Addendum No. 1
4 MB Posted
- Attached to
- Starr Park - Phase I - Project No. 02072023
- Solicitation number
- 02072023
- Issued by
- Clayton County, Georgia
About this file
Addendum No. 1 to Starr Park - Phase I Project
This is an addendum to the sealed unit price bid solicitation issued by the City of Forest Park, Georgia for the Starr Park - Phase I project (Project No. 02072023). The addendum addresses 24 written questions submitted by prospective contractors prior to the February 28, 2023 question deadline and provides clarifications on project requirements, bid procedures, and technical specifications. Key clarifications include confirmation that irrigation design is to be performed on a design-build basis by the contractor and included in the base bid; retaining walls shall be segmental retaining walls per specification H3.00; electrical site lighting is included in new Line Item 97; all City of Forest Park permitting fees are waived; and the site is expected to be approximately balanced for earthwork within specified tolerances. The addendum also establishes that bidders must include a 10% contingency allowance within unit prices such that actual payment will be 90% of submitted values. A revised bid form is provided replacing the original Section III with updated line items, and a geotechnical investigation report dated May 6, 2022 prepared by Atlas Technical Consultants is incorporated as a contract document. The addendum requires all bidders to acknowledge receipt and comply with all modifications; failure to acknowledge may result in bid rejection. Sealed bids remain due by 2:00 p.m. on March 21, 2023 (revised from the original April 6, 2023 date noted in the opportunity), with substantially complete work required within 335 calendar days and final completion within 365 calendar days after contract execution.
The revised bid form includes 97 line items organized by work category, including demolition, site preparation, concrete and asphalt paving, rubberized and synthetic surfaces, fencing, drainage systems, utility piping, landscaping, six building components, and allowances for playground equipment and skate park. Bidders must be licensed Georgia General Contractors and provide bid security equal to 5% of the base bid, along with required forms including LSBD documentation, insurance certificates, financial capability statements, debarment certifications, and qualification statements addressing organizational structure, project experience, management plans, quality control, procurement, and safety records. The geotechnical report identifies shallow groundwater as near as three feet below surface, extensive previously placed fill and alluvial soils requiring undercutting and stabilization, and recommends a design bearing capacity of 1,500 psf for foundations. The report notes that on-site residual soils and previously placed fill are suitable for reuse as structural fill if dried to proper moisture content, though fill encountered in specific boring locations mixed with topsoil is unsuitable for reuse.
Text of this file
CITY OF FOREST PARK, GEORGIA
STARR PARK - PHASE I
PROJECT NO.: 02072023
ADDENDUM NO. 1
MARCH 16, 2023
ALL BIDDERS FOR THE REFERENCED PROJECT ARE REQUIRED TO MAKE THE CHANGES BELOW TO THE
EXISTING CONTRACT DOCUMENTS OBTAINED FROM THE CITY OF FOREST PARK’S WEBSITE FOR BIDDING
PURPOSES:
ITEM NO. 1: RESPONSE TO WRITTEN QUESTIONS RECEIVED PRIOR TO THE FEBRUARY 28, 2023 AT 12:00
PM NOON DEADLINE ESTABLISHED IN THE CONTRACT DOCUMENTS:
• QUESTION:
o What is the estimated cost or budget?
• RESPONSE:
o Project budgets and estimates are proprietary.
• QUESTION:
o Can I get a copy of any addendum released to date?
o All project and bid related documents are posted on the City’s website.
o Is irrigation required for this project? If so, where are the irrigation plans? Or is this a design-build irrigation proposal?
• RESPONSE:
o Per L1.00, irrigation is required for this project. Irrigation design shall be design/build by the contractor and included in base bid.
o When is the estimated installation date?
• RESPONSE:
o Construction is expected to begin within 30 days after the contacts have been completely executed.
o Is there a General Contractors license requirement?
o Yes, per the Contract Documents.
o Can you provide a CAD file?
o CAD files will be provided only to the successful bidder that is awarded the contract.
o Is this a classified or unclassified bid? There is no units for unsuitable.
• RESPONSE:
o This is an unclassified bid. However, bidding contractors may reference Geotechnical
Investigation report prepared by Atlas Technical Consultants, dated May 6, 2022.
o Can this site be balanced to avoid export/import of dirt?
• RESPONSE:
o Earthwork calculations and takeoffs are ultimately the responsibility of the contractor.
Costs for any necessary haul-in or haul-off shall be included in base bid. However, based on preliminary earthwork studies by design team, the site is expected to be approximately balanced, within specified tolerances.
o Explain how the allowances are handled. What is the allowance for playground equipment?
What is the allowance for skate park? Is the 10% contingency allowance supposed to be somewhere in base bid?
• RESPONSE:
o Contractor shall include allowances in bid, as specified on C0.0 and H1.00. Awarded contractor will then coordinate exact design, product, and installation with design team and owner. Contractor shall include the 10% contingency allowance into the unit price for each line item of the bid. Therefore, the actual price that will be paid for each line item is 90% of the value submitted.
o Explain how unit prices work. Is each unit price supposed to have everything priced into that item since there is no grading complete, erosion, or wall line items? Example: are we supposed to include all the grading, clearing, surveying, erosion, ect. for each line item?
The bid schedule is very confusing and the way it is right now there is now way we or subcontractors would ever break out numbers like this?
• RESPONSE:
o Unit pricing is broken into structures and defined project components. This is to simplify if items need to be removed from and/or added to the project. Site grading is a site wide issue but specific excavation that is required for various structures is associated with that specific line item.
o Clarify what the walls are? There is a detail of on pg, C7.1 for cast in place wall but elevation pages show segmental retaining walls. Also bid schedule shows a concrete wall but no segmented retaining walls.
• RESPONSE:
o Refer to H3.00. Walls shall be segmental retaining walls per H3.00 and specification.
Disregard detail on C7.1.
o In which Bid Line Item does the Electrical Site Lighting found on Sheets ES – 101; ES – 401; ES – 402 and ES -403 to be included?
o New Bid Form is provided under “Item No. 2” of this Addendum – See Line Item 97.
o What is the cost of the permits?
o All fees associated with City of Forest Park permitting are being waived by the City.
o Will the retaining wall require a permit? And if so at what cost?
o All fees associated with City of Forest Park permitting are being waived by the City.
o Will the Irrigation system to be designed by the Landscape Contractor? If so, then do you have a minimal Zone requirement.
o Refer to note on L1.00. Exact zone requirements will be coordinated with owner.
o Will Park Avenue be completely closed during construction; seeing we have work to complete on both sides of the street?
