlet and for construction of the grade control structures.
(b) - Project Location. Forest Service Road 334 is approximately 10.5 miles North of Priest River, Idaho. Located in Section 7, T.57 N., R. 4 W., BM Latitude and Longitude of the site is N 48°18'24.989", W 116°53'7.324".
Travel from Priest River, Idaho on Idaho 57 North for approximately 3.5 miles turn right on Peninsula road, travel for 4.5 miles turn left on Forest Service Road 334 for 2.2 miles to Quartz Creek culvert crossing.
(c) – Price Range. $100,000 - $250,000
(d) - Pre-Bid Tour. No pre-bid tour is scheduled for this project. Interested Bidders are encouraged to visit the project site prior to submittal of prices and technical proposal.
(e) - Pre-Bid Conference: No pre-bid conference is scheduled for this project. Interested bidders may obtain additional information by contacting Kevin Davis at: 208-265-6686.
| Contracting Questions: | Technical Questions: | |
| Darren M. Zychek | Kevin Davis | |
| USDA Forest Service | USDA Forest Service | |
| Supervisor’s Office | Sandpoint Ranger Station | |
| 3815 Schreiber Way | 1602 Ontario Street | |
| Coeur d’Alene, Idaho 83815 | Sandpoint, Idaho 83864 | |
| Telephone: (208) 476-8224 | Telephone: (208) 265-6686 |
(f) – Performance Period.
| Estimated Beginning Date | Completion Date |
| August 18, 2016 | October 15, 2016 |
The Contractor shall maintain progress at a rate that will assure completion of work by the required completion date for each Item.
The Government will issue a Notice to Proceed on or near the Estimated Beginning Date. The count of contract time will start on the date specified in the Notice to Proceed.
(g) – Restrictions. In-stream work will be only allowed after July 15th and prior to October 15th of any construction year without prior approval by the Contracting Officer. Contractor shall develop and submit for Contracting Officer approval a Plan of Operation for de-watering and sediment containment to meet project BMP’s and Permits for Erosion and Sediment Control a minimum of 7 days prior to any in-stream work. Include in the Plan of Operation, Contractor’s proposed traffic and traffic sign placement and planned dates for any road closure.
(h) – Required Submittals. Prospective offeror reference attached Supplemental Specifications file:
Quartz Creek AOP Culvert_334-0.1_FSSS_Specifications.pdf Page 18 and 19.
C-2 – GOVERNMENT-FURNISHED PROPERTY. None
C-3 - STANDARD SPECIFICATIONS
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S. Customary Units are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. Copies of these Specifications are available on the internet at www.wfl.fha.dot.gov/design/specs/fp03.htm
Spec No Title Section 101 – Terms, Format, and Definitions Section 102 – Bid, Award, and Execution of Contract
| Section 103 – Scope of Work |
| Section 104 – Control of Work |
| Section 105 – Control of Material |
| Section 106 – Acceptance of Work |
| Section 107 – Legal Relations and Responsibility to the Public |
| Section 108 – Prosecution and Progress |
| Section 109 – Measurement and Payment |
| Section 151 – Mobilization |
| Section 152 – Construction Survey and Staking |
| Section 153 – Contractor Quality Control |
| Section 155 – Schedules for Construction Contracts |
| Section 156 – Public Traffic |
| Section 157 – Soil Erosion Control |
| Section 201 – Clearing and Grubbing |
| Section 203 – Removal of Structures and Obstructions |
| Section 204 – Excavation and Embankment |
| Section 208 – Sructure Excavation and Backfill for Selected Major Structures |
| Section 251 – Riprap |
| Section 308 – Minor Crushed Aggregate |
| Section 553 – Prestressed Concrete |
| Section 603 – Structural Plate Structures |
| Section 622 – Rental Equipment |
| Section 625 – Turf Establishment |
| Section 703 – Aggregate |
| Section 704 - Soil |
| Section 705 – Rock |
| Section 707 – Metal Pipe |
| Section 713 – Roadside Improvement Material |
| Section 718 – Traffic Signing and Marking Material |
| Section 725 – Miscellaneous Material |
C-4 - FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS
Forest Service supplementary specifications are included as a separate APPENDIX of this solicitation. The supplementary specifications applicable to this project are listed in Part III, Quartz Creek AOP Culvert_334-0.1_FSSS_Specifications.pdf.
