This document is an Addendum Two Revised Scope of Work for Bid S-10-25, issued by the City of Cheyenne, Wyoming, for the Kiwanis Community House hardwood floor replacement project located at 4603 Lions Park Drive. The project involves removing existing flooring and base coving from approximately 3,870 square feet, installing standard hardwood underlayment and 3 1/4 Maple Grade 2 hardwood, installing black metal transition strips at six interior thresholds, and applying a waterborne sport court finish with specific Bona brand sealant and finish products. The work must be completed between January 27th and March 2nd, with a two-year warranty on workmanship and materials.
The bid includes a base bid for reinstalling existing coving and a separate alternate bid item to replace all base coving with new black coving. The City specifies that no subfloor replacement is anticipated, and four existing surface-mount electrical boxes will remain in place for future electrician replacement. Bidders are required to submit a Bid Bond only for the base bid, and special care must be taken to ensure the new floor height does not restrict the operation of partition or sliding doors. The document provides detailed specifications for the flooring installation, including the specific finish products to be used and the application process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid S-10-25 / Addendum Two Revised / Page 1 of 2
BID S-10-25 / SCOPE OF WORK / ADDENDUM TWO REVISED
Kiwanis Community House hardwood floor replacement 4603 Lions Park Drive Cheyenne, Wy 82001
Approximate square footage is 3870
Base bid:
1. Remove Existing flooring and dispose of
2. Remove base coving with intent to reinstall.
3. Install standard hardwood underlayment
4. Install 3 1/4 Maple Grade 2
5. Install new metal transition strips at all interior thresholds (6) which shall be black in color.
6. Finish with waterborne sport court finish (high gloss)
a. One coat of sealant followed by three coats of finish
b. Sealant product shall be:
i. Bona SuperSport Seal® Waterborne wood sport floor sealer
c. Finish product shall be:
i. Bona SuperCourt® HD Premium Two-component
Waterborne Wood Floor Finish
ii. If SuperCourt HD is not available, Bona SuperSport
MVP™ may be utilized. Product must be a two-component system.
7. Reinstall existing coving.
8. Perform final cleanup
9. Two-year warranty on workmanship and materials.
10. The City does not wish for any subfloor replacement to be completed. Unless the need is identified but not anticipated.
11. The four (4) existing surface mount electrical boxes shall be left in place. These will be replaced by an electrician and rough-in dimensions will be provided.
Bid S-10-25 / Addendum Two Revised / Page 2 of 2
12. Care should be taken to ensure that the height of the final surface of the finished floor, does not restrict the operation of the partition / sliding door.
Alternate bid items:
1. Remove and replace all base coving with new coving which shall be black in color.
a. Bid Bond only needs to be submitted for Base Bid, not Bid
Alternate.
Timeline: work must be completed during the timeline of Jan 27th –
March 2nd