Forest Service Construction Cost UPB
Attachment A
Forest Service Construction Cost – Unit Price Book
Primary Unit Price Book
| Item No. |
| Description |
| Method & Unit of Measure |
| Unit Price |
| 157.31 |
| Soil erosion and pollution control @ road - stream crossings: measure per area distrubed |
| CQ - SY |
| $ 10.00 |
| 157.02 |
| Silt fence 3ft wood stakes |
| CQ – LF |
| $ 5.00 |
| 158.01 |
| watering for dust control |
| CQ – MGallon |
| $ 35.00 |
| 201.31 |
| clearing and grubbing- Light |
Dispose by scattering
| 201.32 |
| clearing and grubbing- heavy |
dispose by scattering
| 203.30 |
| removal of structures and obstructions |
| CQ - CY |
| $ 100.00 |
| 204.80 |
| EXCAVATION AND EMBANKMENT – COMMON AND LOOSE ROCK COMPACTION METHOD B |
| CQ – CY |
| $ 3.25 |
| 207.01 |
| EARTHWORK GEOTEXTILES:TYPE IV |
| CQ – SY |
| $ 2.00 |
| 208.03 |
| STRUCTURAL EXCAVATION AND BACKFILL |
| CQ – CY |
| $ 35.00 |
| 209.03 |
| STRUCTURAL BACKFILL-PIPE BEDDING |
| CQ – CY |
| $15.00 |
| 211.01 |
| ROADWAY OBLITERATION:ripping 8” to 12” depth |
| CQ – LANE MILE |
| $950.00 |
| 212.01 |
| LINEAR GRADING |
| CQ – LANE MILE |
| $350.00 |
| 230.01 |
| ROADSIDE BRUSHING- MEDium |
| CQ - ACRE |
| $400.00 |
| 251.01 |
| RIPRAP: Machine placed Class 5 |
| CQ – CY |
| $55.00 |
| 252.05 |
| rOCK EMBANKMENT AND ROCK BUTTRESS: cLASS 6 |
| CQ – CY |
| $55.00 |
| 252.51 |
| rOCK: bOULDER PLACEMENT |
| CQ - EACH |
| $50.00 |
| 253.01 |
| Gabions:wELDED wIRE: galvanized |
| CQ – CY |
| $75.00 |
| 255.01 |
| MECHANICALLY STABILIZED EARTH WALLS – measure Per area of wall face, excavation and backfill excluded |
| CQ – SF |
| $30.00 |
| 259.01 |
| SOIL NAIL RETAINING WALLS: PER SOIL NAIL PLACED 20 ft depth |
| CQ – EACH |
| $300.00 |
| 259.11 |
| SOIL NAIL RETAINING WALLS: SHOT CRETE FACE |
| 262.01 |
| reinforced soil embankment: GEOGRID: Category 3. excavation and embankent excluded |
| CQ – SY |
| $5.00 |
| 301.01 |
| Crushed aggregate: Gradation C |
compaction method b fURNISH AND PLACE, EXCLUDE HAUL
| 301.02 |
| Crushed aggregate surface course: with 2% bentonite |
compaction method b fURNISH AND PLACE, EXCLUDE HAUL
| 306.01 |
| dust palliative: magnesium chloride |
| CQ – sY |
| $ 0.75 |
| 303.01 |
| Road reconditioning: includes SCARIFY 6 IN DEPTH, SURFACe blading, and COMPACTION |
| CQ – MILE |
| $2300.00 |
| 303.05 |
| Road Reconditioning: surface blading only |
| CQ – MILE |
| $350.00 |
| 324.01 |
| Minor crushed aggregate: |
quantities LESS THAN 100 cy fURNISH AND PLACE, EXCLUDE HAUL
| 403.01 |
| Hot asphalt concrete pavement |
fURNISH AND PLACE, EXCLUDE HAUL
| 404.01 |
| Minor Hot asphalt concrete pavement: (less than 50 ton) |
fURNISH AND PLACE, EXCLUDE HAUL
| 408.01 |
| cold recycled asphalt base course |
| CQ – SY |
| $ 3.50 |
| 409.01 |
| Asphalt surface treatment – CRS2P Asphalt |
| AQ - Ton |
| $650.00 |
| 409.02 |
| Asphalt surface treatment – Aggregate chips – ½ IN, 30#/SY |
fURNISH AND PLACE, EXCLUDE HAUL
| 410.01 |
| Asphalt surface treatment – slurry seal, type II CSS-1h |
| CQ – SY |
| $ 3.50 |
| 411.01 |
| Asphalt prime coat |
| CQ - gallon |
| $ 2.50 |
| 411.05 |