• RESPONSE:
o At this time there is no plan to close Park Avenue. After the award of this contact the successful bidder may provide a written request to the City for this closure. Requests for road closures will be complete with a traffic control and detour plan.
o Does the Limits of construction determine the linear footage of Construction Fencing required?
o Contractor’s responsibility to determine construction fencing quantities.
o Is there a certified land fill usage required by the city of Forest Park?
o No.
o Are any items listed for removal going to be removed by the city of Forest Park (reference sheets C2.0 & C2.1)?
• RESPONSE:
o At this time, contractor shall assume all work identified on C2.0 an C2.1 is to be performed by contractor.
o Can the limits of demolition be better defined as it relates to the existing pool and its components to remain?
• RESPONSE:
o Refer to C2.0 for description of intent regarding site work. Mechanical equipment located in existing ‘pump house’ (and all associated appurtenances) shall also be saved and protected.
o Was the existing pool in operation during the summer of 2022?
o Yes.
o Is there a detail at the edge of slab for the new splash pad?
o Splash pad slab shall be per SW2.0, with finished as specified on H1.01.
o What is the quantity of kids that the splash pad is designed for?
o Splash pad was not designed to a specific occupancy count.
o Sheet C3.0 references some Pool Drawings for Splash Pad details, could not locate.
o Refer to SW0.0-SW4.2 o What product and color are we using for the integral-colored concrete as shown on sheet
H1.01?
o Refer to updated H2.00.
o Who is providing the laser cut steel city logo as shown on sheet A-201? If the General Contractor is to provide, is there a source that the city wants to use?
• RESPONSE:
o The logo is to be provided by the GC. GC responsible for the all-other requirements for this item.
o What is the anticipated Notice to Proceed date?
• RESPONSE:
o Construction is expected to begin within 30 days after the contacts have been completely executed.
o What Bid Line Items do Specifications 27 0000, 28 0000 and other Low Voltage Systems as well support item bid under?
o New Bid Form is provided under “Item No. 2” of this Addendum – See Line Item 97.
ITEM NO. 2: BID FORM:
All Bidders are required to remove “SECTION III – BID FORM” from the Contract Documents and replace with
“SECTION III – REVISED: BID FORM” that is attached to this Addendum.
ITEM NO. 3: GEOTECHNICAL REPORT:
The geotechnical investigation for Starr Park dated May 6, 2022 is attached to this Addendum and is to be included into the Contract Documents for this project.
ITEM NO. 4: HARDSCAPE DETAILS:
All Bidders are required to remove “Sheet H2.00 – HARDSCAPE DETAILS” from the Contract Drawings and replace this sheet with Sheet “H2.00 – HARDSCAPE DETAILS” with revision date: 03/08/23 that is attached to this Addendum.
ITEM NO. 5: BIDDER FURNISHED INFORMATION:
All Bidders are requested to delete any reference to Georgia DOT Prequalification and/or Certification from the Contract Documents. Bidders are only required to provide a Georgia Contractor’s License number with the submission of the bid.
END OF ADDENDUM NO. 1
Where any original item, term or requirement is not specifically amended, voided or superseded by this addendum, it will remain in effect. This clarification is being provided to all known respondents.
This Addendum must be completed, signed, and attached to the RFP to acknowledge receipt of Addendum. FAILURE
TO ACKNOWLEDGE THIS ADDENDUM MAY RESULT IN REJECTION OF PROPOSAL.
Business Name ____________________________________________________________________________
Authorized Signature ____________________________________ Date _____________________________
Typed Name
& Title ___________________________________________________________________________
SECTION III
Page i
FOREST PARK
STARR PARK – PHASE I
REVISED: BID FORM
FOREST PARK
STARR PARK
PHASE - I
PROJECT NO.: 02072023
BID DATE: MARCH 21ST, 2023
BID TIME: 2:00 PM (EST)
Page ii
FOREST PARK
STARR PARK – PHASE I
TABLE OF CONTENTS
Page
Article 1 – Bid Recipient
Article 2 – Bidder’s Acknowledgements
Article 3 – Bidder’s Representations
Article 4 – Bidder’s Certification
Article 5 – BASIS OF BID
Article 6 – Time of Completion
Article 7 – Attachments to This Bid
Article 8 – Defined Terms
Article 9 – Bid Submittal
FOREST PARK
STARR PARK – PHASE I
ARTICLE 1 – BID RECIPIENT
1.01 This Bid is submitted to:
City of Forest Park, Georgia
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with the Owner in the form included in the Bidding Documents and to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS
2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 – BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
Addendum No. Addendum Date
ADDENDUM NO. 1 MARCH 16, 2023
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
E. Based on the information and observations referred to in Paragraph 3.01.D above, Bidder does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and
FOREST PARK
STARR PARK – PHASE I
within the times required, and in accordance with the other terms and conditions of the Bidding
Documents.
F. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
G. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by
Engineer is acceptable to Bidder.
H. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
ARTICLE 4 – BIDDER’S CERTIFICATION
4.01 Bidder certifies that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:
1. “Corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
ARTICLE 5 – BASIS OF BID
5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s). Any incomplete or illegible bid prices will make this bid subject to rejection by the Owner:
ITEM DESCRIPTION UNITS ESTIMATED UNIT TOTAL
NO. QUANTITY PRICE PRICE
BONDS, INSURANCE,
MOBILIZATION
LS 1 $____________ $_____________
TRAFFIC CONTROL
(COMPLETE PER
GDOT/MUTCD FOR PROJECT
DURATION)
LS 1 $____________ $_____________
DEMOLITION REMOVAL,
DISPOSAL AND STORAGE
(COMPLETE BUT NOT
LIMITED TO VEGETTION,
TREES, SAW CUTTING,
PAVEMENTS, CONCRETE,
STRUCTURES, SIGNAGE,
TRAFFIC SIGNALS AND ALL
RELATED APPURTENANCES)
LS 1 $____________ $_____________
GIS “AS-BUILT” SURVEY OF
COMPLETE PROJECT ON
“GEORGIA STATE PLANE
COORDINATES” FOR ALL
WORK PERFORMED
LS 1 $____________ $_____________
4” THICK 6’ WIDE CONCRETE
SIDEWALK COMPLETE;
CLASS “A” 3000 PSI AND ALL
REQUIRED APPURTENANCES
SF 48,000 $____________ $_____________
6” THICK CONCRETE PAVING
COMPLETE; CLASS “A” 4000
PSI; INCLUDING 6” GAB
COMPACTED BASE AND ALL
REQUIRED APPURTENANCES
SF 10,500 $____________ $_____________
ASPHALT PAVING; “HEAVY
DUTY”; COMPLETE FROM
SUBGRADE TO SURFACE
COURSE INCLUDING BUT
NOT LIMITED TO RECYCLED
APHALTIC CONCRETE 12.5
MM SUPERPAVE, TYPE 1, GP 1
OR 2, INCLUDING
BITUMINOUS MATERIL & “H”
LIME 2” MIN. THICKNESS;
TACK COAT; 2” RECYCLED
APHALTIC CONCRETE 19 MM
SUPERPAVE PRIME COAT 2”
MIN. THICKNESS, TYPE 1, GP
1 OR 2, INCLUDING
BITUMINOUS MATERIAL &
“H” LIME; 8” GAB, STANDARD
PROCTOR COMPACTED
SUBGRADE;
SY 500 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
ASPHALT PAVING; “LIGHT
DUTY”; COMPLETE FROM
SUBGRADE TO SURFACE
COURSE INCLUDING BUT
NOT LIMITED TO RECYCLED
APHALTIC CONCRETE 9.5 MM
SUPERPAVE, TYPE II
INCLUDING BITUMINOUS
MATERIL & “H” LIME, 1 ¼”
MIN. THICKNESS; TACK
COAT; 1 ¾” RECYCLED
APHALTIC CONCRETE 19 MM
SUPERPAVE PRIME COAT 2”
MIN. THICKNESS, TYPE 1, GP
1 OR 2, INCLUDING
BITUMINOUS MATERIAL &
“H” LIME; PRIME COAT, 6”
GAB, STANDARD PROCTOR
COMPACTED SUBGRADE;
SY 400 $____________ $_____________
RUBBERIZED TRACK
SURFACE; COMPLETE
INCLUDING BUT NOT
LIMITED TO POURED IN
PLACE RUBBERIZED TRAIL
SURFACE, STANDARD
PROCTOR GAB & STANDARD
PROCTOR COMPACTED
SUBGRADE AND ALL
REQUIRED APPURTENANCES
SF 13,500 $____________ $_____________
RUBBERIZED PLAYGROUND
SURFACE SYSTEM;
COMPLETE INCLUDING
POURED IN PLACE
RUBBERIZED SURFACE,
FALL-SAFE PADDING,
CONCRETE SLAB PER
MANUFACTURER SPECS.,
DRAINAGE & STANDARD
PROCTOR COMPACTED
SUBGRADE AND ALL
REQUIRED APPURTENANCES
SF 21,000 $____________ $_____________
PERMEABLE PAVER SYSTEM;
COMPLETE INCLUDING
PERMEABLE PAVERS,
BEDDING AND DRAINAGE;
AND ALL REQUIRED
APPURTENANCES
SF 9,000 $____________ $_____________
DOG PARK SURFACE
SYSTEM; COMPLETE
INCLUDING CLEAN
SHREDDED HARDWOOD
MULCH DYED BROWN,
SF 7,000 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
BEDDING AND DRAINAGE;
AND ALL REQUIRED
APPURTENANCES
ATHLETIC COURT SURFACE
SYSTEM; COMPLETE
INCLUDING SPECIFIED
SURFACES, EDGE
RESTRAINT, CONCRETE
PAVING AND STANDARD
PROCTOR COMPACTION;
AND ALL REQUIRED
APPURTENANCES
SF 11,500 $____________ $_____________
SAND VOLLEYBALL COURT
SYSTEM; COMPLETE
INCLUDING CLEAN BEACH
SAND, ANCHORED RUBBER
CURB, NON-WOVEN FILTER
FABRIC, DRAINAGE AND
COMPACTED SUBGRADE;
AND ALL REQUIRED
APPURTENANCES
SF 3,500 $____________ $_____________
RIVERROCK SWALE;
COMPLETE INCLUDING
SUBGRADE PREP, WRAPPED
57 STONE AND 8” MIN – 16”
MAX BROWN RIVER ROCK
SF 700 $____________ $_____________
SYNTHETIC TURF SYSTEM;
COMPLETE INCLUDING
STANDARD PROCTOR
COMPACTED SUBGRADE,
DRAINAGE, STONE BASE,
TOPPING STONE AND
SYNTHETIC TURF SYSTEM;
AND ALL REQUIRED
APPURTENANCES
SF 46,000 $____________ $_____________
3000 PSI CONCRETE CURB
AND GUTTER; COMPLETE
INCLUDING ROLLBACK
CURB, GDOT GAB ROAD
BASE; MIN. 8" THICK x 30"
WIDE UNDER CURB
INCLUDING STANDARD
PROVTOR COMPACTION AND
GRADING AND ALL
REQUIRED APPURTENANCES
LF 2,800 $____________ $_____________
3000 PSI CONCRETE HEADER
CURB (WITHOUT FENCING);
COMPLETE INCLUDING
EXPANSION MATERIAL
WHERE REQUIRED, REBAR
REINFORCEMENT AND
STANDARD PROCTOR
LF 4,300 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
COMPACTION AND ALL
REQUIRED APPURTENANCES
3000 PSI CONCRETE HEADER
CURB (WITH FENCING);
COMPLETE INCLUDING
EXPANSION MATERIAL
WHERE REQUIRED, REBAR
REINFORCEMENT, FENCING,
AND STANDARD PROCTOR
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 1,300 $____________ $_____________
CURB RAMP; GDOT ADA
RAMP “TYPE A” COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 3 $____________ $_____________
CURB RAMP; GDOT ADA
RAMP “TYPE B” COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 6 $____________ $_____________
CURB RAMP; GDOT ADA
RAMP “TYPE D” COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 2 $____________ $_____________
4’ TALL ORNAMENTAL
METAL FENCING; COMPLETE
INCLUDING 3000 PSI
CONCRETE FOOTINGS AND
ALL MANUFACTURER
REQUIRED APPURTENANCES
LF 1,200 $____________ $_____________
8’ TALL ORNAMENTAL
METAL FENCING; COMPLETE
