Addendum Two.pdf

PDF 300 KB Posted

Attached to
RFB-275-26 Willisburg Lake Dam Rehabilitation Project
Solicitation number
RFB 785 2600000643 3
Issued by
Kentucky

About this file

This is an addendum document to RFB-275-26 Willisburg Lake Dam Rehabilitation Project, issued by the State of Kentucky. The addendum provides clarifications and modifications to the original request for bids regarding the rehabilitation of Willisburg Lake Dam. The document addresses questions submitted by potential bidders and issues additional guidance on project requirements, specifications, and bid submission procedures. The addendum supersedes conflicting language in the original solicitation documents and becomes part of the binding contract requirements for all bidders. Potential bidders are required to acknowledge receipt and incorporation of this addendum in their bid submissions to ensure compliance with the most current project specifications and evaluation criteria.

The addendum includes technical clarifications on dam rehabilitation scope items, updates to material specifications, and revisions to construction methodology requirements. It may address questions related to site conditions, environmental considerations, permitting requirements, or specific engineering standards applicable to the dam rehabilitation work. Bidders must carefully review the addendum to ensure their proposals account for all modifications and additions to the original solicitation requirements and to avoid submission of non-responsive bids that fail to address the updated specifications and conditions outlined in this document.

View the file

Other files

File Type Posted
Addendum One.pdf PDF
Final_RFB_785_2600000643_3_SO_FORM.PDF PDF
Final_RFB_785_2600000643_2_SO_FORM.PDF PDF
Final_RFB_785_2600000643_1_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-275-26

FOR: Rehabilitation of Willisburg Lake Dam Kentucky Division of Water Energy and Environmental Cabinet Washington County, Kentucky

DATE: June 16, 2026

RFB-785-2600000643

ADDENDUM NO. Two (2)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-275-26 For: Rehabilitation of Willisburg Lake Dam Kentucky Division of Water Energy and Environmental Cabinet Washington County, Kentucky

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

ADDENDUM NO. Two (2)

Date: June 15, 2026

RFB – 275-26

Item 1: Questions and answers listed below:

Question 1: Request for material substitution for culvert water proofing materials per Section 07 13 26 of the Technical Specifications. The proposed product is MEL-ROL SYSTEM, manufactured by W. R.

Meadows.

Response: The proposed MEL-ROL SYSTEM, manufactured by W. R. Meadows, does not appear to meet the minimum puncture requirements of 60 pounds per ASTM E154 outlined in Section 07 13 26 of the Technical Specifications. Additional information about the material would be required because it does not meet the specified requirements for minimum puncture and therefore would not be an acceptable substitution given the limited information provided at this stage of the project (bidding).

Question 2: Can H-Piles for a soldier pile or lagging wall be driven into the dam specifically for the culvert section (Spillway Inlet) beneath KY 555?

Response: Driving of sheet piling, H-piles, or any other type of piling in the embankment is prohibited at all times during construction, including for the use of temporary bracing in accordance with the

Construction Restrictions, Note 14 shown on Drawing A03.

Addendum Two
Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM

Addendum_2_Response