NOTE THAT THE SUPPLEMENTAL SPECIFICATION LIST INCLUDES THE MAJOR SPECIFICATIONS APPLICABLE TO THIS PROJECT. OTHER SPECIFICATIONS REFERRED TO WITHIN THESE SPECIFICATIONS (EVEN THOUGH NOT SPECIFICALLY LISTED HEREIN) ARE ALSO FULLY APPLICABLE TO THIS REQUEST FOR PROPOSALS AND ANY RESULTANT CONTRACT.
| Spec No | Title | Page(s) | |||
| Preface | 1 | ||||
| FSSS 101 – Terms, Format, and Definitions | 3 | ||||
| FSSS 102 – Bid, Award, and Execution of Contract | 1 | ||||
| FSSS 103 – Scope of Work | 1 | ||||
| FSSS 104 – Control of Work | 1 | ||||
| FSSS 105 – Control of Material | 1 | ||||
| FSSS 106 – Acceptance of Work | 1 | ||||
| FSSS 107 – Legal Relations and Responsibility to the Public | 2 | ||||
| FSSS 108 – Prosecution and Progress | 1 | ||||
| FSSS 109 – Measurement and Payment | 1 | ||||
| FSSS 151 – Mobilization | 1 | ||||
| FSSS 152 – Construction Survey and Staking | 1 | ||||
| FSSS 153 – Contractor Quality Control | 3 | ||||
| FSSS 155 – Schedules for Construction Contracts | 1 | ||||
| FSSS 156 – Public Traffic | 1 | ||||
| FSSS 157 – Soil Erosion Control | 1 | ||||
| FSSS 201 – Clearing and Grubbing | 1 | ||||
| FSSS 203 – Removal of Structures and Obstructions | 1 | ||||
| FSSS 204 – Excavation and Embankment | 1 | ||||
| FSSS 208 – Structure Excavation and Backfill for Selected Major Structures | 1 | ||||
| FSSS 251 – Riprap | 1 | ||||
| FSSS 272 – Geocell Abutment Stabilization | 2 | ||||
| FSSS 308 – Minor Crushed Aggregate | 2 | ||||
| FSSS 553A – Precast Contrete Structures | 3 | ||||
| FSSS 603 – Structural Plate Structures | 1 | ||||
| FSSS 622 – Rental Equipment | 1 | ||||
| FSSS 625 – Turf Establishment | 2 | ||||
| FSSS 648 – Stream Simulation | 2 | ||||
| FSSS 703 – Aggregate | 1 | FSSS 705 – Rock | 1 | ||
| FSSS 713 – Roadside Improvement Material | 1 | ||||
| FSSS 725 – Miscellaneous Material | 3 | ||||
| FSSS 736 – Geocell | 1 |
C-5 – CONSTRUCTION PLANS The following drawings are a part of this solicitation and any resulting contract and are found in a separate attachment in Section J.
Entitled “Quartz Creek AOP Culvert Plans_Drawings.pdf” (Schedule of Items B-1)
| Description | Sheet | |||
| Title Sheet | Sheet 01 of 10 | |||
| Estimated Quantities and General Notes | Sheet 02 of 10 | |||
| Road Typical Sections, points & Project Control Sheet 03 of 10 | ||||
| Road Plan and Profile | Sheet 04 of 10 | |||
| Culvert General Layout | Sheet 05 of 10 | |||
| Excavation Details | Sheet 06 of 10 | |||
| Foundation Details Sheet 07 of 10 | ||||
| Precast Footing Details Sheet 08 of 10 | Stream Details Sheet 09 of 10 | |||
| Stream Dewatering Details Sheet 10 of 10 | ||||
| Roadway Cross Sections | Sheet XS1 |
C- 6 BIOBASED PRODUCT UTILIZATION
The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.
The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).
The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
| Hydraulic Fluids | Penetrating Lubricants | Degreasers |
| Absorbents | Diesel Fuel Additives | Greases |
| Dust Suppressants | 2-Cycle Engine Oil | Sorbents |
| Adhesive and Mastic Removers | Cleaners | Concrete/Asphalt Release Fluids |
| Composite Panels | Sealers | Wood and Concrete Sealers |
| Graffiti and Grease Removers | Stain Removers | Metalworking Fluids |
Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.
In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available biobased products.
The Contractor shall submit with the initial proposal a complete list of biobased products, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract (see Section L, Clause L- * - Instructions for the Preparation of Technical and Business Proposals).
Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).
Within thirty (30) days of contract award, the Contractor shall submit an Operation Plan. This submittal will be approved by the COR in writing. The Contractor shall not commence work until this submittal is approved by the COR in writing. The Plan must be reviewed and updated annually, and as required by the COR. The Plan must contain and define the following elements:
· The Contractor’s written policy stating its commitment to the use of biobased products, employee health and safety, and sound environmental management practices.
· Detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance.
· Proposed biobased construction products which must be selected in accordance with the criteria included above. At a minimum, the Plan must identify products by brand name for each of the product types.
NOTE: A Contractor may propose more than one product within a product category and/or propose a product or products addressing more than one product category.
· The product guides which define standard operating procedures for instructing staff in the proper use, storage, and disposal of biobased products; proper maintenance of equipment; and other procedures/instructions to accomplish work under this contract.
The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.
A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.
SECTION E - INSPECTION AND ACCEPTANCE
E-1 - INSPECTION OF CONSTRUCTION (FAR 52.246-12) (JUL 1986)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) below.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
SECTION F - DELIVERIES OR PERFORMANCE
F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
| 52.242-14 | Suspension of Work (APR 1984) |
| F- 2 | FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I (APR 1984) |
After the payment and performance bonds are received and approved by the Contracting Officer, the Contractor shall be required to (a) commence work in accordance with the accepted work plan (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 15 October 2016. The time stated for completion shall include final cleanup of the premises.
