Addendum Eight.pdf
PDF 176 KB Posted
- Solicitation number
- RFB-785-2500000645-11
- Issued by
- Harrison County, Kentucky
About this file
This document is an Addendum (No. Eight) to an Invitation to Bid (RFB-235-25) issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration for the Upper Guide Wall Repairs Project at Kentucky River Locks 2 & 3 in Henry County, Kentucky. The addendum, dated July 27, 2025, provides clarification on project scheduling and liquidated damages related to weather and flooding delays during the specified construction season of July 1 to November 30.
The addendum addresses a contractor's question about potential liquidated damages if work is delayed beyond the construction season. The response indicates that liquidated damages will be computed based only on the established, adjusted Substantial Completion date, and are not tied to specific construction seasons. The Owner will not consider contract price adjustments for river levels, will only grant time extensions for delays, and intends to establish a Completion Date between July 1 and November 30. The contractor is allowed to work outside the specified construction season but will not receive project adjustments for high-water conditions during that time, and remains responsible for protecting and securing the site at all times.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-235-25
FOR: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky
DATE: July 27, 2025
RFB-785-2500000645
ADDENDUM NO. Eight (8)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-235-25 For: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky
Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration
ADDENDUM NO. Eight (8)
Date: July 25, 2025
RFB – 235-25
Item 1: Question and answer listed below:
Question 1: If weather and flooding delays cause the contractor’s schedules to push outside of
“construction season” (July 1 – November 30) prohibiting the contractor from starting work again until the following July 1st date, will liquidated damages be charged for the days in between or will the construction schedule be paused?
Response: No. Liquidated damages will be computed based only on the established, adjusted
Substantial Completion date. Liquidated damages are not tied to the “construction seasons” as specified.
For clarity:
• The Contractor is not prohibited from working outside the specified dates of the Construction Season. Work is allowed December 1 through June 30, although project adjustments will not be accepted for high-water conditions during this time.
• The Owner will not consider adjustments to the Contract Price based on river levels, regardless of dates (Refer to Article 4, Temporary Shutdowns/Elevated Water Levels of the Special Conditions).
• If the Work is delayed, only an extension in time will be granted. No adjustments to the Contract Price will be considered for the General Conditions.
• Requests for schedule extensions shall adhere to the requirements outlined in Article 16 of the General Conditions and the Special Conditions - Temporary Shutdowns/Elevated Water Levels.
• Schedule extensions due to high river levels will be considered by the Owner ONLY for high water events that occur during the Construction Seasons (July 1 – November 30 annually).
• Liquidated damages will accrue only if substantial completion is not achieved by the established, adjusted date for completion, regardless of the dates.
• To avoid assessments of Liquidated Damages outside of the Construction Season, the Owner intends to establish a Completion Date between July 1 and November 30.
• The Contractor is responsible for protecting and securing the site(s) at all times, including dates outside the Construction Season (Refer to Article 14.3, Construction Sequence of the Special Conditions).