This Addendum No. 1, issued by the Michigan Department of Technology, Management and Budget (DTMB), modifies the bidding documents for the Baraga Correctional Facility Underground Storage Tank (UST) Removal and Replacement project (File No. 472/23439.IND). The project involves removal of an existing underground storage tank system and installation of a new 500-gallon above-ground storage tank (AST) system with fuel dispensing capabilities at the Baraga Correctional Facility in Baraga County, Michigan. The pre-bid meeting occurred with an attendee sign-in sheet included, site photographs from May 2024 were provided, and responses to contractor questions were documented. The bid opening date is January 29, 2025, with drawing sheets G001 and C105 issued with this addendum. The project is subject to prevailing wage rate requirements effective through the contract award deadline of March 13, 2025.
Key specification modifications include changes to work hours (7:00 AM to 4:30 PM with coordination required for outside-hours work), contractor-provided portable sanitary facilities with mandatory daily locking, and clarified UST disposal and recycling procedures. Base Bid Item No. 12 was revised from a per-ton unit cost to a lump sum price. The fuel dispensing installation package specifications were amended to remove the pulser component and specify powder-coated, heavy-duty galvanized steel construction. The contract includes 15 base bid items covering site preparation, AST system installation, and UST removal, plus an owner provisionary allowance of $20,000. Prevailing wage rates for various classifications (operating engineers, laborers, carpenters, electricians, and other trades) are detailed with comprehensive overtime provisions and apprenticeship levels. Contractor questions addressed responsibility allocations, material testing requirements, and project scheduling, with the selected contractor expected to work collaboratively with the Pennsylvania Custodial Unit (PSC) and DTMB/Michigan Department of Corrections (MDOC) to establish a feasible contract schedule upon award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 10/22)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND
BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
1/23/2025
PROJECT NAME
Baraga Correctional Facility - UST Removal & Replacement
FILE NUMBER
472/23439.IND
PROFESSIONAL
U.P. Engineers and Architects Inc.
PROJECT DIRECTOR
Sadi Rayyan
BID OPENING DATE:
1/29/2025
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
GENERAL
1. See attached pre-bid meeting sign-in sheet.
2. See attached site photos taken in May 2024.
3. See attached list of contractor questions and answers.
4. Drawing sheets G001 and C105 to be issued with this addendum.
5. See attached Prevailing Wage Rates
BID SCHEDULE
1. Base Bid Item No. 12 Change Bid Quantity to Lump Sum
SPECIFICATIONS
1. Section 00700. 4.2
a. Replace “6:00 AM to 6:00 PM” with “7:00 AM to 4:30 PM”
b. Add – (a) Contractor must coordinate with Baraga Correctional Facility Maintenance staff to work outside the hours of 7:00 AM to 4:30 PM.
2. Section 01500, Part 3, Paragraph 3.5
Remove “Baraga Correctional Facility is to provide access to maintenance building toilet. No portable toilet is required to be provided by the contractor.” And replace with the following:
a. The Contractor must provide and maintain a sufficient number of portable temporary sanitary facilities for the use of all persons employed on the Work.
b. Sanitary facilities must be locked with an MDOC provided padlock upon completion of work each day.
c. The locations of the temporary sanitary facilities must be in suitable locations, properly screened from public observation, in accordance with State and Local ordinances, and approved by the Professional.
The location must also allow for access by maintenance personnel (i.e., the location cannot be within the fenced work zone if maintenance personnel do not have the proper training (HAZWOPER, etc.)).
d. The temporary sanitary facilities must comply with all Federal, State and Local code requirements.
e. The Contractor shall rigorously enforce the use of the approved sanitary facilities provided.
f. The Contractor must maintain the temporary toilets in a sanitary condition at all times and must remove them when the Work under this Contract is complete.
