Addendum No. 2 - Baker Family Learning Center Expansion.pdf
PDF 157 KB Posted
- Attached to
- 1632 - Baker Family Learning Center Expansion
- Solicitation number
- ANE223-ANE2C-6498
- Issued by
- San Bernardino County, California
About this file
Summary of Addendum No. 2 - Baker Family Learning Center Expansion
This addendum modifies the bid documents for the Baker Family Learning Center Expansion project (Project No. 10.10.1632) administered by San Bernardino County's Project and Facilities Management Department in Muscoy, California. The addendum updates the sealed bid submission deadline to October 8, 2026 at 3:00 PM, with bids to be submitted to the Project and Facilities Management Department at 620 South E Street, San Bernardino, CA 92415-0184. The addendum clarifies that two certification items are not applicable: the Signed Certification of Offeror/Bidder Regarding Tax Delinquency and Felony Convictions and the Signed Trade Restriction Certification. Additionally, Sheet # E-.04 has been omitted from the project plans and specifications. The instructions to bidders have been revised to provide updated access information for project meetings, including a Microsoft Teams meeting link and dial-in details for bidders requiring remote access.
The addendum was issued on September 28, 2026, and signed by Sarah Riley, Chief of Project Management on September 29, 2026. All other requirements and terms of the original bid documents, including the contract specifications, pricing terms, performance bonds, prevailing wage requirements, and project scope for the 3,514 square foot expansion, remain unchanged. Bidders must acknowledge receipt of this addendum by noting its number and date in their bid proposal.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No.: 10.10.1632 Page 1 of 2
Project No. 10.10.1632
ADDENDUM NO. 2
TO THE BID DOCUMENTS FOR THE
BAKER FAMILY LEARNING CENTER EXPANSION
AT
MUSCOY, CA
The following changes and/or additions shall be made to the plans and/or specifications. All other requirements of the contract documents shall remain the same. The Bidder shall acknowledge receipt of the addendum by inserting its number and date in the Bid Proposal.
Clarifications to the Bid Proposal Checklist Items:
The following items are not applicable for the project;
• Signed Certification of Offeror/Bidder Regarding Tax Delinquency and Felony Convictions
• Signed Trade Restriction Certification
Changes to Bid Proposal:
Sheet # E-.04 Has been omitted.
Changes to Bid Due Date:
Sealed Bids to be turned in on or before 3:00 PM on October 8th, 2026 to Project and Facilities Management Department, 620 South E Street, San Bernadino, CA 92415-0184
Changes to the Instructions to Bidders:
Instructions to Bidders, Paragraph L, is revised to indicate updated access information.
Microsoft Teams meeting Join:https://teams.microsoft.com/meet/247046018887854?p=2ahbYTD1LjIf3htF67 https://teams.microsoft.com/meet/247046018887854?p=2ahbYTD1LjIf3htF67 https://teams.microsoft.com/meet/247046018887854?p=2ahbYTD1LjIf3htF67
Project No.: 10.10.1632 Page 2 of 2
Meeting ID:247 046 018 887 854 Passcode:zV6gL6hY
Need help? | System reference Dial in by phone +1 661-568-6806,,16258022# United States, Santa Clara Find a local number Phone conference ID:162 580 22#
End of Addendum No. 2
Sarah Riley, Chief of Project Management Project and Facilities Management Department, Project Management
DS:sp
San Bernardino County Project and Facilities Management Department, Project Management 385 North Arrowhead Avenue, Third Floor San Bernardino, CA 92415-0184 https://pfm.sbcounty.gov/
DATE: 9/28/26
Sarah Riley (Sep 29, 2026 08:33:25 PDT) https://aka.ms/JoinTeamsMeeting?omkt=en-US https://teams.microsoft.com/l/meetup-join/19%3ameeting_Nzk1ZTcwZjYtZTQ3OC00MGZkLTg2NGQtZDg0YThlZDY3YzFi%40thread.v2/0?context=%7b%22Tid%22%3a%2231399e53-6a93-49aa-8cae-c929f9d4a91d%22%2c%22Oid%22%3a%22219fe10b-8f1b-4201-9958-ea3951267e6e%22%7d https://dialin.teams.cloud.microsoft/79918c0c-079d-433b-ace1-5102e02b9197?id=16258022 https://pfm.sbcounty.gov/ https://aka.ms/JoinTeamsMeeting?omkt=en-US https://teams.microsoft.com/l/meetup-join/19%3ameeting_Nzk1ZTcwZjYtZTQ3OC00MGZkLTg2NGQtZDg0YThlZDY3YzFi%40thread.v2/0?context=%7b%22Tid%22%3a%2231399e53-6a93-49aa-8cae-c929f9d4a91d%22%2c%22Oid%22%3a%22219fe10b-8f1b-4201-9958-ea3951267e6e%22%7d https://dialin.teams.cloud.microsoft/79918c0c-079d-433b-ace1-5102e02b9197?id=16258022 https://pfm.sbcounty.gov/
Addendum No. 1 - Fuel Tank Infrastructure Phase IV Final Audit Report 2026-09-29
Created: 2026-09-28
By: Robert Martinez (Robert.martinez@pfm.sbcounty.gov)
Status: Signed
Transaction ID: CBJCHBCAABAA1xBGtSCLoh-fFsmibVr2QwyUOylJJwMY
"Addendum No. 1 - Fuel Tank Infrastructure Phase IV" History Document created by Robert Martinez (Robert.martinez@pfm.sbcounty.gov)
2026-09-28 - 11:11:28 PM GMT
Document emailed to Sarah Riley (sarah.riley@pfm.sbcounty.gov) for signature
2026-09-28 - 11:11:31 PM GMT
Email viewed by Sarah Riley (sarah.riley@pfm.sbcounty.gov)
2026-09-29 - 3:33:16 PM GMT
Document e-signed by Sarah Riley (sarah.riley@pfm.sbcounty.gov) Signature Date: 2026-09-29 - 3:33:25 PM GMT - Time Source: server - Signature Appearance Selected: DRAW
Agreement completed.
2026-09-29 - 3:33:25 PM GMT
| 2026-09-29T15:33:27+0000 | |
| Certified by Adobe Acrobat Sign |
File details come from the government source that posted it. Updated .