Amend3b.docx

DOCX document 21 KB Posted

Attached to
IMAT, Nez Perce-Clearwater NF's Glade Creek Trails
Solicitation number
AG-02RC-S-13-0058
Issued by

About this file

Amendment 3 Attachments

View the file

Other files

File Type Posted
Amend4a.docx DOCX document
Amend_4.doc DOC document
Amend_3.doc DOC document
Amend_2.doc DOC document
amendment.docx DOCX document
loop_straight_line.doc DOC document
Rolling_Dip_(2).pdf PDF
Amend_1.doc DOC document
connector_straight_line.doc DOC document
RFQ.doc DOC document
Glade_Creek_Trails_Project_Map.JPG JPG image
Glade_Creek_Trails_Project_Vicinity_Map.JPG JPG image
Dispersed_Sites.docx DOCX document
Straightline_Diagrams0001.pdf PDF
Drawings0001.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Glade Creek Trails - Accessible Construction Nez Perce – Clearwater National Forests Idaho County, Idaho

B- 1 - BID SCHEDULE (Prices must be entered for all Items in both schedules; do not round the total extended prices.) **Unit prices and total item amounts must be submitted for the Base and Optional item in order to be considered for award.

ITEM NO.
DESCRIPTION
MTHD

of

MEAS*

PAY UNIT
EST. QTY.
UNIT PRICE
TOTAL PRICE
911(02)
Clearing and Grubbing
DQ
LF
5605
$
$
912(01)
Excavation
DQ
LF
5605
$
$
912(04)
Trail Turnout (resting area)
AQ
LF
40
$
$
912(09)
Ditch
DQ
LF
140
$
$
915(01)
Trail Restoration
DQ
LF
830
$
$
921(03)
Culvert, Gov’t. furnished (8”x6’)
AQ
EA
3
$
$
932(02)
Install Puncheon Bridge, with Curb rails, Gov’t Furnished (30’ and 10’)
DQ
EA
2
$
$
934(01)
Rock Retaining Wall
DQ
SY
18
$
$
941(02)
Aggregate Surfacing, Grading B, Compaction Method C
DQ
CY
477
$
$
951(01)
Mobilization
LSQ
LS
1
$
$
Rental Equipment Hydraulic Excavator, w/Thumb
CQ
HR
8
TOTAL BID PRICE
$ ______

*Method of Measurement AQ - Actual Quantity, DQ - Designed Quantity, CQ – Contract Quantity, LSQ - Lump Sum Quantity

OPTIONAL ITEM B-2

3 Dispersed Sites – Decompaction, Revegetation, and Recontouring
LSQ
LS
1

B-1 AWARD OF OPTIONAL ITEM: The Government reserves the right to make award of optional item concurrent with award of the base item. The optional item shall be awarded on an all-or-nothing basis. Award of an optional item is contingent upon NEPA approval of the work required.

B-2 EXCAVATOR: Contractor shall give a price per hour for Hydraulic Excavator with Thumb for additional work above the estimated quantities that is encountered during the contract performance. The Government reserves the right to reduce or eliminate entirely the work under this item with no adjustment in contract unit price.

B-3 BOND PREMIUMS: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

B-4 BASIS OF AWARD: As your quote, submit a completed and signed Standard Form 18, a completed Schedule of Items (Section B), a Technical Proposal, a completed Section K and a completed Verification of Worker’s Compensation Insurance Form. Technical proposals and price quotes are required for evaluation. See Section L for proposal instructions and Section M for evaluation/award information.

B-5 IDAHO USE TAX: Under clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. Questions regarding assessment of Idaho Use Tax on Government Furnished Property should be directed to the Idaho State Tax Commission at (208) 799-3491.

B-6 ADDITIONAL CLASSIFICATION REQUIRED – DAVIS-BACON GENERAL WAGE DECISION ID130054, 04/05/2013, HEAVY CONSTRUCTION, IDAHO COUNTY, IDAHO

A wage rate for an Excavator Operator shall be added to the above referenced wage decision after award in accordance with FAR 52.222-6 Davis-Bacon Act. Based on a preliminary review of the wage decision, a reasonable range between which the conformed rate would fall is $33.26 and $36.80 per hour (wages and fringes combined). These rates align with the “Laborer:Landscape” and “Truck Driver:Dump Truck” rates derived from wage survey data listed under SUID2010-044.

(f) Start Work. It is estimated that work may begin on August 12, 2013. All items of work will be completed no later than September 30, 2013. Motor vehicle use is restricted, but will be allowed for contract administration, refueling and equipment repair.

FAR 52.217-7 Option for Increased Quantity - Separately Priced Line Item (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor concurrent with the award of the base item. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

FAR 52.217-4 Evaluation of Options Exercised at Time of Contract Award (JUNE 1988)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate the total price for the basic requirement together with any option(s) exercised at the time of award.