INCLUDING 3000 PSI
CONCRETE FOOTINGS AND
ALL MANUFACTURER
REQUIRED APPURTENANCES
LF 500 $____________ $_____________
4’ TALL CHAIN LINK
FENCING; COMPLETE
INCLUDING 3000 PSI
CONCRETE FOOTINGS AND
ALL MANUFACTURER
REQUIRED APPURTENANCES
LF 800 $____________ $_____________
10’ TALL CHAIN LINK
FENCING; COMPLETE
INCLUDING 3000 PSI
CONCRETE FOOTINGS AND
ALL MANUFACTURER
REQUIRED APPURTENANCES
LF 600 $____________ $_____________
CMU SEAT WALL; COMPLETE
INCLUDING CAST STONE,
DRIP EDGE, 2000 PSI GROUT,
REBAR REINFORCEMENT,
COLOR MATCH MORTAR,
LF 140 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
3000 PSI CONCRETE FOOTING
AND STANDARD PROCTOR
SUBGRADE COMPACTION
AND ALL REQUIRED
APPURTENANCES
CONCRETE RETAINING
WALL; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
SF 4,900 $____________ $_____________
ADA RAMP; CONCRETE RAMP
WITH EDGE PROTECTION
INCLUDING ALL REQUIRED
APPURTENANCES
LF 40 $____________ $_____________
PEDESTRIAN WATER
FOUNTAIN; COMPLETE IN
ACCORDANCE WITH
MANUFACTURER SPECS
INLCUDING ALL REQUIRED
APPURTENANCES
EA 2 $____________ $_____________
DOG WATER FOUNTAIN;
COMPLETE IN ACCORDANCE
WITH MANUFACTURER
SPECS INCLUDING ALL
REQUIRED APPURTENANCES
EA 1 $____________ $_____________
PET WASTE STATION;
COMPLETE IN ACCORDANCE
WITH MANUFACTURER
SPECS INCLUDING ALL
REQUIRED APPURTENANCES
EA 2 $____________ $_____________
LITTER RECEPTACLE;
COMPLETE IN ACCORDANCE
WITH MANUFACTURER
SPECS INCLUDING ALL
REQUIRED APPURTENANCES
EA 17 $____________ $_____________
VOLLEYBALL COURT;
COMPLETE INCLUDING NET
SYSTEM, RUBBER CURB,
FULL DEPTH FABRIC WRAP,
CLEAN BEACH SAND,
ANCHORING, GAB LEVELING,
DRAINAGE AND STANDARD
PROCTOR COMPACTION AND
ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BASKETBALL COURT;
COMPLETE INSTALLED PER
MANUFACTURER SPECS
INCLUDING GOAL(S),
SURFACING, STRIPING, EDGE
RESTRAINT AND CONCRETE
PAVING AND ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
TENNIS COURT; COMPLETE
INSTALLED PER
MANUFACTURER SPECS
INCLUDING NET SYSTEM,
SURFACING, STRIPING, EDGE
RESTRAINT AND CONCRETE
PAVING AND ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
SHADE SAIL; INSTALLED
COMPLETE IN ACCORDANCE
WITH MAUFACTURER SPECS
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BENCH; INSALLED
COMPLETE IN ACCORDANCE
WITH MANUFACTURER
SPECS INCLUDING ALL
REQUIRED APPURTENANCES
EA 24 $____________ $_____________
RELOCATION OF FITNESS
EQUIPMENT
EA 10 $____________ $_____________
SPLASH PAD SYSTEM;
COMPLETE INCLUDING BUT
NOT LIMITED TO FEATURES,
PLUMBING, MECHANICAL,
GRADING, 6” THICK 3500 PSI
CONCREST SLAB, REBAR
REINFORCEMENT AND 3”
GRAVEL BASE AND ALL
REQUIRED APPURTENANCES
EA 1 $____________ $_____________
48" DIAMETER HDPE STORM
DRAIN; WATER TIGHT JOINT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 1,110 $____________ $_____________
48" DIAMETER RCP STORM
DRAIN; CLASS "V"; RUBBER
GASKET BELL & SPIGOT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 40 $____________ $_____________
36" DIAMETER HDPE STORM
DRAIN; WATER TIGHT JOINT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 40 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
36" DIAMETER RCP STORM
DRAIN; CLASS "V"; RUBBER
GASKET BELL & SPIGOT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 90 $____________ $_____________
30" DIAMETER HDPE STORM
DRAIN; WATER TIGHT JOINT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 480 $____________ $_____________
24" DIAMETER HDPE STORM
DRAIN; WATER TIGHT JOINT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 1,500 $____________ $_____________
18" DIAMETER HDPE STORM
DRAIN; WATER TIGHT JOINT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 1,370 $____________ $_____________
18" DIAMETER RCP STORM
DRAIN; CLASS "V"; RUBBER
GASKET BELL & SPIGOT;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
HAUNCHING, BACKFILL AND
COMPACTION AND ALL
REQUIRED APPURTENANCES
LF 120 $____________ $_____________
12” ROOF DRAIN PIPING
INCLUDING ALL REQUIRED
APPURTENANCES
LF 40 $____________ $_____________
10” ROOF DRAIN PIPING
INCLUDING ALL REQUIRED
APPURTENANCES
LF 560 $____________ $_____________
8” ROOF DRAIN PIPING
INCLUDING ALL REQUIRED
APPURTENANCES
LF 970 $____________ $_____________
6” ROOF DRAIN PIPING
INCLUDING ALL REQUIRED
APPURTENANCES
LF 490 $____________ $_____________
4” ROOF DRAIN PIPING
INCLUDING ALL REQUIRED
APPURTENANCES
LF 230 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
UNDERGROUND
STORMWATER DETENTION
SYSTEM “A”; COMPLETE
INCLUDING BUT NOT
LIMITED TO SUITABLE
FOUNDATION, BEDDING,
HAUNCHING, PIPING,
BACKFILL AND GRADING
AND ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
UNDERGROUND
STORMWATER DETENTION
SYSTEM “B”; COMPLETE BUT
NOT LIMITED TO SUITABLE
FOUNDATION, BEDDING,
HAUNCHING, PIPING,
BACKFILL AND GRADING
AND ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
SUBMERGED GRAVEL
WETLAND SYSTEM;
COMPLETE INCLUDING ALL
REQUIRED APPURTENANCES
EA 1 $____________ $_____________
BIO RETENTION AREA “#1”;
COMPLETE
EA 1 $____________ $_____________
TRENCH DRAIN; COMPLETE
INCLUDING GRATE & COVER,
4000 PSI CONCRETE SLAB &
BASE AND ALL REQUIRED
APPURTENANCES
LF 370 $____________ $_____________
GDOT 1019 PRECAST
CONCRETE CURB INLET
