This document is a Justification for Other than Full and Open Competition (J&A) for architecture and engineering (A/E) design services at the Kennedy Center. The Kennedy Center intends to sole-source a one-year contract to Page Southerland Page, Inc. for continuing critical design projects, including a Comprehensive Life Safety Assessment, Cantilever Roof Repairs, Domestic Hot Water Heater Design, Motor Lobby Restroom Renovations, and an Electrical Grounding Study. The contract will be a firm-fixed-price arrangement with fixed hourly rates, leveraging FAR 6.302-1 authority due to the contractor's unique qualifications and the urgent need to maintain building safety and service continuity after the previous IDIQ contract lapsed in September 2024.

The proposed contract is valued at an amount to be determined (TBD), funded through capital funding, and will cover a 12-month performance period. The justification emphasizes that further delays in these design services could negatively impact the safe occupancy of the Kennedy Center building and site. The sole-source procurement is based on the contractor's existing knowledge of the facility and the critical nature of the proposed projects, which require immediate attention to maintain the building's infrastructure and safety systems.

View the file

Other files

File Type Posted
Statement of Objectives AE Page.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Management Office 2700 F Street, N.W.

Washington, D.C. 20566

(202) 416-8000

JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION

PART I - BACKGROUND

1.Date: 7/21/2025
2.Program Office: Project Management Office
3.Contracting Officer's Technical Representative: Elizabeth Doane
4.Description of Services Required: Architecture/Engineering Design Services
5.Period of Performance: 12 Months
6.Contract Amount: TBD
7.Appropriation Data: Capital Funding
8. Proposed Contractor:Page Southerland Page, Inc.

PART II - JUSTIFICATION

1. Authority Cited:

The statutory authority permitting other than full and open competition is 41 U.S.C. 253(c)(2) in accordance with;

[X] FAR 6.302-1, only one responsible source and no other supplies and services will satisfy Agency Requirements, [ ] FAR 6.302-2, Unusual and compelling urgency.

2. Nature and/or Description of the action being approved:

Bridge Contract for Architecture/Engineering for the continuation of design services to support Capital Projects for the Kennedy Center.

3. State why the proposed contractor's unique qualifications or nature of the acquisition requires use of the authority cited:

The existing IDIQ A/E design services with Page Southerland Page lapsed in September of 2024. The Center has several projects that must proceed to maintain the safety and integrity of the building. Further delays may have a serious negative impact to the safe occupancy of the building and site. Due to the nature of work, it is necessary and in the best interest of The Center to maintain continuity of services with the original design services A/E contractor through the end of the one-year project period.

4. Price reasonableness:

The Contractor will be requested to provide a proposal based on fixed hourly rates for services. The number of hours proposed for each of the remaining projects identified below will be negotiated. A single award firm-fixed price contract will result.

5. Is this requirement a continuation of previous effort?

This requirement is a single effort for the continuation of services, previously provided under an IDIQ contract.

Projects proposed for completion under the resultant contract award include to the following:

· Kennedy Center Comprehensive Life Safety Assessment and Analysis

· Cantilever Roof Repairs and Finish Replacement Design

· Domestic Hot Water Heater Design

· Motor Lobby Restroom Renovations

· Electrical Grounding Study

6. Market Survey/Effort to Obtain Competition:

N/A

PART III - CERTIFICATION/APPROVAL

1. Program Office:

I certify that this request to procure services using the authorities cited in FAR 6.3 (Other than Full and Open Competition) is made in good faith that the supporting data and information are accurate and complete to the best of my knowledge and belief.

__________________________________________
Carissa FaroughiDate

Program Director

2. Contracting Officer:

I certify that the justification is accurate and complete to the best of my knowledge and belief.

_________________________________________
Cecelia RoysterDate

Contracting Officer