3. Section 02 65 00, Part 2, Paragraph 2.7 – UST Cleaning
a. Amend Paragraph F to state: “Deliver UST, removed access ports, and waste collection drums to disposal or recycling facility.”
b. Amend Paragraph G to state: Deliver UST, removed access ports, and waste collection drums to disposal or recycling facility.
c. Amend Paragraph G.2. to state: Obtain final report of materials disposition after disposal or recycling completion.
4. Section 23 13 23, Part 2 Paragraph 2.09 – Fuel Dispensing Installation Package
a. Remove 4.d. “Pulser.”
b. Amend 5.a. to state: “Powder coated, heavy duty, galvanized steel construction.”
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: Greg Putman, Project Manager DATE: 1/23/2025
APPROVED BY:
PROJECT DIRECTOR: Sadi Rayyan DATE: 1/23/2025
Bidding and Contract Document (R 02/24) Baraga CF UST Removal and Replacement File No. 472/23439.IND
The Bidder must figure its Base Bid on the specified, or Addendum-approved, materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.
Addenda: Bidder acknowledges receipt of Addenda: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated: ________
BID SCHEDULE
Base Bid Schedule - The Bidder will complete the Work and accept as full payment, for the Work items listed, the following Unit Prices and/or Item Bid Prices, as applicable:
Base Bid Item No.
Bid Quantity
Description Unit Price
Item Bid Price
SITE PREPARATION, PROJECT ADMINISTRATION, PROJECT CLOSEOUT
1 LS Pre-Construction Submittals $ LS $
2 LS GPR utility location and marking $ LS $
3 LS Project administration and permitting $ LS $
4 LS Project Closeout $ LS $
AST SYSTEM INSTALLATION
5 LS Mobilization, demobilization, and meetings
6 LS AST system including 500-gal Fireguard tank, dispensing system, leak/spill/overfill detection system, fuel level monitoring system, fuel piping and all other required installation materials
$ LS $
7 LS All required labor, and material involved with the sitework/preparation for and installation of AST system, including grading and concrete.
$ LS $
8 LS Testing of AST system, and training of owner’s facility personnel.
$ LS $
UST SYSTEM REMOVAL
9 LS Mobilization, demobilization, and meetings LS
10 LS Demolition and site preparation activities $ LS $
11 LS UST emptying, cleaning, removal and disposal of UST and all associated piping
$ LS $
12 LS Native/Non-Impacted Material
Excavation/Stockpiling/Processing/Backfill/Compaction
$ LS $
13 225 Tons Backfill and compaction – certified clean sand $ /Ton $
14 LS Site restoration $ LS $
15 100 Tons Excavation, characterization, and disposal of potentially contaminated soils as directed by PSC
$ /Ton $
ALLOWANCES
16 Owners Provisionary Allowance NA $ 20,000
TOTAL (This amount should equal the Base Bid amount on the Bid Summary Form) $
Base Bid (Sum of Item Bid Prices for all Base Bid Items):
__________________________________________________________________ Dollars $__________________________ (use words) (in figures)
Bidding and Contract Document (R 02/24) Baraga CF UST Removal and Replacement File No. 472/23439.IND
Schedule of Alternates - The Bidder will complete (or deduct from the Contract) the parts of the Work designated by the Alternates that follow and accept in full payment (or allow in full credit) for those parts of the Work the following Item Bid Prices:
Alternate Item No.
Bid Quantity
Description
Unit Price
Item Bid
The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.
Schedule of Unit Prices or Contingent Change Order Prices - The Bidder shall use this “Schedule” to quote unit prices identified in the bid documents or propose other contingent Change Order prices. The proposed Unit Prices or contingent Change Order prices set forth in this schedule, at the sole discretion of the Owner, may, or may not be incorporated into the Contract Documents. The Owner reserves the right to negotiate Unit Prices or contingent Change Order prices set forth herein prior to their possible incorporation into the Contract Documents.
Item No. Bid Quantity
Description
Unit
Item Bid
Baraga CF UST Removal & Replacement Site Photos taken on May 14, 2024
List of Contractor Questions and Answers
Contractor 1
1. Is there a separate pay items for any liquids and sludge in the UST?
Emptying and disposal of liquids and sludge is included in the lump sum price of Pay Item 11.