CATCH BASIN W/ CAST IRON
HOOD AND GRATE;
COMPLETE IN ACCORDANCE
WITH GDOT DETAIL 1019B
INCLUDING BUT NOT
LIMITED TO TRAFFIC RATED
FRAME AND GRATE,
BEDDING, SEALING PIPE
PENETRATION, AND
BACKFILL AND ALL
REQUIRED APPURTENANCES
EA 8 $____________ $_____________
GDOT 1019 PRECAST
CONCRETE DROP INLET
CATCH BASIN W/ CAST IRON
HOOD AND GRATE;
COMPLETE IN ACCORDANCE
WITH GDOT DETAIL 1019B
INCLUDING BUT NOT
LIMITED TO TRAFFIC RATED
FRAME AND GRATE,
EA 15 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
BEDDING, SEALING PIPE
PENETRATION, AND
BACKFILL AND ALL
REQUIRED APPURTENANCES
GDOT 1034 PRECAST DOUBLE
WING CATCH BASIN;
COMPLETE IN ACCORDANCE
WITH GDOT DETAIL 1034D
INCLUDING BUT NOT
LIMITED TO TRAFFIC RATED
FRAME AND COVER,
BEDDING, SEALING PIPE AND
ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
GDOT 1019 PRECAST
CONCRETE WIER INLET
CATCH BASIN W/ CAST IRON
HOOD AND GRATE;
COMPLETE IN ACCORDANCE
WITH GDOT DETAIL 1019A
INCLUDING BUT NOT
LIMITED TO BEDDING,
SEALING PIPE PENETRATION,
AND BACKFILL AND ALL
REQUIRED APPURTENANCES
EA 4 $____________ $_____________
CONCRETE JUNCTION BOX W/
CAST IRON TRAFFIC RATED
FRAME AND COVER;
COMPLETE IN ACCORDANCE
WITH GDOT DETAIL 9031U
INCLUDING BUT NOT
LIMITED TO TRAFFIC RATED
FRAME AND COVER,
BEDDING, SEALING PIPE
PENETRATION, AND
BACKFILL AND ALL
REQUIRED APPURTENANCES
EA 15 $____________ $_____________
AREA DRAIN PEDISTAL
INLET COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 32 $____________ $_____________
65 ROOF DRAIN CO EA 30 $____________ $_____________
6" DIAMETER DUCTILE IRON
PIPE FOR SANITARY SEWER;
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
COMPACTION AND TESTING
AND ALL REQUIRED
APPURTENANCES
LF 230 $____________ $_____________
8" DIAMETER DUCTILE IRON
PIPE FOR SANIARY SEWER;
LF 150 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
COMPLETE INCLUDING BUT
NOT LIMITED TO BEDDING,
COMPACTION, TESTING AND
ALL REQUIRED
APPURTENANCES
8” PVC DRAINAGE LINES;
COMPLETE INCLUDING
BEDDING AND BACKFILL
AND ALL REQUIRED
APPURTENANCES
LF 90 $____________ $_____________
69 SANITARY SEWER MANHOLE EA 3 $____________ $_____________
SANITARY SEWER
CLEANOUT
EA 4 $____________ $_____________
2.5” COPPER PIPE; COMPLETE
INCLUDING ALL REQUIRED
FITTINGS, BENDS AND
BLOCKING AND ALL
REQUIRED APPURTENANCES
LF 20 $____________ $_____________
2” COPPER PIPE; COMPLETE
INCLUDING ALL REQUIRED
FITTINGS, BENDS AND
BLOCKING AND ALL
REQUIRED APPURTENANCES
LF 440 $____________ $_____________
1.5” COPPER PIPE; COMPLETE
INCLUDING ALL REQUIRED
FITTINGS, BENDS AND
BLOCKING AND ALL
REQUIRED APPURTENANCES
LF 20 $____________ $_____________
1” COPPER PIPE; COMPLETE
INCLUDING ALL REQUIRED
FITTINGS, BENDS AND
BLOCKING AND ALL
REQUIRED APPURTENANCES
LF 100 $____________ $_____________
0.75” COPPER PIPE;
COMPLETE INCLUDING ALL
REQUIRED FITTINGS, BENDS
AND BLOCKING AND ALL
REQUIRED APPURTENANCES
LF 100 $____________ $_____________
NEW 2” WATER SERVICE
METER; COMPLETE
INCLUDING CONNECTION TO
EXISTING WATER MAIN
EA 1 $____________ $_____________
UPSIZE EXISTING 1.5” WATER
SERVICE METER
EA 1 $____________ $_____________
REUSE EXISTING 5/8” WATER
SERVICE METER
EA 1 $____________ $_____________
REUSE EXISTING 1” WATER
SERVICE METER
EA 1 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
80 EARTHWORK; COMPLETE CY 16,500 $____________ $_____________
4” CALIPER TREE (SPECIFIED
SPECIES VARY, SEE
SCHEDULE ON TP3.0)
EA 44 $____________ $_____________
3” CALIPER TREE (SPECIFIED
SPECIES VARY, SEE
SCHEDULE ON TP3.0)
EA 74 $____________ $_____________
4” POT GROUNDCOVER
(SPECIFIED SPECIES VARY,
SEE SCHEDULE ON L2.0)
EA 2,419 $____________ $_____________
1 GALLON
SHRUB/GOURNDCOVER
(SPECIFIED SPECIES VARY,
SEE SCHEDULE ON L2.0)
EA 706 $____________ $_____________
2 GALLON
SHRUB/GROUNDCOVER
(SPECIFIED SPECIES VARY,
SEE SCHEDULE ON L2.0)
EA 285 $____________ $_____________
3 GALLON
SHRUB/GROUNDCOVER
(SPECIFIED SPECIES VARY,
SEE SCHEDULE ON L2.0)
EA 3,134 $____________ $_____________
PERMANENT GRASSING;
SOD; COMPLETE
SF 236,000 $____________ $_____________
88 MULCHING SF 61,000 $____________ $_____________
BUILDING “A”; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BUILDING “B”; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BUILDING “C”; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BUILDING “D”; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BUILDING “E”; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
BUILDING “F”; COMPLETE
INCLUDING ALL REQUIRED
APPURTENANCES
EA 1 $____________ $_____________
PLAYGROUND EQUIPMENT
ALLOWANCE
LS 1 $____________ $_____________
96 SKATE PARK ALLOWANCE LS 1 $____________ $_____________
FOREST PARK
STARR PARK – PHASE I
SITE ELECTRICAL
COMPLETE: INCLUDING BUT
NOT LIMITED TO ALL SITE
WIDE LIGHTING, POWER,
LOW VOLTAGE, ETC. THAT IS
NOT SPECIFICALLY
INCLUDED IN LINE ITEMS
FOR STRUCTURES AND
APPURTENANCES INCLUDED
IN THIS PROJECT
LS 1 $____________ $_____________
Total Base Bid in Words:
_____________________________________________________________________________Dollars
In Numbers: $_____________________________________
Unit Prices have been computed in accordance with Paragraph 11.03.B of the General Conditions.
Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents.
Bidder acknowledges that total base bid includes a contingency allowance equal to 10% of the total sum of all line items within the above “Article 5: Basis of Bid” as provided in the Contract
Documents.
ARTICLE 6 – TIME OF COMPLETION
6.01 Bidder agrees that the Work will be substantially complete within 335 calendar days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions, and will be completed and ready for final payment in accordance with Paragraph 14.07 of the General
Conditions within 365 calendar days after the date when the Contract Times commence to run.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 7 – ATTACHMENTS TO THIS BID
7.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid Security (5%);
B. LSBD Forms 1-4 ;
FOREST PARK
STARR PARK – PHASE I
C. List of 5 Project References (Section XVII – Reference and Release Form);
D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such license within the time for acceptance of Bids;
E. Copy of Contractor’s License [or] Evidence of Bidder’s ability to obtain a State
Contractor’s License and a covenant by Bidder to obtain the following said license within the time for acceptance of Bids.
1. Georgia General Contractor’s License Number
F. Certificate of Insurance (City of Forest Park as the Certificate Holder);
G. Contractor Affidavit and Agreement (Form 6a);
H. Subcontractor Affidavit (if available) (Form 6b);
I. Contractor’s Statement of Legal Status and Financial Capability (Form7);
J. Certification Regarding Debarment, Suspension, and Other Matters (Form 8);
K. Non-Collusion Affidavit (Form 9);
L. Bidder’s Contact Directory (Form 10);
M. Acknowledgment of Addenda (Form 11);
N. Required Bidder Qualification Statement with Supporting Data for the following:
1. Organizational Structure/Key Personnel and Resumes:
2. Overall Project Experience, Qualifications, and Performance on Previous Similar
Projects
3. Management and Staffing Plan
4. Quality Control Plan Approach
5. Procurement Plan
6. Safety Record and Experience
7.02 The following documents are to be submitted post-award:
A. LSBD Participation Report – Contract Goal: Report detailing percentage of LSBD participation (work performed) and payments to VOB/MBE/WBE/DBE subcontractors on a monthly basis.
ARTICLE 8 – DEFINED TERMS
8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to
Bidders, the General Conditions, and the Supplementary Conditions.
FOREST PARK
STARR PARK – PHASE I
ARTICLE 9 – BID SUBMITTAL
9.01 This Bid is submitted by:
If Bidder is:
An Individual
Name (typed or printed):
By:
(Individual’s signature)
Doing business as:
A Partnership
Partnership Name:
(Signature of general partner -- attach evidence of authority to sign)
A Corporation
Corporation Name: (SEAL)
State of Incorporation:
Type (General Business, Professional, Service, Limited Liability): _______
(Signature -- attach evidence of authority to sign)
Title:
(CORPORATE SEAL)
Attest
Date of Qualification to do business in ______________ is ____/____/____.
A Joint Venture
Name of Joint Venture:
First Joint Venturer Name: (SEAL)
(Signature of first joint venture partner -- attach evidence of authority to sign)
Second Joint Venturer Name: (SEAL)
(Signature of second joint venture partner -- attach evidence of authority to sign)
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)
Bidder's Business Address
Phone No. _____________________________________ Fax No.
E-mail ______________________________ _______
SUBMITTED on , 20____.
Georgia Contractor License No.: .
GEOTECHNICAL INVESTIGATION
Starr Park Phase 1 Forest Park, Georgia
Atlas Project No.: 122104
PREPARED FOR:
Falcon Design Consultants, LLC
235 Corporate Center Drive, Suite 200
Stockbridge, Georgia 30281
PREPARED BY:
Atlas Technical Consultants, LLC
3000 Northfield Place, Suite 1100
Roswell, Georgia 30076
May 6, 2022 ii
ATLAS Project No. 122104
May 6, 2022
Ms. Sarah Shirk
Falcon Design Consultants, LLC
235 Corporate Center Drive, Suite 200
Stockbridge, Georgia 30281
Subject: Report of Subsurface Exploration and
Geotechnical Engineering Evaluation
Starr Park Phase 1
5031 Park Avenue
Forest Park, Georgia
Dear Ms. Shirk:
Atlas Technical Consultants, LLC (Atlas) is pleased to provide this report of our subsurface exploration and geotechnical engineering evaluation for the referenced project. The field study and this report were accomplished in general accordance with Atlas Proposal No. 22-03300, dated March 7, 2022.
The following report will present a brief summary of our pertinent findings and recommendations followed by our understanding of the proposed construction, methods of exploration employed, site and subsurface conditions encountered, and conclusions and recommendations regarding the geotechnical aspects of the project. Should you have any question regarding items discussed in this report, please do not hesitate to contact the undersigned.
Sincerely, Atlas Technical Consultants, LLC
David Howell Frank Pike, P.E.
