Addendum No. 1.pdf

PDF 150 KB Posted

Attached to
Elkhorn Elementary School Site Work Inc 1 Project (Addendum No. 1)
Solicitation number
RFQ/P # 0915-8215-470-77
Issued by
San Joaquin County, Stockton City, California

About this file

This is Addendum No. 1 to a Request for Qualifications and Proposal (RFQP) issued by Elkhorn Elementary School Inc for Phase 1 Site Work in California. The project encompasses comprehensive site make-ready operations and infrastructure development required before main building construction begins, including removal of conflicting existing site elements, major earthwork to establish proper site drainage and elevation, complete infrastructure upgrades with wet and dry utility lines, construction of new student drop-off lanes, and essential site provisions. A mandatory informational meeting is scheduled for Friday, August 7, 2026 at 9:30 A.M. The deadline for written questions from respondents is Friday, August 21, 2026 at 4:00 P.M., with the District issuing addenda to answer questions and clarifications by Friday, September 4, 2026. The submission deadline for responses to the RFQ/P is Friday, September 18, 2026 at 1:00 P.M. Notice to the selected developer to commence contract negotiation is anticipated for the week of October 5, 2026.

The addendum clarifies the bid submission time, which had appeared in two different formats in the original RFQ documentation. No information regarding pricing terms, set asides, incumbents, funding sources, or other financial details is provided in this addendum document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

Elkhorn Elementary School Inc 1 Phase 1 Site Work LLB RFQP No. 0915-8215-470-77

July 29, 2026

Questions

1. Is there anyway that you can clarify the bid submission time? There are two different times listed on the RFQ.

a. Bid and other important dates are as follows:

DATE ACTION ITEM

Friday, August 7, 2026 at 9:30 A.M. Mandatory Informational Meeting.

Friday, August 21, 2026 at 4:00 P.M. Last day to receive written questions from Respondents.

Friday, September 4, 2026 Last day for District to issue addenda to answer questions/clarifications.

Friday, September 18, 2026 at 1:00 P.M. Deadline for submissions in response to RFQ/P.

Week of October 5, 2026 Notice to selected developer to commence contract negotiation.

File details come from the government source that posted it. Updated .