2. How many gallons should we assume will be left in the UST that we will need to pump, haul, and dispose?
Assume a maximum of 200 gallons.
3. Is there any HMA that is involved in this project?
HMA will only be involved in this project if the existing HMA is damaged and needs to be restored.
4. How many SF of HMA?
See above.
5. Who is responsible for the cost of providing compaction testing of the backfill materials?
Contractor
6. What is the earliest possible start date for this project?
March 1, 2025 – TBD based on spring road restrictions and MDOC approval.
7. Will a soil erosion permit from the DTMB be required to be obtained by the contractor?
An SESC Permit is not required for this project, but the design document specified SESC measures and all requirements in accordance with Rule 1709 promulgated under the authority of Part 91, 1994PA 451, must be adhered to. See Appendix III – Project Special Procedures
8. What is the cost of the soil erosion permit?
NA
9. Is there a specific bid bond required form?
No specific bid bond form is required.
10. What kinds of tests are required on the fill materials that will be imported to the site?
ASTM C136 - Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates – is required for imported fill material (Class II sand for tank excavation fill)
The contractor must submit the name of the imported fill materials suppliers. Aggregate supplier shall provide current test results of materials supplied verifying that supplied products meet product requirements.
Contractor 2
1. Who is responsible for staking and layout?
Contractor
2. Who is responsible for material / density testing?
Contractor
3. Who is responsible for testing and analytical fees for soil testing at the UST portion?
PSC/DTMB are responsible for UST removal soil testing and associated fees.
4. Who is responsible for land fill approval and tipping fees?
Contractor.
5. Do we assume that the dirt that will be excavated and hauled away for the AST portion of the work is clean soil?
Yes.
6. Is there a detail for the Washed Stone Barrier at the AST location?
No.
7. Will the UST be empty before we start the removal process?
The fuel in the UST will be drawn down as much as possible, but because there is typically a minimum clearance of 6 inches between a submersible pump intake and the bottom of the tank, some fuel will remain and must be disposed of.
8. Do you know if there will be any perched water in the UST removal hole? If so, do we leave the water in the hole or do we need to pump the water out?
Perched groundwater is not expected to be encountered – although depth of groundwater is unknown. In the case that groundwater is encountered, if there is no visual, olfactory, or PID evidence of a release, backfill can be placed in water, no pumping required.
Contractor 3
1. Can the water table elevation for the work area be provided?
Refer to above.
2. Can additional photos be provided of the site prior to any snow?
Yes, additional photos will be provided in the Addendum.
3. Base Bid Item No 12 on the Bid Schedule is shown as a per ton unit cost. In the Base Bid Pay Items part of the specification it is called out as a lump sum. Please confirm this should be a lump sum price.
Base Bid Item No 12 shall be a be a Lump Sum cost. Bid Schedule will be amended to reflect this.
4. Should we assume that there will be any usable fuel in the UST that should be transferred at the time of UST removal? If so, how much usable fuel should we assume to be in the UST at the time of removal? Also, how much fuel should we assume for disposal at the time of UST removal?
There should be no useable fuel at the time of removal, and no transfer of fuel required.
Assume a maximum of 200 gallons of fuel to be disposed of.
5. The specification for the new fuel tank installation requires a company with ten years’ experience and 20 tank installations in Michigan. Because of limited local companies in Michigan, would a Wisconsin (or other neighboring state) company be acceptable?
Yes, a manufacturer from any state meeting those qualifications is acceptable.
Contractor 4
1. The anticipated completion date is July 1, 2025 however the contractor has no control over the amount of time for the AST to be constructed and delivered nor the weather and spring road restrictions. Is there a penalty for the project extending past the anticipated end date that isn’t in the contractor’s control?
The selected contractor will work with the PSC and DTMB/MDOC to determine a feasible contract schedule upon contract award. Penalties are not expected with approved schedule.