Staff Engineer Senior Registered Engineer iii
TABLE OF CONTENTS
SECTION PAGE NUMBER
1.0 SUMMARY
2.0 PROPOSED CONSTRUCTION
3.0 METHODS OF EXPLORATION
4.0 SITE DESCRIPTION, GEOLOGY AND SUBSURFACE CONDITIONS
4.1 Site Description
4.2 Geology
4.3 Subsurface Conditions
4.3.1 Pavement
4.3.2 Topsoil
4.3.3 Previously Placed Fill
4.3.4 Alluvium/Possible Alluvium
4.3.5 Residuum
4.3.6 Groundwater
4.3.7 Infiltration Test Results
5.0 CONCLUSIONS AND RECOMMENDATIONS
5.1 General
5.2 Site Preparation
5.3 Earthwork
5.4 Groundwater Control
5.5 Foundations
5.5.1 Shallow Foundations
5.5.2 Alternate Foundations/ Structural Slabs
5.6 Soil Supported Slabs
5.7 Temporary and Permanent Slopes
5.8 Lateral Earth Pressures
5.9 Seismic Criteria for Structural Engineer
6.0 QUALIFICATIONS OF RECOMMENDATIONS
APPENDIX
Soil Test Boring Procedures
Correlation with Standard Penetration Test Results
Figure 1: Site and Boring Location Plan
Soil Classification Chart
Soil Boring Records (20)
1.0 SUMMARY
The following is a brief summary of our pertinent findings and recommendations. The reader is referred to the remaining text of this report for elaboration on these items.
1. The property appears developable from a geotechnical standpoint but extensive undercutting of previously placed fill materials and water deposited alluvium is anticipated. Temporary dewatering during undercutting and stabilization of undercut subgrades with geotextile fabrics and crushed stone are anticipated. Some stabilization of existing subgrades is also anticipated for hardscape and any synthetic turf areas.
2. General subsurface conditions consist of previously placed relatively poor fill underlain in some areas by very soft water deposited alluvium followed by residual soils. No rock or partially weathered rock was encountered to the depths drilled.
Shallow groundwater will impact development. The shallow groundwater was measured as near as 3 feet below the surface as measured at the time of boring. Due to this being an active park, it was not possible to leave the borings open to obtain stabilized groundwater readings. Unstable surface soils were observed in the northeast portion of the site under the weight of the drilling equipment which may indicate groundwater near the surface.
3. We recommend previously place fill and alluvium be undercut from below foundations and slab areas.
The new structures may be supported on residual soil or new structural fill designed based on a soil bearing capacity of 1,500 psf. We anticipate that hardscape and landscape subgrade preparation will be routine in some areas, but other areas will require remedial undercutting and stabilization.
4. The on-site residual soils and most of the encountered previously placed fill soils are visually suitable for reuse as structural fill from a material standpoint but are wet of their optimum moisture and will require drying. The fill encountered in borings B-6, B-9, and B-13 appeared to be mixed with topsoil, so this fill material is not suitable for reuse as structural fill. This conditions may be more widespread than indicated since the fill was placed for playfields.
5. Excavations to the depths explored can be accomplished using conventional heavy earthmoving equipment.
2.0 PROPOSED CONSTRUCTION
We understand that you are planning the improvement of Starr Park in Forest, Park Georgia. Our understanding of the proposed construction is based on the provided “Grading Plan C4.0” , undated, by Croft and Associates, as well as a memo by Martin/Martin Consulting Engineers dated February 24, 2022 regarding the anticipated loads in the proposed structures. The planned improvements will include pavilions, a new pool house, amphitheater, restrooms, hardscapes, and associated stormwater control measures. Proposed finish floor elevations for new structures will be near the existing grade and minimal grade adjustment is anticipated to reach finished floor levels. We understand that all structures are anticipated to be 1-story with no below grade areas. The maximum column loads have been given as 28 kips and wall loads are expected to be approximately 1 kip per foot. The amphitheater will be metal frame and the other structures concrete block walls. No other details of the proposed construction were available at the time this report was prepared.
3.0 METHODS OF EXPLORATION
To evaluate the subsurface conditions, the property was explored by a combination of a visual site reconnaissance and drilling 20 soil test borings to depths ranging from 10 to 20 feet below the existing grade.
The borings were located in the field by measuring distances and estimating directions from identifiable site features. Therefore, their locations as shown on the Site and Boring Location Plan in the Appendix should be considered approximate.
The borings were advanced by twisting continuous hollow stem auger flights into the ground. At selected intervals, Standard Penetration Resistance Testing (SPT) was performed in general accordance with ASTM
Standard D-1586, and soil samples were collected for visual classification. Upon completion, the soil test borings were plugged and backfilled. The results of the penetration tests, when properly evaluated, provide an indication of the relative consistency of the soil being sampled, the potential for difficult excavation, and the soil's ability to support loads. A more detailed description of the drilling and sampling process is included in the Appendix of this report.
Soil samples recovered during the drilling process were returned to the office where they were classified in general accordance with the Unified Soil Classification System (USCS). Detailed descriptions of the materials encountered at each boring location, along with a graphical representation of the Standard Penetration Test results, are shown on the Soil Boring Records in the Appendix. Elevations on the Soil Boring Records were interpolated from the topographical contours on the plan provided to us and should be considered approximate.
4.0 SITE DESCRIPTION, GEOLOGY AND SUBSURFACE CONDITIONS
4.1 Site Description
The subject property is an existing park that includes a small stage, tennis courts, playgrounds, a walking track, pavilions, restrooms and other single-story structures, and various ball fields. The site generally slopes down to the southwest with approximately 15 feet of elevation change. Unstable surface soils were observed in the northeast soccer fields, pumping of the subgrade was observed under the weight of the drilling equipment.
The investigated site is immediately surrounded by single-family residences to the northwest and southeast, while it is bound by existing multi-level developments to the northeast and existing baseball fields to the southwest.
A review of selected historical aerial photographs and historical USGS topographic maps indicates the park was initially developed between 1955 and 1960 with modification through the years since. The 1960 aerial photograph indicates a pond in the northwest corner of the site. A creek exits the pond and flows to the south.
At the pond the drainage swale bends to the east and the old drainage swale continued “upstream” through this section of the park and under Ash Street.
4.2 Geology
The site is located in the Piedmont Physiographic Province of Georgia. The residual soils in the Piedmont are the result of the chemical and physical weathering of the underlying parent rock. The weathering profile usually results in fine grained clayey silts and silty clays near the surface, where weathering is more advanced.
With depth, sandy silts and silty sands are found, often containing mica. Below the residual soils, partially weathered rock is often found as a transition above relatively unweathered rock. In local practice, partially weathered rock is arbitrarily defined as residual soils with Standard Penetration Resistances in excess of 100 blows per foot (50 blows per 6 inches), and which can be penetrated by a power auger.
4.3 Subsurface Conditions
4.3.1 Pavement
Boring B-19 initially encountered about 2 inches of asphalt, which was underlain by 3 inches of base stone.
4.3.2 Topsoil
Most of the borings with the exception of borings B-11, B-18, and B-19 initially encountered 1 to 8 inches of topsoil and associated root zone.
