Addendum No. 4.pdf
PDF 103 KB Posted
- Solicitation number
- RFB-785-2500000645-11
- Issued by
- Harrison County, Kentucky
About this file
This document is an Addendum (No. Four) to an Invitation to Bid issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration, for the Upper Guide Wall Repairs Project at Kentucky River Locks 2 & 3 in Henry County. The addendum modifies two key aspects of the original bid: first, the bid due date is extended to July 30, 2025 at 1:30 PM ET, and second, the project schedule is extended by one year. The revised substantial completion dates are now set for Lock 3 on November 30, 2026 (with a construction season from July 1, 2026 through November 30, 2026) and for Lock 2 on November 30, 2027 (with a construction season from July 1, 2027 through November 30, 2027).
The addendum ensures that bidders understand the updated timeline and can adjust their proposals accordingly, with the intent of allowing one construction season per site. The project is associated with the Kentucky River Authority and involves repairs to the upper guide walls at two separate lock locations. The bid number is RFB-235-25, with a reference number of RFB-785-2500000645, and was issued on May 28, 2025. The document is signed by Kristi Sharp, Statewide Procurement Manager from the Division of Engineering and Contract Administration.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-235-25
FOR: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky
DATE: May 28, 2025
RFB-785-2500000645
ADDENDUM NO. Four (4)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Change Bid Due date to July 30, 2025 at 1:30 PM ET. All other information remains the same.
Item 2: The project schedule for the KY River Locks 2 and 3 Upper Guide Wall Project will be extended one (1) year. The revised Substantial Completion dates and updated construction seasons are listed below. The intent is to allow one construction season per site.
Substantial Completion for Lock 3 – November 30, 2026 Construction Season July 1, 2026, through November 30, 2026
Substantial Completion for Lock 2 – November 30, 2027 Construction Season July 1, 2027, through November 30, 2027
END OF ADDENDUM
Invitation to Bid No. RFB-235-25 For: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky
Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration
| Item 2: The project schedule for the KY River Locks 2 and 3 Upper Guide Wall Project will be extended one (1) year. The revised Substantial Completion dates and updated construction seasons are listed below. The intent is to allow one construction sea... |
| END OF ADDENDUM |