2. Is the contractor responsible for submitting a Suspected Release or other required LARA documentation if impacts are identified?
No, the PCS is responsible for LARA documentation involving a suspected/confirmed release. Contractor is only responsible for submitting LARA intent of UST Removal/Closure 30 days prior to tank removal.
3. How long will the excavation need to remain open for confirmation sample results?
Excavation will be field screened using a PID and filled when clean boundaries are established. If contamination is absent, the excavation would likely only be open for one day. If contamination is present this timeframe may extend.
4. Section 01050 Field Engineering contains a note regarding HAZWOPER training for surveyors. Please confirm the HAZWOPER training and medical monitoring requirements apply to all workers who could encounter potential contamination associated with the existing UST.
Section 01300 Part 2.4, Paragraph c) 4) states that the contractor’s Health and Safety Plan must comply with 29 CFR 1910.120.
5. Section 01500, Part 3, paragraph 3.5 states that the Baraga Correctional Facility is to provide access to the maintenance building toilet. At the Pre-Bid Meeting it was stated that the contractor will need to provide a porta-john and use a lock provided by MDOC. Please confirm which is correct.
Spec will be amended to reflect what was stated at the pre-bid meeting. Porta-John and lock will be used.
6. Specifications Section 02 65 00, Part 2, paragraph 2.5 UST Liquid Contents Removal, part C indicates to pump the UST liquid contents to above ground storage tank. At the Pre-Bid Meeting, it was stated that all fuel in the UST should be removed and disposed, not-reused in the new AST. Please confirm which is correct. If the intent is to capture and reuse the UST contents for the new AST will filtering of the contents be required?
There should be no useable fuel at the time of removal, and no transfer of fuel required.
7. Approximately how much gasoline will be in the UST when the project starts?
Assume a maximum of 200 gallons of remaining fuel that must be disposed of.
8. What is the depth to groundwater at the project location?
Refer to above questions regarding groundwater.
9. Specifications Section 02 65 00, Part 2, paragraph 2.7 UST Cleaning, Paragraph F states to transport the UST to a LARA disposal facility. Can the UST be recycled instead of disposed?
Yes. Specifications will be amended to reflect this.
10. Specifications Section 31 05 13 states that re-used sub-soil and topsoil materials must be tested for contamination by the engineer before use. What is the anticipated turn-around time for the test results?
Turn-around time will depend on how long it takes to conduct in-situ PID screenings. It is not anticipated that this testing will cause delays, and a determination will likely be reached the same day excavation is finished.
11. Item #12 on the Bid Schedule table is listed as a per Ton unit price but in the Division 01 – General Requirements, Section 01025 Measurement and Payment, 1.6 Base Bid Pay Items, paragraph 12a Payment is listed as a Lump Sum Price. Can you please clarify?
Base Bid Item No 12 shall be a be a Lump Sum cost. Bid Schedule will be amended to reflect this.
12. In Section 23 12 16, Part 2, paragraph 2.1 FUEL DISPENSER, it mentions -C. Cabinet -2.
Material: Heavy duty galvanized steel, and -3. Finish: Powder Coat. In Section 23 13 23, Part 2, paragraph 2.09 FUEL DISPENING INSTALLATION PACKAGE, it mentions -5. Cabinet and
Frame -a. Powder coated, all stainless-steel construction. Please clarify the material of construction.
Material of construction shall be powder coated, galvanized steel. Specifications will be amended to reflect this.
13. In Section 23 13 23, Part 2, paragraph 2.09, -4. Dispenser Accessories: d. Pulser - This part would be used for a fuel management system. Please confirm whether or not a fuel management system is required.
A fuel management system is not required. Specifications will be amended to reflect this.
Contractor 5
1. Can bollard length be 72" instead of 74"? Then we can get 3 bollards out of one stick.
The contractor may submit the request for this change, post award. The PSC will not take issue with it.
2. Vac truck services needed. In the last set of plans there was one but not seeing it on these ones for piping and conduit removal.
Yes, hydrovac excavation is required in any location within six feet of underground utilities.
