This is Addendum One to Invitation to Bid No. RFB-65-27 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for an emergency chiller replacement project at the Adair Youth Development Center operated by the Department of Juvenile Justice in Columbia, Kentucky. The addendum clarifies and modifies specifications and drawings for the project, which includes procurement and installation of an air-cooled chiller system. Key specifications require the contractor to provide and install a temporary chiller within the first 30 days of project start, including all necessary piping and power, with the temporary unit remaining operational until substantial completion. The chiller must include BacNet capabilities to communicate with new mechanical equipment and control the chilled water pump, though the existing control system will be reused without upgrades. The contractor must coordinate temporary chiller flex hose routing in the field with the engineer, with placement on asphalt acceptable in some areas but requiring support in others to avoid interference with entry doors and generator access.
Additional clarifications address existing infrastructure reuse and component specifications. The existing concrete pad for the chiller shall be reused without enlargement for the basis of design chiller; however, if an alternatively proposed chiller exceeds the existing pad dimensions, the contractor bears responsibility for concrete pad enlargement, subject to engineer verification on-site. The chilled water piping shown in the chase is to be reused as it enters and leaves the chase. The air separator must be equal to a Bell & Gossett R-6 unit with strainer, automatic air vent, blow-down valve, and drain piping to the nearest floor drain, with supports and mountings equal to the existing configuration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_RFB_785_2700000071_2_SO_FORM.PDF | ||
| Final_RFB_785_2700000071_1_SO_FORM.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-65-27
FOR: Emergency Chiller Replacement Adair Youth Development Center Department of Juvenile Justice Columbia, Kentucky
DATE: September 8, 2026
RFB-785-2700000071
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-65-27 For: Emergency Chiller Replacement Adair Youth Development Center Department of Juvenile Justice Columbia, Kentucky
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
E-TECH CONSULTANTS, PLLC
Consulting Engineers
378 Park Avenue Lexington, KY 40502
PROJECT: RFB-65-27
Project #523-CCEK-AC16-00
DJJ – ADAIR EMERGENCY CHILLER REPLACEMENT
401 Appleby Drive Columbia, KY 42728
ADDENDUM ITEMS
The following items shall be included in the Contract Documents for this Project.
ITEM NO. ONE (1)
SPECIFICATION 231670 – AIR COOLED CHILLERS
- Refer to Specification, Paragraph 1.01 o Clarify that the Contractor provide and install the temporary Chiller within the first 30 days of the Start of the Project including all piping and power required for the installation of this temporary chiller. The temporary Chiller shall remain operational until Substantial Completion of the Project is obtained. See Specification for further details.
o Clarify that the route indicated for the temporary chiller flex hoses are to be coordinated in the field with the Engineer. It some areas, laying the hoses on the asphalt pavement is acceptable, however in other cases the flex hoses shall be supported as they cannot interfere with operations of the entry door and/or generator access.
o Chiller shall have BacNet Capabilities. The intent of this specification is to reuse the existing control system and not provide upgrade of the control system with this project. The Chiller shall control the Chilled Water Pump at this time and to communicate with the new mechanical equipment. All new equipment are to have BacNet Communication Interface modules. A future Controls Project will interface the new equipment with the new controls system.
o The existing concrete pad for the Chiller shall be reused. No new concrete pad enlargement is required for the basis of design Chiller. If an Alternateley Proposed Chiller is of longer or wider physical sizes, then the Contractor is responsible for the increased dimensions of a concrete pad enlargement which is to be verified on-site with Engineer before its installation.
Attachments: None Drawings: None
ITEM NO. TWO (2)
SHEET M-3.2 – CHILLED WATER PIPING DIAGRAM
- Refer to Detail #1 o Clarify that the chilled water piping shown in the Chase is to be reused, as it enters and leaves the chase.
E-TECH CONSULTANTS, PLLC
Consulting Engineers
378 Park Avenue Lexington, KY 40502
ITEM NO. THREE (3)
SHEET M-3.2 – AIR SEPARATOR
- Refer to Schedule and Detail #4:
o Clarify that the Air Separator shall be equal to Bell & Gossett R-6 with strainer, automatic air vent, blow down valve and drain piping to nearest floor drain. Supports and Mountings shall be equal to existing.
END
| Addendum One |
| Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings. |
| END OF ADDENDUM |
| DJJ Adair Chiller Replacement Columbia KY Addendum One |
| SPECIFICATION 231670 – AIR COOLED CHILLERS |
| - Refer to Specification, Paragraph 1.01 |
| o Clarify that the Contractor provide and install the temporary Chiller within the first 30 days of the Start of the Project including all piping and power required for the installation of this temporary chiller. The temporary Chiller shall remain ope... |
| o Clarify that the route indicated for the temporary chiller flex hoses are to be coordinated in the field with the Engineer. It some areas, laying the hoses on the asphalt pavement is acceptable, however in other cases the flex hoses shall be support... |
| o Chiller shall have BacNet Capabilities. The intent of this specification is to reuse the existing control system and not provide upgrade of the control system with this project. The Chiller shall control the Chilled Water Pump at this time and to co... |
| o The existing concrete pad for the Chiller shall be reused. No new concrete pad enlargement is required for the basis of design Chiller. If an Alternateley Proposed Chiller is of longer or wider physical sizes, then the Contractor is responsible for ... |
| SHEET M-3.2 – CHILLED WATER PIPING DIAGRAM |
| - Refer to Detail #1 |
| o Clarify that the chilled water piping shown in the Chase is to be reused, as it enters and leaves the chase. |
| SHEET M-3.2 – AIR SEPARATOR |
| - Refer to Schedule and Detail #4: |
| o Clarify that the Air Separator shall be equal to Bell & Gossett R-6 with strainer, automatic air vent, blow down valve and drain piping to nearest floor drain. Supports and Mountings shall be equal to existing. |