The 15 October 2016 completion date is based on the assumption that the successful offeror will receive the notice to proceed by 18 August 2016. This completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
PART I - THE SCHEDULE
SECTION G – CONTRACT ADMINISTRATION
G-1 AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within 30 days of the commencement of work. The conference will be held at Nez Perce – Clearwater National Forests Office, in Grangeville, ID. Another location may be approved if all parties agree.
G-2 CONTRACTING OFFICER'S REPRESENTATIVE
The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the prework conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the Specifications, shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.
G-3 Contractor Quality Control
Submittals for project plan contained within:
Quartz Creek AOP Culvert_334-0.1_FSSS_Specifications.pdf Page 18 and 19.
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.236-72 Use of Premises (NOV 1996)
H- 2 FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the plans and in the specifications are the result of site investigations by Forest Service specialists making physical determination based on surface observations.
(b) Weather Conditions. Normal snow conditions indicate a work season from approximately March 1 to November 30.
(i) Transportation Facilities. Forest Service Road 334 is approximately 10.5 miles North of Priest Lake, Idaho. Located in Section 7, T.57 N., R. 4 W., BM Latitude and Longitude of the site is N 48°18'24.989", W 116°53'7.324".
Travel from Priest Lake, Idaho on Idaho 57 North for approximately 3.5 miles turn right on Peninsula road, travel for 4.5 miles turn left on Forest Service Road 334 for 2.2 miles to Quartz Creek culvert crossing.
(c) Material Sources.
None.
H- 3 AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the key personnel identified in the accepted technical proposal.
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H-4 Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
Contractor to submit traffic control plan for each project in the schedule of items. Minimum requirements of the traffic control plan are described in Specification 156.
H-5 ENVIRONMENTAL PROTECTION
Prevention of Oil Spills.
The contractor is required to have a spill plan. The plan will contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling.
All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site.
All pumps and generators used in or near streams will have appropriate spill containment structures and/or absorbent pads in place during use.
When storage facilities for oil or oil products are on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or any other body of water. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer and appropriate state agencies.
Fuel and service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. The contractor must clean up spills or leaks in a manner that complies with Federal, state, and local laws and regulations and to the satisfaction of the CO. Any spills resulting in a detectable sheen on water shall be reported to the EPA National Response Center (1-800-424-8802). Any spills over 25 gallons will be reported to the Idaho Division of Environmental Quality and cleanup will be initiated within 24 hours of the spill. When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
Equipment Fuel/Oil Leakage.
All equipment used for instream work will be cleaned of external oil, grease, dirt and mud; and leaks repaired; prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Any leaks or accumulations of grease will be corrected before entering streams or areas that drain directly to streams or wetlands.
Equipment used for in-stream or riparian work (including chainsaws and other hand power tools) will be fueled and serviced in an area approved by the CO. When not in use, vehicles will be stored in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc. to streams.
Contractor is required to have a Spill Kit or equivalent that contains oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, available on-site during all phases of construction. For small streams with few pools or slack water, booms may not be effective. Use pads and straw bales to anchor booms if necessary. Booms will be placed in a location that facilitates an immediate response to potential petroleum leakage.
H-6 NOXIOUS WEED CONTROL
In order to prevent the potential spread of noxious weeds into work areas, Contractor shall be required to use weed-free equipment.
The following is considered proof of weed-free equipment:
The Contractor will be required to clean all construction equipment prior to entry on to national forest land. This cleaning shall remove all dirt and plant parts and material that could carry noxious weed seeds into the work area. Only clean construction equipment inspected by the Forest Service will be allowed to operate within the work area. All subsequent move-ins of construction equipment shall be treated in the same manner as initial move-in. "Construction equipment" does not include pickup trucks and personal vehicles.
H-7 FIRE CONTROL (FS 236-1)
| (a) | Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations. |
| (b) | Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned. |
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area. An equitable adjustment in contract time may be made for this period.
| (c) | Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract. | |
| (1) | Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service. | |
| (2) | Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows: | |
| One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating. | ||
| One - shovel, round point #0 lady or equal. | ||
| One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski. | ||
| One - water container (at least 1-gallon capacity), not required with stationary equipment. | ||
| (3) | Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained. | |
| (4) | Powersaws. For each powersaw used in connection with this contract, the following will be provided: | |
| One - shovel, round point #0 lady or equal. Shovel must be immediately available for use. | ||
| One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times. |
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
| (5) | Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated. |
| (6) | Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot. |
| (7) | Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site when all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist. |
| (8) | Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended. |
| (9) | Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch. |
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
| (10) | Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start. |
| (11) | Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions. |
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
| (i) | All high fire risk operations could be terminated at 1300 local time. | |
| (ii) | All burning could be stopped, including debris burning fires. |