4.3.3 Previously Placed Fill
Fill soils are those soils that have been placed or reworked in conjunction with past construction activities, grading or farming. Previously placed fill soils were encountered in all boring locations to depths ranging from
2 to 12 feet below the existing grade. The fill was classified as silty SAND (SM) with Standard Penetration Test
(SPT) results ranging from 1 to 13 blows per foot (bpf). Based on the SPT results, the soil represented by these samples would be considered poorly to variably compacted. Some of the previously placed fill encountered in borings B-6, B-9, and B-13 appeared to be mixed with topsoil. The fills were often underlain by very soft soils. It is unlikely that a high degree of compaction could be obtained for fills placed on this type of subgrade.
4.3.4 Alluvium/Possible Alluvium
Alluvium is soil that has been transported and deposited by moving water. It is typically encountered adjacent to water course and in the bottom of valleys like previously crossed the park site. Alluvium soil type can change drastically over short horizontal and vertical distances and can contain organics. It is difficult to distinguish between alluvium and fill that was placed from an alluvial soil borrow source. Apparent alluvium was encountered in borings B-3, B-5, B-6, B-8, B-9, B-11, B-12, and B-13 with initial contact occurring at depths ranging from 3 to 12 feet below the existing grade. The alluvium/possible alluvium was found to be wet during drilling. Standard Penetration Tests varied from 1 to 10 blows per foot but most of the alluvium was very soft.
4.3.5 Residuum
Residuum is soil formed by in-place weathering of the parent rock. In wet environments the residuum is often difficult to distinguish from alluvium. Soils classified as apparent residuum was encountered at all boring locations beneath the previously placed fill or alluvium/possible alluvium, where encountered. The residuum was classified as sandy SILTs (ML), silty SANDs (SM), and clayey SANDs (SC), and were of low consistency.
Standard Penetration Test results ranged from 1 to 20 blows per foot.
No rock or partially weathered rock was encountered to the depths drilled.
4.3.6 Groundwater
Groundwater was encountered in borings B-1 through B-3, B-5, B-6, B-8 through B-10 through B-14, B-16, B-
17, and B-20 at the time of drilling at depths ranging from 3 to 13 feet below the existing grade. Stabilized groundwater levels will be somewhat higher.
Groundwater fluctuations of 5 feet or more are common in this geology.
4.3.7 Infiltration Test Results
Infiltration testing was completed using an automated constant-head permeameter which measures the soil’s infiltration rate or saturated hydraulic conductivity (Ksat) at specified time intervals. Test locations and depths were selected by others. The testing began by performing hand auger borings by manually rotating a sharpened steel bucket auger into the ground at test locations P-1 through P-7 to depths of 2 feet below the existing grade. The test locations are shown on Figure 1 in the appendix. The proposed infiltration test could not be performed at location P-1 due to the presence of water 3 inches above the test elevation.
Infiltration testing was completed using an automated constant-head permeameter, which measures the soil’s infiltration rate or saturated hydraulic conductivity (Ksat) at specified time intervals. The depth of water in the borehole does not change during the measurement period and the change in weight of the water reservoir over the time interval is recorded. As a result, the rate of water supplied corresponds to the soil infiltration rate from the bottom and side surfaces of the borehole. Once a steady water consumption rate is reached, the resulting percolation rate can be determined. The infiltration rate is then calculated using the Reynolds and
Elrick solution. The resulting infiltration rates for the referenced test locations are presented in the table below.
The following table provides a tabular summary of the infiltration rate recorded at each test location.
Summary of Infiltration Test Results
Location
Depth (ft)
Test Elevation (Feet)
Infiltration Rate (in/hr)
P-1 2 977 n/a
P-2 2 968 0.1
P-3 2 971 0.2
P-4 2 977 0.2
P-5 2 968 1+
P-6 2 975 0.2
P-7 2 975 0.1
At the time of construction, we request the opportunity to evaluate soil conditions to verify that the conditions anticipated in design actually exist. Otherwise, we assume no responsibility for construction compliance with the design concepts, specifications or recommendations. The infiltration rate may be different at other locations and depths and is dependent on soil properties at the specific location. If variations become evident during construction, it will be necessary to reevaluate the recommendations of this letter after on-site observations of the conditions.
The conditions described in the preceding paragraphs, and those shown in the Appendix, have been based on interpolation of the results of the previously described data using generally accepted principles and practices of geotechnical engineering. However, conditions in this geology may vary intermediate of the tested locations, and even more so on previously developed property.
Although individual soil test borings are representative of the subsurface conditions at the precise boring locations on the day drilled, they are not necessarily indicative of the subsurface conditions at other locations or other times. The nature and extent of variation between the borings may not become evident until the course of construction. If such variations are then noted, it will be necessary to reevaluate the recommendations of this report after on-site observation of the conditions.
5.0 CONCLUSIONS AND RECOMMENDATIONS
The following conclusions and recommendations are based on the data gathered during this exploration, our understanding of the proposed construction, our experience with similar site and subsurface conditions and generally accepted principles and practices of geotechnical engineering. Should the proposed construction change significantly from that described in this report, we request that we be advised so that we may amend these recommendations accordingly. This report and the conclusions and recommendations provided herein are provided exclusively for the use of Falcon Design Consultants, LLC and are intended solely for design of the referenced project.
5.1 General
The fill encountered in the soil test borings was generally loose and appeared to be mixed with topsoil in some areas such as in borings B-6, B-9, and B-13. No documentation of the previous grading process was available for review. It appears the fill may have been placed in some areas on soft subgrade and in most cases apparently placed for the construction of playfields. It is not likely that fills were placed with the intent of structural support. There is the possibility that undetected areas of unsuitable soils were left in place or were placed during the grading, that pits have been dug and unsuitable soils or organics have been buried, or other unanticipated conditions may exist. This is a risk inherent in development on an undocumented, previously graded property. We recommend that any soils to remain in place be thoroughly evaluated by the engineer as detailed in Section 5.2 and 5.3 of this report.
The majority of the borings performed included a zone of very soft alluvial soils and shallow groundwater that will impact development.
This is the start of the file's text. The full file is on GovTribe.
Other files
| File | Type | Posted |
|---|---|---|
| Award Information | — | |
| Addendum No. 3 | — | |
| Addendum No. 2 | — | |
| Sign-In Sheet 2.14.2023 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .