Addendum Q&A.pdf
PDF 181 KB Posted
- Attached to
- CREW Willow Mulching
- Solicitation number
- ITB-15435
- Issued by
- Leon County, Florida
About this file
This Addendum Q&A document issued by the Florida Fish and Wildlife Conservation Commission (FWC) provides clarifications to Solicitation No. FWC 25/26-68 for mechanical mulching services at the Corkscrew Regional Ecosystem Watershed (CREW) Wildlife and Environmental Area in Collier County, Florida. The project involves mechanical treatment of invasive woody vegetation through mulching operations on a per-acre basis. Work must commence no sooner than April 27, 2026, and be completed no later than June 10, 2026, with final invoicing due by June 17, 2026. The sealed bid submission deadline is April 17, 2026, at 2:30 PM ET, with an anticipated award date of April 21, 2026. The contract will be effective for one year from the Purchase Order issuance, with FWC holding the option to renew for up to two additional years under the same terms and conditions.
The addendum clarifies that alternative equipment meeting Scope of Work specifications is acceptable, including excavators with flotation mats or amphibious excavators for challenging terrain conditions. No scheduling buffer or contingency extension will be granted; contractors must complete all contracted acreage within the specified timeframe, though Force Majeure provisions may apply in extraordinary circumstances. The total project budget across all three fiscal years is $300,000 ($100,000 per year), with payment issued for actual acreages mulched and approved by the FWC Contract Manager. References will be contacted on April 20, 2026, prior to award. Evaluation is based on lowest total price from responsive and responsible bidders. The South Florida Water Management District may separately procure up to $150,000 in additional mechanical treatment outside this FWC solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 287 ITB 68 Final Draft.pdf | ||
| Addendum Q&A.pdf | ||
| 287 ITB 68 Final Draft.pdf | ||
| 287 ITB 68 Final Draft.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners
Rodney Barreto
Chairman
Coral Gables
Steven Hudson
Vice Chairman
Fort Lauderdale
Preston Farrior
Tampa
Joshua Kellam
Palm Beach Gardens
Gary Lester
Oxford
Albert Maury
Coral Gables
Sonya Rood
St. Augustine
Office of the
Executive Director
Roger A. Young
Executive Director
Charles “Rett” Boyd
Assistant Executive Director
George Warthen
Chief Conservation Officer
Jessica Crawford
Chief of Staff
850-487-3796
850-921-5786 FAX
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street
Tallahassee, Florida
32399-1600
Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T)
800-955-8770 (V)
MyFWC.com
DATE: APRIL 10, 2026
ADDENDUM NO.: 1
BID NO.: FWC 25/26-68
BID TITLE: CREW WILLOW MULCHING
UPDATE: QUESTIONS & ANSWERS
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s
(FWC) Solicitation No. FWC 25/26-68, “CREW Willow – Mulching ”.
All responses to the subject solicitation must be received no later than 2:30
PM (ET) on Friday, April 17, 2026.
A response received after the exact time specified will not be considered.
Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in
Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875
Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Xavier Wilson
FWC Procurement Manager
FWC SOLICITATION ADDENDUM 2
BEGIN ADDENDUM
QUESTION #1
In relation to the Machinery to be used, Will the awarded Vendor be allowed to use a JD
275G with a Fecon Mulcher head, as opposed to using a Prinoth Raptor 500 w/ M700
Forestry Mulcher?
ANSWER #1
Other equipment will be accepted as long as it meets the requirements included in the
Scope of Work under Section 3 (Equipment Specifications).
QUESTION #2
Once the Bid is awarded, will the Vendor be granted a 15%-25% Scheduling Buffer in lieu of mitigating circumstances?
ANSWER #2
No, mulching of the contracted total acreage for Fiscal Year 25/26 shall begin no sooner than April 27, 2026 and shall be completed no later than June 10, 2026. The awarded contractor should mobilize the necessary equipment to complete the contracted project acreage within that time frame (see Force Majeure language in the “TERM” clause if an extension is warranted).
QUESTION #3
Is there a contingency plan if we were to receive an increase of untimely/unexpected rainfall in the proposed area, preventing the awarded Vendor from moving forward?
ANSWER #3
No, mulching of the contracted total acreage for Fiscal Year 25/26 shall begin no sooner than April 27, 2026 and shall be completed no later than June 10, 2026 (see Force Majeure language in the “TERM” clause if an extension is warranted)
QUESTION #4
Considering all References are submitted within the proper time frame, and now the
Project Manager has to contact the list of References, will there be some type of notification given to at least inform the List of References that an attempt should be expected from the State within a certain time frame?
FWC SOLICITATION ADDENDUM 3
ANSWER #4
References for the low-bid contractor will be contacted by the Contract Manager prior to the Anticipated Date of Intended Award (Tuesday, April 21). Please let your references know they are likely to be contacted on April 20 (Monday).
QUESTION #5
In relation to the Set Budget Amount, it was mentioned that the Proposed Contract is a one (1) year contract with an additional year #2 and a subsequent possible year #3. The
$300,000.00 Budget that is set, is that to cover each year, including the initial year (#1) or is that a reflection of the entire project for the three(3) year period?
ANSWER #5
The budget for all three fiscal years is $300,000 ($100,000 per FY)
QUESTION #6
If the Project Manager should or elects to only service/mulch 1/3 of the entire
"ACRES PROJECT" and all service area work is determined by the quoted dollar amount, will the Awarded Vendor be paid 50% of expected Revenue after successfully completing 50% (halfway portion) of the said number of Acres?
ANSWER #6
The awarded vendor will be paid for the total acreages mulched and approved by the
FWC Contract Manager per the Scope of Work (Section 8)
QUESTION #7
Previous contractor used swamp mats to complete project because of how soft the ground was. Any psi over the 1.0 will sink. A pontoon excavator/ amphibious excavator or excavator with Mats can provide this Buoyancy in muck. Are we able to bring in an amphibious excavator?
ANSWER #7
Yes as long as the equipment used meets the requirements included in the Scope of Work under Section 3 (Equipment Specifications).
QUESTION #8
Can this be done with excavators and flotation mats?
ANSWER #8
Yes as long as the equipment used also meets the requirements included in the Scope of
Work under Section 3 (Equipment Specifications).
FWC SOLICITATION ADDENDUM 4
END ADDENDUM