RFP-55-27 KASTOW - ORPHAN WELL PACKAGE - WEBSTER #003
Solicitation number
RFP 785 2700000048 2
Issued by
Wayne County, Kentucky

About this file

This is Addendum No. 1 to Invitation to Bid No. RFP-55-27 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for the Kentucky Abandoned Storage Tank and Orphan Well Reclamation Program (KASTOW) Webster 003 project. The addendum, dated September 4, 2026, modifies the plugging activities requirements for orphan wells in Western Kentucky counties (Ballard, Butler, Caldwell, Calloway, Carlisle, Christian, Crittenden, Daviess, Fulton, Graves, Hancock, Henderson, Hickman, Hopkins, Livingston, Logan, Lyon, Marshall, McCracken, McLean, Muhlenberg, Ohio, Todd, Trigg, Union, and Webster). The revised specifications establish distinct procedures for wells with total depths at 1500 feet or shallower versus deeper wells. For shallow wells, work includes establishing wellhead entry, extracting tubing and rods if present, tripping in with rig tools to establish total depth, running tubing with water or gel circulation, perforating casing if necessary, and circulating Class A, Class L, or Type 1L cement to surface. For deeper wells, procedures include pulling rods and tubing, removing free casing, spotting cement plugs at total depth and across perforated zones, and isolating freshwater and coal seams with cement from 600 feet to surface.

All plugging activities must be performed using a service rig with a work string of steel tubing run downhole; slickline plugging is not acceptable. Special provisions apply when hydrogen sulfide gas is present or detected, requiring the use of 50/50 POZ or latex-laden cement. Prior to commencing work, bidders must confer with the Division Inspector and ensure landowner access approval. Site reclamation requirements include constructing access roads, digging and lining pits with 6-mil liners, removing brush and debris, cutting off casing 3 feet below surface, properly disposing of fluids, and fully grading and stabilizing the wellsite. The addendum revises Attachment K of the original solicitation and supersedes all previously issued specifications for this program.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFP-55-27

FOR: Kentucky Abandoned Storage Tank and Orphan Well Reclamation Program (KASTOW) Webster 003

DATE: September 4, 2026

RFP-785-2700000048

ADDENDUM NO. One (1)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to attachment K and use the attached in lieu of previously issued.

END OF ADDENDUM

Invitation to Bid No. RFP-55-27 For: Kentucky Abandoned Storage Tank and Orphan Well Reclamation Program (KASTOW) Webster 003

Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration

ATTACHMENT K

*PLUGGING ACTIVITIES MUST BE PERFORMED WITH A SERVICE RIG AND WORK

STRING OF STEEL TUBING TO RUN DOWNHOLE. “SLICKLINE” PLUGGING WILL

NOT BE ACCEPTABLE.

WESTERN KY (Ballard, Butler, Caldwell, Calloway, Carlisle, Christian, Crittenden, Daviess, Fulton, Graves, Hancock, Henderson, Hickman, Hopkins, Livingston, Logan, Lyon, Marshall, McCracken, McLean, Muhlenberg, Ohio, Todd, Trigg, Union, Webster)

Wells with TD at 1500’ or shallower

• Confer with Division Inspector, assure landowner access is approved

• Construct access road to well

• Dig pit and line with 6 mil liner

• Remove brush from location, rig-up service rig

• Establish wellhead entry if not open casing, or dismantle wellhead if fully equipped

• If tubing & rods remain in well, extract same from the hole and trip out

• Trip in well with rig tools to establish TD and ensure no wellbore obstructions

• Run tubing to TD and pump minimum five barrels of water or 6% gel

• If casing is not cemented or unknown; perforate casing from 250’ to 50’; (50’ increments)

• Circulate Class A, Class L, or Type 1L cement solid to surface (Cement calculation based on hole volume). 50/50 POZ or latex laden cement shall be used if H2S gas is present and/or detected.

• Monitor cement level and top off as needed

• Cut off all casing 3 ft. below surface the next day to ensure no fall back has occurred

• Remove fluids from pit, properly dispose of same, and backfill pit

• Properly grade, stabilize, and fully reclaim wellsite as outlined in Scope of Work

Wells deeper than 1500’

• Confer with Division Inspector, assure landowner access is approved

• Construct access road to well

• Dig pit and line with 6 mil liner

• Remove brush from location, rig-up service rig

• Pull Rods & tubing, if present

• Any free casing (annulus not cemented) shall be removed. If no records are available to determine Top of Cement (TOC), a bond log may be required

• Trip in well with rig tools to establish TD and ensure no wellbore obstructions

• Run tubing, spot 200’ Class A, Class L, or Type 1L cement plug at TD. 50/50 POZ or latex laden cement shall be used if H2S gas is present and/or detected.

• Pull up above TOC, wash out, Tag Bottom Plug

• Pump spacer water or 6% gel

• Spot Class A or Class L cement plug 50’ below deepest perforation to 50’ above shallowest perforation (or production zones if open hole), across any and all perforated (or production zones in open hole) not covered by bottom plug. 50/50 POZ or latex laden cement shall be used if H2S gas is present and/or detected.

• Pump spacer water or 6% gel

• If casing is not cemented or unknown; perforate casing from 250’ to 50’; (50’ increments)

• Spot Class A, Class L, or Type 1L cement from 600’ to surface (to isolate and protect fresh water and coal seams). 50/50 POZ or latex laden cement shall be used if H2S gas is present and/or detected.

• Monitor cement level and top off as needed

• Cut off all casing 3 ft. below surface the next day to ensure no fall back has occurred

• Remove fluids from pit, properly dispose of same, and backfill pit

• Properly grade, stabilize, and fully reclaim wellsite as outlined in Scope of Work

Addendum No One.pdf
Item 1: Refer to attachment K and use the attached in lieu of previously issued.
END OF ADDENDUM