See plan set : C001-General Utility Notes #4 See Spec Document : 31 23 16 - Part 3.3.A
3. Orange snow fencing suƯicient for security fencing if holes and trenches are left open over night?
Yes.
19 20
BO
YE
RS
CR
MENGE CR.
SIXMILE CR.
NE
ST
ER
S
CR
BO
YL
ES
C
R.
HAZEL CR.
BL
AC
K
CR
M
EN
GE
C
R.
LE
VI
TU
RE
C R.
CLEAR CR. R
D.
7 8 9 10 11 12
141516
19 20 21 22 23 24
19 20
23 24
252627
31 3234 35 36
BENDRY
LAKE
KYRO RD.
H A
LO
N
EN
R
D
G R
IS
TM
IL
L
R D
KROLIK RD.
EL
SN
O R
R D
LINDBLOM RD.
PLAINS CUTOFF RD.
PL
A
IN
S
R D
BARAGA
LITTLE CARP RIVER
27 26
B A
R A
G A
T W
P.
GUY RD.
LINDEMANN RD.
T51N,R33W
SIX M
ILE CR.
H A
M A
R R
D
M O
YE
R
R D
WADAGA RD.
VA
R
LI
N
E R
D
MANSFELDT RD.
OBERG RD.
SCHWAIM RD.
B
EA
R
TO
W N
R D
OLD 41
C A
R
LS
O N
R D
MENGE CREEK RD.
L' A
N
SE
T W
P.
SHRINE RD.
FALLS RIVER
RED CR.
B
EN
R D
TANGEN RD.
GRISTMILL CR.
W C
R .R
BENDRY LAKE
SI
XM
IL
E
C R
EE
K
P O
N D
KELLY LAKE
BARAGA
BARAGA TWP.
L' A
N
SE
T W
P.
T51N,R33W
FILE NO.: 472/ 23439.IND
OWNER
ENGINEER
PR
OJ
EC
T N
O:
DR
AW
N
BY
CH
EC
KE
D:
AP
PR
OV
ED
1 2 3 4 5
1 2 3 4 5
D
C
B
A
D
C
B
A
© U.P. Engineers & Architects, Inc.
DE
SI
GN
ED
B Y:
w w w .u pe a.
co m
IS
SU
ED
F
O R
D
A
TE
B
A R
A G
A C
O R
R
EC
TI
O
N A
L
FA
C
IL
IT
Y
ST
A
TE
O
F M
IC
H
IG
A
N
D M
TB
AD
D
EN
D U
M N
O . 1
/2
2/
M
-0
G
AP
M
EJ
AS
J
G
AP
COVER
G001
B A
R A
G A
C O
R R
EC
TI
O N
A L
FA
C
IL
IT
Y
ST
A
TE
O
F M
IC
H
IG
A
N
D M
TB
B A
R A
G A
, M
IC
H G
A N
1/
/2
6:
P
M
P:
\M
-0
D
TM
B- M
D O
C -B
AR
AG
A C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y U
ST
R
EP
LA
C
EM
EN
T\
D W
G S\
M
-0
3_
BA
SE
.D
W G
TA
N
K R
EM
O
VA
L
A N
D R
EP
LA
C
EM
EN
T
TA
N
K R
EM
O
VA
L
A N
D R
EP
LA
C
EM
EN
T
PROJECT LOCATION
BARAGA COUNTY
SECTION 1 T50N, R34W
PROJECT LOCATION
BARAGA COUNTY
MICHIGAN DEPT. OF TECHNOLOGY, MANAGEMENT & BUDGET
BARAGA CORRECTIONAL FACILITY UNDERGROUND
BARAGA COUNTY, MICHIGAN
FILE NO.: 472/23439.IND
STORAGE TANK REMOVAL AND REPLACEMENT
BARAGA COUNTY ROAD VICINITY MAP
UTILITY COORDINATION:
SHEET INDEX
SHEET
NUMBER Sheet Title
G001 COVER
C001 GENERAL NOTES
C101 SITE MAP
C102 EXISTING-DEMO SITE PLAN AREA 1
C103 EXISTING-DEMO SITE PLAN AREA 2
C104 PROPOSED SITE PLAN AREA 1