| Asphalt fog coat |
| CQ – sy |
| $ 1.50 |
| 413.01 |
| Asphalt pavement milling: 3 in depth |
| CQ – sy |
| $ 1.00 |
| 414.01 |
| Asphalt pavement crack and joint sealing, Polymer or rubber modified |
| AQ –gallon |
| $ 3.50 |
| 414.31 |
| Asphalt pavement: Saw cutting |
| AQ –LF |
| $ 1.50 |
| 430.01 |
| Asphalt pavement Patching: full depth hot asphalt concrete mix |
| aQ –SY |
| $ 25.00 |
| 501.01 |
| Reinforced Portland Cement concrete slabs |
| CQ – cy |
| $250.00 |
| 552.01 |
| Structural concrete Class A(AE) |
| CQ – CY |
| $500.00 |
| 553.01 |
| precast, prestressed concrete structural member CLASS p(ae) |
| CQ – CY |
| $750.00 |
| 556.01 |
| Bridge Railing type II class B |
| CQ – LF |
| $60.00 |
| 556.02 |
| Remove and reset bridge railing |
| CQ – LF |
| $35.00 |
| 556.01 |
| aPPROACH GUARDRAIL type II |
| CQ – LF |
| $60.00 |
| 557.01 |
| treated structural timber and lumber |
| CQ – MBF |
| $3000.00 |
| 557.02 |
| treated structural timber and lumber - glulam |
| CQ – MBF |
| $3500.00 |
| 561.01 |
| Bridge curb: remove and replace |
| CQ – LF |
| $35.00 |
| 600 |
| incidental construction |
| 602.01 |
| CMP cULVERT-18 INCH – 16 GA |
| AQ – LF |
| $ 35.00 |
| 602.02 |
| CMP cULVERT-24 INCH – 14 GA |
| aQ – LF |
| $ 45.00 |
| 602.03 |
| CMP cULVERT-36 INCH – 12 GA |
| aQ – LF |
| $ 60.00 |
| 603.11 |
| sTRUCTURAL pLATE CULVERTS – MEASURED BY SPAN TIMES LENGTH OF STRUCTURE |
| CQ – SF |
| $ 35.00 |
| 605.01 |
| Underdrain system: includes all geosnthetic, pipe, and backfill materials |
| CQ – sy |
| $ 40.00 |
| 607.01 |
| remove, clean, and reset existing culvert |
| aQ – LF |
| $ 20.00 |
| 614.01 |
| lEAN CONCRETE BACKFILL |
| aQ – CY |
| $150.00 |
| 615.01 |
| cONCRETE PAVEMENTS: SIDEWALKS AND PADS |
| aQ – CY |
| $200.00 |
| 617.01 |
| gUARDRAIL type II, class a |
| aQ – LF |
| $50.00 |
| 617.01 |
| gUARDRAIL terminal section |
| CQ – each |
| $400.00 |
| 617.01 |
| gUARDRAIL replace post |
| CQ – each |
| $50.00 |
| 624.01 |
| tOPSOIL: furnish and place |
| CQ – cY |
| $30.00 |
| 624.02 |
| tOPSOIL: place conserved |
| CQ – cY |
| $15.00 |
| 629.01 |
| erosion control mat: type 2.D |
| CQ – sY |
| $ 8.00 |
permanent traffic control
| 633.01 |
| sign system – HDO plywood |
| CQ – sF |
| $ 50.00 |
| 633.05 |
| Posts: 4X4 treated wood |
| CQ – each |
| $ 25.00 |
| 633.06 |
| object marker |
| CQ – EAch |
| $150.00 |
| 633.07 |
| delineator |
| CQ – EAch |
| $ 25.00 |
| 633.11 |
| remove and reset Sign or object |
| CQ – EAch |
| $ 50.00 |
| 634.01 |
| Permanent pavement marking: |
4” wide stripe, thermoplastic type H
| 648.01 |
| sTREAM SIMULATION MATERIAL PLACEMENT |
| CQ – CY |
| $ 30.00 |
| 648.02 |
| sTREAM SIMULATION MATERIAL placement- furnish and place class 14 |
| CQ – CY |
| $ 60.00 |
| 648.51 |
| bOULDER PLACEMENT: size 4 |
| CQ – each |
| $ 50.00 |
| 648.52 |
| bOULDER placement– Furnish and place size 4 |
| CQ – each |
| $150.00 |
| 801.1 |
| MATERIAL SHORT HAUL < 5 Mile |
| Aq – cY mile |
| $ 1.80 |
| 801.2 |
| MATERIAL LONG HAUL > 5 Mile |
| Aq – cY mile |
| $ 0.40 |
| 801.3 |
| wEIGHED MATERIAL HAUL |
| Aq–tON mile |
| $ 0.25 |