Addendum No. 1 RFQ-CMAR Animal Adoption Center.pdf
PDF 157 KB Posted
- Solicitation number
- 525-525-09262025
- Issued by
- Halifax County, North Carolina
About this file
This document is an Addendum #1 for a Request for Qualifications (RFQ) for a Construction Manager at Risk (CMAR) project issued by the Harnett County Finance Department for an Animal Adoption Center. The project is seeking a CMAR for construction services, with a preliminary estimated budget of $10 million and a targeted construction start date of June 2026, which is subject to design and permitting progress. The county will manage the project with in-house oversight, and the architect selection is being handled internally.
The project will be funded through a combination of general funds and county bonds. No specific Minority/Women/Veteran Business Enterprise (MWBE) goals have been established at this time. Proposers are advised to assume an AIA contract form template and should note that executed Appendix documents and the Surety Letter will not count against the 25-page submission limit. Site due diligence reports, including geotechnical, environmental, utility mapping, and survey documents, have already been posted for potential bidders to review.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25.09.09 Revision CMAR RFQ Adoption Center.pdf | ||
| 1241148ea-Ph1 (002).pdf | ||
| 25.01.24 - Survey Information.pdf | ||
| Harnett Co_US 421 N_Soil Wetland Recon.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Finance Department
RFQ FOR CMAR FOR THE ANIMAL ADOPTION CENTER
HARNETT COUNTY
Addendum #1
TO: Prospective Vendors
FROM: Renea Warren-Ford, Finance
DATE: September 16, 2025
PROJECT: RFQ for CMAR for the Animal Adoption Center
NOTICE: Questions and Anwers
1. Funding Source – Could you confirm whether the project is funded via County bonds, general funds, or supported by any state or federal grants?
This project is funded by both general funds and bonds.
2. Project Oversight – Will the County be managing this project directly, or will a third-party
Owner’s Representative be involved during preconstruction and construction phases?
The County will be managing the project with in-house oversight.
3. Architect Selection – Will the CMAR be expected to have influence on the architect selection?
No, the architect is being handled in-house and we are negotiating a contract.
4. Target Budget – Is there a preliminary construction budget or GMP range the County is working within?
There is a preliminary estimated budget of $10M.
PO Box 760
455 McKinney Parkway
Lillington, NC 27546
Phone: 910-893-7557
Fax: 910-893-3445 www.harnett.org
Finance Department
5. Site Due Diligence – Will reports such as geotechnical, environmental, utility mapping, or survey be provided during preconstruction?
The studies and surveys have been posted.
6. Schedule Flexibility – Is the June 2026 construction state date fixed, or subject to design and permitting progress?
This is subject to design and permitting progress.
7. MWBE Goals – Are there any defined goals or expectations for MWBE, local contractor, or veteran participation?
The County has not set MWBE goals at this time.
8. Contract Form – Will the County provide a standard contract template for CMAR services, or should proposers assume an AIA form?
Proposers should assume an AIA form template.
9. For qualification submission, we would like to request that the executed Appendix documents 1
& 2 + Surety Letter NOT count against the 25-page limit. We are requesting because this could be 4-5 pages alone.
The mentioned documents do not count against the 25-page limit.
END DOCUMENT