C105 PROPOSED SITE PLAN AREA 2
C501 DETAILS
C502 DETAILS
E101 ELECTRICAL OVERVIEW
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE OF MICHIGAN
ADAM P. LACH, RA, DIRECTOR
STATE FACILITIES ADMINISTRATION
DESIGN AND CONSTRUCTION DIVISION
PERMITTING
AutoCAD SHX Text
L'ANSE BAY
AutoCAD SHX Text
SIXMILE CREEK POND
AutoCAD SHX Text
KELLY LAKE
AutoCAD SHX Text
MARK MATTILA (MDOC): 906-275-5125
AutoCAD SHX Text
COREY DALY (MDOC): 517-927-3326
AutoCAD SHX Text
SADI RAYYAN (DTMB): 517-719-2801
AutoCAD SHX Text
MICHIGAN DEPARTMENT OF CORRECTIONS
AutoCAD SHX Text
GRANDVIEW PLAZA
AutoCAD SHX Text
206 E. MICHIGAN AVE.
AutoCAD SHX Text
LANSING, MI 48909
AutoCAD SHX Text
U.P. ENGINEERS & ARCHITECTS
AutoCAD SHX Text
100 PORTAGE STREET
AutoCAD SHX Text
HOUGHTON, MI 49931
AutoCAD SHX Text
PROJECT CONTACT:
AutoCAD SHX Text
PROJECT CONTACTS:
AutoCAD SHX Text
GREG PUTMAN, PM (UPEA): 906-315-1323
AutoCAD SHX Text
JASON PASCOE (DTMB): 906-280-1046
AutoCAD SHX Text
NO SCALE
AutoCAD SHX Text
THE FOLLOWING UTILITIES ARE LOCATED IN OR NEAR THE RIGHT
AutoCAD SHX Text
34 EAST U. S. 41
AutoCAD SHX Text
SEMCO ENERGIES
AutoCAD SHX Text
NEGAUNEE, MICHIGAN 49866
AutoCAD SHX Text
VILLAGE OF BARAGA
AutoCAD SHX Text
100 HEMLOCK STREET
AutoCAD SHX Text
211 EAST B STREET
AutoCAD SHX Text
(906) 779-2744
AutoCAD SHX Text
CHARTER COMMUNICATIONS
AutoCAD SHX Text
115 EAST MCLEOD AVENUE
AutoCAD SHX Text
BARAGA, MICHIGAN 49908
AutoCAD SHX Text
AT&T
AutoCAD SHX Text
VILLAGE OF BARAGA
AutoCAD SHX Text
100 HEMLOCK ST.
AutoCAD SHX Text
IRONWOOD, MICHIGAN 49938
AutoCAD SHX Text
%%UGAS:
AutoCAD SHX Text
%%UWATER, SANITARY AND STORM SEWERS
AutoCAD SHX Text
%%UTELEPHONE:
AutoCAD SHX Text
%%UELECTRICITY:
AutoCAD SHX Text
%%UCATV:
AutoCAD SHX Text
(906) 475-6083
AutoCAD SHX Text
(906) 353-6237
AutoCAD SHX Text
CONTACT: MARSHA BERTOLDI
AutoCAD SHX Text
BARAGA, MICHIGAN 49908
AutoCAD SHX Text
(906) 553-7867
AutoCAD SHX Text
IRON MOUNTAIN, MICHIGAN 49801
AutoCAD SHX Text
CONTACT: JEFF JACKOVICH
AutoCAD SHX Text
CONTACT: GERARD LINDEMANN, DPW DIRECTOR
AutoCAD SHX Text
(906) 353-6237
AutoCAD SHX Text
CONTACT: JEFFERY GREGG
AutoCAD SHX Text
OF WAY OF THE PROPOSED PROJECT.
AutoCAD SHX Text
204 STATE STREET
AutoCAD SHX Text
(906) 353-6644
AutoCAD SHX Text
BARAGA TELEPHONE
AutoCAD SHX Text
CONTACT: JON FRENCH
AutoCAD SHX Text
BARAGA, MICHIGAN 49908
AutoCAD SHX Text
(906) 235-9623 (CELL)
AutoCAD SHX Text P
AutoCAD SHX Text L
AutoCAD SHX Text U
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text B
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text N
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text R
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text I
AutoCAD SHX Text Q
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text O
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text UTILITIES ONSITE ARE ALL PRIVATELY OWNED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO LOCATE AND MARK ALL UTILITIES IN AND AROUND THE CONSTRUCTION AREA USING GROUND PENETRATING RADAR (GPR) PRIOR TO BEGINNING ANY WORK. SEE C001 GENERAL UTILITY NOTES FOR FURTHER INFORMATION.
AutoCAD SHX Text CONTRACTOR IS RESPONSIBLE FOR SUBMITTING LARA BFS INTENT OF UST REMOVAL/CLOSURE, 30 DAYS PRIOR TO TANK REMOVAL. OWNER/ENGINEER ARE RESPONSIBLE FOR LARA BFS SITE ASSESSMENT AND CLOSURE. CONTRACTOR IS RESPONSIBLE FOR ALL OTHER NECESSARY PERMITS.
CONTROL POINT DATA
BENCHMARK DATA
LEGEND
PR
OJ
EC
T N
O:
DR
AW
N
BY
CH
EC
KE
D:
AP
PR
OV
ED
1 2 3 4 5
1 2 3 4 5
D
C
B
A
D
C
B
A
© U.P. Engineers & Architects, Inc.
DE
SI
GN
ED
B Y:
w w w .u pe a.
co m
IS
SU
ED
F
O R
D
A
TE
B
A R
A G
A C
O R
R
EC
TI
O
N A
L
FA
C
IL
IT
Y
ST
A
TE
O
F M
IC
H
IG
A
N
D M
TB
AD
D
EN
D U
M N
O . 1
1/
/2
M
-0
G
AP
M
EJ
AS
J
G
AP
PROPOSED
SITE PLAN
AREA 2
C105
B A
R A
G A
C O
R R
EC
TI
O N
A L
FA
C
IL
IT
Y
ST
A
TE
O
F M
IC
H
IG
A
N
D M
TB
B A
R A
G A
, M
IC
H G
A N
1/
/2
6:
P
M
P:
\M
-0
D
TM
B- M
D O
C -B
AR
AG
A C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y U
ST
R
EP
LA
C
EM
EN
T\
D W
G S\
M
-0
3_
BA
SE
.D
W G
TA
N
K R
EM
O
VA
L
A N
D R
EP
LA
C
EM
EN
T
TA
N
K R
EM
O
VA
L
A N
D R
EP
LA
C
EM
EN
AutoCAD SHX Text
MH
AutoCAD SHX Text 1 inch = ft.
