This is an Architect-Engineer Statement of Work (SOW) for project JUBJ 12-5335 at Maxwell AFB Gunter Annex, requiring architectural and engineering services for the demolition of Building 1503 and renovation of Building 833. The SOW outlines requirements for a complete design package including construction drawings, specifications, design analyses, cost estimates, and other project documentation.
The A-E firm must complete the design within 260 days of Notice to Proceed, with submissions required at 65% (30 days), 95% (60 days), and Ready to Advertise (RTA) stages (100 days). Key deliverables include demolition design for Building 1503 with site restoration and new parking lot maximization, and renovation design for Building 833's finishes and building systems. The A-E must provide Level 5 cost estimates, use Master Format 2018 specifications, deliver AutoCAD 2024 drawings on 11"x17" sheets, and follow green procurement requirements. All documentation must be submitted to Sandra Bredlow at Maxwell AFB, with specific quantities required at each design stage. The A-E must have or obtain registered professional engineers and architects across various disciplines to support the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Locations.pdf | ||
| 1503 Area.jpg | JPG image | |
| FA330025R0005 RFI LOG v2.pdf | ||
| RFP - FA330025R0005_v2.pdf | ||
| FA330025R0005 RFI LOG.pdf | ||
| RFP - FA330025R0005.pdf | ||
| SF330-21a.pdf | ||
| RFP - FA330025R0005.pdf | ||
| Appendix A revised Jun 2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A/E-SOW
ARCHITECT-ENGINEER STATEMENT OF WORK
JUBJ 12-5335 Demo 1503 Renovate 833, Maxwell AFB Gunter Annex
1.0 INTRODUCTION
Maxwell AFB 42CES/CEN has a requirement for a Subcontractor to provide Architectural-
Engineering services for:
JUBJ 12-5335 Demo 1503 Renovate 833, Maxwell AFB Gunter Annex
1.1 The Service provider (Architect/Engineer) will perform all design work necessary to accomplish the work indicated herein and in accordance with Appendix A, Performance Requirements for
Architect-Engineering Services, except as modified herein. Provide all plant, labor, equipment and materials required to complete the project and deliver to Maxwell AFB complete project documents, including but not limited to: construction drawings, specifications, design analyses, cost estimates, construction submittal register, drawing list, specification list, bid schedules, product and material technical data sheets, and working sketches. For 65% drawing and specification submittals, the A-E shall deliver two sets of bound half-size drawings and one set of bound specifications along with drawings and specifications in electronic format stored on
CD. For 100% drawings and specifications submittals, the A-E shall deliver three sets of bound half-size drawings and three sets of bound specifications along with drawings and specifications in electronic format stored on CD. All RTA final construction drawings shall be delivered as three sets of bound half-size copies and in electronic format stored on CD. All
Mechanical Drawings shall be stamped by the Mechanical Engineer. Drawings shall be delivered in a useable electronic format as an AutoCAD “.dwg” file, 2020. All RTA final specifications shall be delivered three sets bound and in electronic format in both MSWord
2010 (.docx) and Adobe PDF format stored on CD. Design analyses shall be delivered in two bound sets at all junctures of the project time frame. Cost estimate and submittal register shall be delivered in two bound sets and in electronic format stored on CD with the all submittals.
1.2 All work is to be performed in accordance with this SOW (Statement of Work).
1.3 Consultants. The A-E will be required to have as an integral part of the firm, or shall be able to obtain the services of, registered professional engineers and registered Architects established in various disciplines to support the subject project. The use of consultants will be determined by the A-E with all coordination, control, payment and scheduling responsibilities belonging to the A-E. The A-E shall make the consultants aware of the scope of the work and shall be responsible for the accomplishment of the work in accordance with all related standards, regulations, instructions, directions, and adopted codes that are pertinent to Maxwell AFB, AL and as described under 3.0 herein.
Cost Estimates:
All cost estimates will be a ‘LEVEL 5’ cost estimate as defined by the Whole Building Design
Guide.
Cost Estimating | WBDG - Whole Building Design Guide https://www.wbdg.org/design-disciplines/cost-estimating
The purpose of this level of estimate is to develop probable costs in the preparation and submittal of bids for contract. This will be provided with 65%, 100%, and RTA submittal.
Include a complete and thorough "Scope of Estimate" statement that would state clearly such https://www.wbdg.org/design-disciplines/cost-estimating items assumptions, allowances, documents used for the estimate, and contingency amounts included.
Specifications:
All specifications will be in the format of Master Format 2018.
Specifications will be in line with the specifications at the Whole Building Design Guide website. https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs
SpecsIntact software is an automated system for preparing standardized facility construction specifications used worldwide by National Aeronautics and Space Administration (NASA), the
U.S. Naval Facilities Engineering Command (NAVFAC), and the U.S. Army Corps of
Engineers (USACE). The SpecsIntact software is government funded and does not require or provide an End Users Agreement (EULA) therefore, can be downloaded and installed on an unlimited number of computers free of charge.
This software produces the specifications that are available on WBDG site, except that they are editable and customizable. Information and software download is available at the link below.
https://www.wbdg.org/dod/specsintact/software?
1.4 The Service provider (Architect/Engineer) shall furnish and provide for the contracting officer the quality and quantity of service per Section 4 of this Statement of Work.
2.0 ACRONYMS/DEFINITIONS:
A-E = Architect/ Engineer
ASHRAE = American Society of Heating, Refrigerating and Air Conditioning Engineers
CHWP= Chilled Water Pump
CHWR= Chilled Water Return
CHWS= Chilled Water Supply
COE = Corps of Engineers
CWP= Condenser Water Pump
CWR= Condenser Water Return
CWS= Condenser Water Supply
DDC = Direct Digital Control
NTP = Notice to Proceed
SMACNA = Sheet Metal and Air Conditioning Contractors National Association
SOW = Statement of Work
VFD = Variable Frequency Drive
3.0 APPLICABLE SPECIFICATIONS/STANDARDS/RELATED STUDIES:
3.1 Applicable Publications, Laws and Regulations, and Instructions, ETC.:
3.1.2 Latest Edition of the following Codes & References
a. ASHRAE Std 62
b. ASHRAE Std 90.1
c. SMACNA Duct Construction Standards
d. American with Disabilities Act and Architectural Barriers Accessibility Guidelines
e. National Fire Protection Association Codes and Standards.
f. National Fire Protection Association 101, Life Safety Code
g. International Building Code
h. International Mechanical Code
i. International Fuel Gas Code https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.wbdg.org/dod/specsintact/software
j. International Plumbing Code
k. ASHRAE Handbook of Fundamentals; Handbook of HVAC Systems and Equipment;
Handbook of HVAC Applications; and Handbook of Refrigeration
l. National Electric Code
m. UFC, DOD Minimum Antiterrorism Standards for Buildings, UFC 4-010-01
4.0 TASK DESCRIPTION
4.1 Background Information & Location – this work will be located on Gunter Annex building 1503 and 833
4.2 Description of Services: This description of services provides the A/E with a basis to develop the design intent as proposed. The SOW is not intended to be a complete and concise description of all the details required in the work effort. The determination of all applicable constraints on the project and the refinement of the intent as indicated in the
SOW are the responsibility of the A/E. AE must meet with the Project Manager to review the Scope of Work prior submitting proposal
The A/E is to design for, o Building 1503 - Design to demolish and include restoration of the site and grade. Sod (with Tifton Bermuda) at areas of disturbance. The design shall include complete removal of the building utilities, plumbing, and electrical, mechanical system, which includes all piping, conduit, sewer drains, sprinklers, concrete footings, concrete slabs, any other abandoned lines in the footprint of the facility.
An asbestos survey will need to be completed for this facility.
o Reconfigure the existing parking lot and facility footprint, to design a parking lot to maximize the number of parking spaces.
o Building 833 - Design to renew finishes and check building systems for repairs.
STANDARD PROJECT REQUIREMENTS
*ALL FORMS AND SOW MUST BE INCLUDED IN BID PACKAGE AND WILL BE
FURNISHED BY SANDRA BREDLOW IN CE
1. 01000 General Requirements
2. AF Form 66
3. Spec Section 1305 Submittal Procedures
4. AF Form IMT 3000
5. Contractor's HAZMAT Questionnaire Form ESH-ESH-FM-002.
6. Contractor's Environmental Reporting Entry Form ESH-ESH-FM-003
7. Recycling and Landfill Report
8. 13279A Asbestos Protocol/13280 Asbestos Spec
9. Updated Signature Block
10. Cost Estimate Form
11. Project signage requirements and location of contractor trailer information
4.3 This description of services provides the A/E with a basis to develop the design intent as proposed. The SOW is not intended to be a complete and concise description of all the details required in the work effort. The determination of all applicable constraints on the project and the refinement of the intent as indicated in the SOW are the responsibility of the A/E.
4.4 Performance of Work
4.4.1 Performance Period. Complete design shall be completed within 260 days from
NTP. The definition of complete work shall mean that all design stages have been accomplished, all reviews required herein have been completed, all comments made by the user/42CES/CEN are incorporated into the construction documents, and all documents are ready for advertisement and the bidding process.
4.4.2 Schedules: The A-E shall provide a schedule that indicates the start of the performance period, the review milestones, and the completion date. If the contract is modified to adjust the completion date the A-E shall submit a revised schedule to Contract
Administrator within one day of the signed modification to the original delivery order clearly indicating the original performance period and the new completion date.
4.4.3 Submittal Milestones. The A-E shall submit the following design documents and supporting elements for the subject project in the following sequence. Note that all time elements are in reference to the date the purchase order is received by the A-E, which hereafter shall be referred to as NTP (Notice to Proceed):
A. 35% Design Charrette---------------------------------------------------- N/A
B. 65% Design Documentation-------------------------------------------30 Days after NTP
C. 95% Design Documentation-------------------------------------------60 Days after NTP
D. RTA Design Documentation------------------------------------------100 Days after NTP
4.4.4. The design documents submitted by the A-E will be reviewed by various agencies located on Maxwell AFB to verify that Air Force requirements are reflected in the design.
The A-E shall be held responsible for ALL requirements particular to the project being designed. 42CES/CEN shall only act as a regulatory body specifically there to provide the
A-E with direction on relevant regulations, standards, codes, and public laws that impact the subject project. The A-E shall determine how all of these elements guide and control the resultant design.
4.5 REVIEW PROCESS.
4.5.2 Upon completion of the 65% milestone the A-E shall submit the design package in the quantities indicated to the agencies listed in paragraph 5.1. Drawings shall be half-scale. The review process shall take 10 working days after receipt of the package and will generate written documents stating 42CES/CEN / user’s observations, questions and comments. The review time indicated is concurrent with the performance period time line indicated in paragraph 4.4.3.
4.5.3 Upon completion of the 100% milestone the A-E shall submit the design package in scale. The review process shall take 10 working days after receipt of the package and will generate written documents stating 42CES/CEN / user’s observations, questions and comments. The review time indicated is concurrent with the performance period time line indicated in paragraph 4.4.3.
4.5.4 Upon completion of the RTA milestone, the A-E shall submit the design package in scale. The original specifications, drawing list, specification list, and Submittal Register shall be printed on one side of each page. All drawings, including CAD files, specifications and cost estimate shall be provided to 42CES/CEN on compact disks. Both
CD and shall be labeled with project name, no., submittal phase, date and A/E name. The
Construction Cost Estimate and Annotated Comments shall be submitted in separate bound copies with Title Cover Sheets.
4.5.5 Note: The A-E shall attach a letter to each RTA design level addressee above that indicates the project number and name, the using organization, the project location, and state that all comments be forwarded to Ms. Sandra Bredlow at the address indicated in #1 on the list within 5 working days from the date on the A-E’s letter.
4.5.6 Specifications. A sample format will be given to the A-E. There shall be no reference to the “owner”, “Architect”, “Engineer” etc. in specifications. The only entity authorized to obligate government funds and negotiate with a contractor is 42 Contracting
Squadron’s Contracting Officer and shall be used in place of all references to an individual, except where the term “Contractor” is used.
We are now required to use the Master format 2018. SpecsIntact is an automated
Specification Management System and is the latest generation of software for preparing facility construction specifications used worldwide by NASA, the Naval Facilities
Engineering Command (NAVFAC), U.S. Army Corps of Engineers (USACE) and Air
Force Civil Engineer Center. SpecsIntact utilizes Master guide specifications prepared by the Government agencies, which is at the hear of what makes the system unique.
SpecsIntact is a free download at https://specsintact.ksc.nasa.gov/Software/Software.sht
4.5.7 Specification References. Provide in both MS-word (.docx) and PDF format (PDF @
RTA only). All references to industry standards such as ASTM, ANSI, Fed Spec, etc. shall be dated. Only references specifically applicable to the subject project shall be included in the specifications.
4.5.8 Warranty & Guaranties. All items that carry a warranty longer than the one-year warranty provided for in the Federal Acquisition Regulations shall be covered by a warranty paragraph in the specifications that reflects the extended warranty period.
4.5.9 Proprietary References. Federal projects are required to provide open competition for all products that serve the intended function and fulfill the performance requirements stated in the construction documents. The A-E shall provide performance specifications whenever possible and use reference specifications when necessary. If the work requires the use of proprietary specifications the A-E shall provide 42CES/CEN with a Sole Source justification letter that explains why a particular product is the only one that can perform the intended function. When reference specifications are used provide the name and address of the manufacturer used as a basis for the design. Qualify the use of a single manufacture name by stating, “any reference to a specific manufacture is intended to set minimum standards, configuration, and appearance, and not to restrict competition of equal or better manufacturers and products. The A-E shall provide 42CES/CEN project manager with a cut sheet from the manufacture that describes all the salient features of the product being specified.
4.6 Green Procurement.
4.6.1. In order to comply with federally mandated environmental preference programs and
Department of Defense (DOD) “Green Procurement Program” (GPP) policy, Maxwell-
Gunter AFB requires the use of environmentally preferable products and services. These program elements include; recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, non-ozone depleting substances, priority chemicals, and environmentally preferable products.
4.7 Asbestos. The A-E shall not specify asbestos containing materials in the work. In those instances that removal of asbestos containing materials is required a comprehensive specification meeting the requirements and conditions of the federal government will be required. A sample specification will be given to the A-E.
4.8 Drawing Notes. A sample title sheet will be given to the A-E. Ensure that the following is on the title sheet:
“ALL DRAWINGS ARE DIAGRAMMATIC AND ARE INTENDED TO QUANTIFY THE
MATERIALS SPECIFIED AND INDICATE THEIR INTENDED RELATIONSHIP TO EACH
OTHER. THE DRAWINGS ARE NOT TO BE SCALED. THE VARIOUS SCALES USED ON THE
DRAWINGS MAY NOT ALLOW FOR ALL FITTINGS, OFFSETS, AND ACCESSORIES THAT
MAY BE REQUIRED TO COMPLETE THE WORK. THE CONTRACTOR SHALL CAREFULLY
INVESTIGATE THE CONDITIONS THAT WOULD AFFECT THE WORK TO BE PERFORMED
AND SHALL ARRANGE SUCH WORK AS NECESSARY TO COMPLY WITH THE INTENT OF
THE CONSTRUCTION DOCUMENTS.”
4.9 Designs In Inch-Pound. This requires the use of inch-pound measurements in criteria, design, and specification documents for facility projects. When dual units are needed present International
System of Units (SI) designations first, followed by the inch-pound (IP) designation in parenthesis.
4.10 42CES/CEN Provided Materials. 42CES/CEN will provide hard copies of the subject building listed above from archive drawing files and other drawings selected by the A-E. The archive files are located in the Civil Engineering administrative building, 400 Cannon Street. The A/E will be required to retrieve all necessary drawings from the archives vault & reproduce them on site. We will also provide blank electronic copies of a submittal register (AF Form 66), a cost estimate form
(AF Form 3053), Tri-Services drawing format, title sheet, sample specification format, sample specifications for General Requirements, Schedule of Material, Submittal Procedures, and
Recycled / Recovered Materials.
4.11 Drawing Data
a. Drawing sheet size to be 11”x 17” with (Tri-Services Standards border)
b. Drawings shall be AutoCAD 2024
c. Pen settings shall be (Tri-Services Standards line weights/colors or as directed by
42CES/CEN).
In addition to other title block information, the following data shall be on each drawing sheet: (As appropriate)
Project Number: JUBJ 12-5335
Project Title: JUBJ 12-5335 DEMO 1503, RENOVATE 833, MAXWELL AFB
GUNTER ANNEX
5.0 DELIVERABLES:
5.1 Submittal Requirements. All submittals shall be hand delivered or express mailed to the following office:
6.0 TECHNICAL MONITOR:
Sandra Bredlow
400 Cannon Street, Bldg 1060
Maxwell AFB, AL 36106
(334) 953-3563 sandra.bredlow.ctr@us.af.mil
Receiving Office Percentage of Design Quantity of Doc. Sets
Sandra Bredlow
400 Cannon Street
(Bldg 1060)
Maxwell AFB, AL 36112-6523
Attn: Sandra Bredlow
65%
95%
RTA
2 spec originals &
2 set plans (+1 pdf copy)
2 spec originals &
2 set plans (+1 pdf copy)
1 CD includes spec originals & set plans, also
CAD files, pdf copies et al.
2 paper copies of spec originals & 2 set plans mailto:sandra.bredlow.ctr@us.af.mil