This Addendum No. 1 document, issued by VK Civil Engineering on behalf of Grand Rapids Public Schools in Kent County, Michigan, modifies the contract documents for the 2027 Paving Projects. The addendum clarifies that each project is to be bid as a lump sum as the controlling project contract price, with unit prices provided for reference only. The document revises asphalt specifications across multiple school sites: the Nutrition Building, CA Frost, and Kent Hills West. Specific changes include adjustments to base and top course asphalt depths, addition of new bid items such as casting adjustments and stop sign placement at CA Frost, and renumbering of line items at Kent Hills West to eliminate duplicates. The addendum also adds a $1,000 allowance for playground pavement striping at Kent Hills West and revises plan details related to sidewalk protection, curb work, ADA compliance, parking configurations, and landscape specifications.
The addendum does not establish pricing terms, set-asides, or funding requirements, as it functions solely as a modification to existing contract documents. The changes emphasize design refinements and scope clarifications, including protection of existing infrastructure at multiple sites, revised pavement removal limits, addition of ADA ramp details, and updated parking lot specifications. The engineer, Colin Finch, P.E., notes that receipt of this addendum must be acknowledged on page 1 of the proposal submitted for bids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
7885 Byron Center Ave SW, Suite A, Byron Center, MI 49315 616-277-2185 www.VKcivil.com
ADDENDUM NO. 1
2027 PAVING PROJECTS
GRAND RAPIDS PUBLIC SCHOOLS
KENT COUNTY, MICHIGAN
Date: October 30, 2026
To: ALL PLAN HOLDERS
From: Colin Finch, P.E., Project Engineer
Receipt of this Addendum No. 1 is to be acknowledged on page 1 of the Proposal submitted for bids. The following changes are hereby made part of the Contract Documents for the above project:
PROPOSAL:
The engineer’s item quantity estimates have been added to the proposal for bidding simplification. Each project is to be bid as a lump sum as provided on the cover sheet of the proposal as the controlling project contract price. The unit prices provided are not the controlling cost for the project.
Nutrition Building Proposal Sheet – Item #15 and Item #32 for 2.5” MDOT 4EL Base Course Asphalt have been revised to 3” MDOT 3EL Base Course Asphalt.
Nutrition Building Proposal Sheet – Item #16 and Item #33 for 2.5” MDOT 5EL Top Course Asphalt over Bond Coat have been revised to 2” MDOT 5EL Top Course Asphalt over Bond Coat.
CA Frost Proposal Sheet – Item #13 for 2.5” MDOT 4EL Base Course Asphalt has been revised to 3” MDOT 3EL Base Course Asphalt.
CA Frost Proposal Sheet – Item #14 for 2.5” MDOT 5EL Top Course Asphalt over Bond Coat has been revised to 2” MDOT 5EL Top Course Asphalt over Bond Coat.
CA Frost Proposal Sheet – Item #32 has been added: Adjust Casting to Finish Grade
CA Frost Proposal Sheet – Item #33 has been added: Place Stop Sign
Kent Hills West Proposal Sheet – Item numbering has been revised to avoid duplicate #5 items. Previous items #5-#19 have become #6-#20.
Kent Hills West Proposal Sheet – Item #21 added for $1,000 allowance for playground pavement striping.
Colin Finch, P.E.
October 30, 2026
PLANS:
Kent Hills West Plan Sheet – A note has been added to emphasize protection of the existing poured-in-place playground surface.
Kent Hills West Plan Sheet – A note has been added for the contractor to include a $1,000 allowance for playground striping.
CA Frost Plan Sheet – Sidewalk at the driveway entrance at Covell Ave has been revised from remove to protect.
CA Frost Plan Sheet – Limits of full depth pavement removal and curb removal have been revised around the proposed curb peninsula, including new removal of an existing curb island.
CA Frost Plan Sheet – Notes have been added to protect and adjust the casting in the removed curb island.
CA Frost Plan Sheet – The east end of the existing western curb island has been extended.
CA Frost Plan Sheet – The proposed peninsula has been redesigned and contains sidewalk and ADA ramp. Crosswalk location has been revised with the addition of a stop sign.
CA Frost Plan Sheet – New curb island has been added to replace the removed curb island.
CA Frost Plan Sheet – Pavement striping has been added to delineate a parent drop off lane.
CA Frost Plan Sheet – Proposed trees have been specified as Japanese Maple.
CA Frost Plan Sheet – Parking counts have been revised.
Project Details Plan Sheet – Parking Lot Paving Detail has been revised to 3” MDOT 3EL Base Course Asphalt and 2” MDOT 5EL Top Course Asphalt over Bond Coat.
Project Details Plan Sheet – ADA sidewalk ramp detail has been added.
By:
Colin Finch, P.E.