Addendum No. 1 to Invitation for Bid 11A4244
This addendum, issued by the California Department of Transportation (Caltrans) on November 7, 2025, addresses clarifications and responses to prospective bidders for Multi-Provider, On Call, Vactor and Drainage Facility Cleaning services in San Diego and Imperial Counties. The solicitation seeks multiple contractors to provide on-call vactor and drainage facility cleaning services. Key operational clarifications include: contractors are not required to apply for encroachment or traffic control permits; contractors must pump out pump house chambers and pits themselves rather than having Caltrans perform pre-work pumping; Caltrans will inspect cleaned drainage facilities within 24 hours of contractor notification; and either the contractor or a subcontractor may hold the required Hazardous Substance Removal Certification to satisfy licensing requirements under Exhibit E, Section 4.
Previous Contract Performance and Bidding Context
The previous on-call vactor and drainage facility cleaning contract for San Diego and Imperial Counties (which was not a multi-provider agreement) resulted in four bids ranging from $3,468,560.00 to $35,153,000. The lowest bidder was United Storm Water, Inc. at $3,468,560.00, followed by American Integrated Services, Inc. at $5,250,740.00; both were non-Small Business entities. Downstream Services, Inc. bid $14,528,230.00 and Andersen Integrated Services, Inc. bid $35,153,000, with both designated as Small Business contractors. All other terms and conditions of the original IFB remain in full force and effect.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB_Solicitation_package_11A4244_.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1727 30th STREET, MS-65
SACRAMENTO, CA 95816
PHONE (916) 227-6000
TTY 711
https://dot.ca.gov/programs/procurement-and-contracts/
November 7, 2025
Addendum No. 1 Invitation for Bid (IFB) 11A4244
Multi-Provider, On Call, Vactor and Drainage Facility Cleaning services in San Diego and Imperial Counties
NOTICE TO ALL PROSPECTIVE BIDDERS:
Addendum No. 1 is being issued for the above-referenced IFB. Bids for this work shall be with the full understanding of this Addendum.
The following represents questions submitted for this IFB and the Department’s responses:
Question 1:
Is Caltrans willing to waive the requirement for the Contractor to hold a Hazardous Substance Removal Certification if our Subcontractor can provide one?
Response 1:
Yes. In the Agreement under Exhibit E, Section 4. Licenses and Permits, it states, “Contractor and/or subcontractor shall maintain the following training, permits and licenses for the duration of this Agreement”.
Question 2:
Can you provide the bid results for the last Multi-Provider, On Call, Vactor and Drainage Facility Cleaning services in San Diego and Imperial Counties?
Response 2:
The previous contract was not a multi-provider. The previous bid results for the last On Call, Vactor and Drainage Facility Cleaning services in San Diego and Imperial Counties were:
Bidder 1: United Storm Water, Inc. $3,468,560.00 SB= No
Bidder 2: American Integrated Services, Inc. $5,250,740.00 SB= No
Bidder 3: Downstream Services, Inc. $14,528,230.00 SB= Yes
Bidder 4: Andersen Integrated Services, Inc. $35,153,000 SB= Yes
DEPARTMENT OF TRANSPORTATION
ADMINISTRATION
DIVISION OF PROCUREMENT AND CONTRACTS
http://www.dot.ca.gov/dpac/ http://www.dot.ca.gov/dpac/ http://www.dot.ca.gov/dpac/
Question 3:
Traffic Control- Is Caltrans requiring the Contractor apply for encroachment/traffic control permits? If so, would Caltrans be willing to issue a “No Fee” encroachment/traffic control permit?
Response 3:
No, the contractor will not need to apply for encroachment/traffic control permits
Question 4:
Would Caltrans be willing to pump down the pump house chambers and pits as low as possible before the Contractor arrives to perform their work?
Response 4:
No, the contractor will have to pump out the pump house chambers and pits to perform the work.
Question 5:
The scope in Exhibit A does not state how long after the Contractor notifies Caltrans of cleaning drainage facilities will Caltrans complete inspections. Can you confirm?
Response 5:
We will check the drainage facilities within 24 hours of being notified.
All other terms and conditions set forth in the IFB remain in full force and effect.
Sincerely, Queenann Herron Queenann Herron Contract Analyst
“Provide a safe, sustainable, integrated and efficient transportation system to enhance California’s economy and livability”
| The following represents questions submitted for this IFB and the Department’s responses: |
| Response 1: |
| Yes. In the Agreement under Exhibit E, Section 4. Licenses and Permits, it states, “Contractor and/or subcontractor shall maintain the following training, permits and licenses for the duration of this Agreement”. |
| Response 2: |
| Response 3: |
| Response 5: |
| Queenann Herron |