AutoCAD SHX Text
( IN FEET )
AutoCAD SHX Text
GRAPHIC SCALE
AutoCAD SHX Text
AutoCAD SHX Text 1/2
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
UTILITY POLE
AutoCAD SHX Text
TELEPHONE PEDESTAL
AutoCAD SHX Text
SANITARY MANHOLE
AutoCAD SHX Text
ELECTRICAL PEDESTAL
AutoCAD SHX Text
LIGHT POLE
AutoCAD SHX Text
WATER VALVE
AutoCAD SHX Text
TREE (DECIDUOUS)
AutoCAD SHX Text
TREE (CONIFER)
AutoCAD SHX Text
DOUBLE POLE SIGN
AutoCAD SHX Text
SINGLE POLE SIGN
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
GUY WIRE
AutoCAD SHX Text
CONTROL POINT
AutoCAD SHX Text T
AutoCAD SHX Text E
AutoCAD SHX Text
WV
AutoCAD SHX Text S
AutoCAD SHX Text
TEST PIT
AutoCAD SHX Text T
AutoCAD SHX Text
PROPERTY BOUNDARY
AutoCAD SHX Text
TREE LINE
AutoCAD SHX Text
EDGE OF GRAVEL
AutoCAD SHX Text
OVERHEAD TELEPHONE LINE
AutoCAD SHX Text
OVERHEAD ELECTRIC LINE
AutoCAD SHX Text
GAS LINE
AutoCAD SHX Text
WATER LINE
AutoCAD SHX Text
UNDERGROUND TELEPHONE LINE
AutoCAD SHX Text
UNDERGROUND ELECTRIC LINE
AutoCAD SHX Text
SANITARY SEWER
AutoCAD SHX Text
HYDRANT
AutoCAD SHX Text H
AutoCAD SHX Text Y
AutoCAD SHX Text D
AutoCAD SHX Text
FOUND SURVEY MONUMENT
AutoCAD SHX Text
SOIL BORING
AutoCAD SHX Text
STORM MANHOLE
AutoCAD SHX Text D
AutoCAD SHX Text
EX. BITUMINOUS
AutoCAD SHX Text
PROPERTY SETBACK LINE
AutoCAD SHX Text
MISC. PLAT LINES
AutoCAD SHX Text
ROCK OUTCROPPING
AutoCAD SHX Text
RIGHT OF WAY LINES
AutoCAD SHX Text
EX. CONCRETE
AutoCAD SHX Text
WATER SHUTOFF
AutoCAD SHX Text W
AutoCAD SHX Text S
AutoCAD SHX Text O
AutoCAD SHX Text
MISC. BROKEN BIT
AutoCAD SHX Text
BIT. DEMO
AutoCAD SHX Text
TREE DEMO
AutoCAD SHX Text
CONCRETE DEMO
AutoCAD SHX Text
BOLLARD OR POST
AutoCAD SHX Text
SERVICE BUILDING
AutoCAD SHX Text
GAS DISPENSER PER TANK SUPPLIER
AutoCAD SHX Text
PROPOSED GALVANIZED STEEL BOLLARD WITH YELLOW PLASTIC COVER SEE A1/C501
AutoCAD SHX Text
DIESEL DISPENSER PER TANK SUPPLIER
AutoCAD SHX Text
FUEL LINES INSTALLED ABOVE GROUND PER TANK SUPPLIER
AutoCAD SHX Text
WASHED STONE BARRIER
AutoCAD SHX Text PROVIDE UGE CONDUITS BELOW GRADE, IN PVC-COATED RIGID STEEL CONDUIT. ROUTE IN EMT INSIDE BUILDING. PROVIDE SEPARATE CONDUITS FOR LOW VOLTAGE/TELCOM/CONTROL.
AutoCAD SHX Text
CONDUIT STUB
AutoCAD SHX Text PROPOSED 500 GALLON DOUBLE WALLED FIREGUARD GAS TANK. SEE C501 FOR TANK SUPPLIER DETAIL.
AutoCAD SHX Text
EXISTING 2000-GAL DIESEL TANK TO BE TIED INTO PROPOSED PUMP ISLAND
AutoCAD SHX Text
FUEL DISPENSER SUMP PER SUPPLIER, AS SPECIFIED.
AutoCAD SHX Text
SAWN CONTROL JOINT SPACED AT MIN OF EVERY 6' SEE B2/C501
AutoCAD SHX Text
EXPANSION JOINT SEE B4/C502
AutoCAD SHX Text
EXPANSION JOINT SEE B4/C502
AutoCAD SHX Text
PROVIDE SEAL-OFFS AND TRANSITION TO INTERIOR EMT CONDUIT TO PANEL
AutoCAD SHX Text
PROPOSED TANK SLAB AT 722.5' ELEVATION AND 0% GRADE. SEE C501 FOR SLAB DETAILS.
AutoCAD SHX Text
PROPOSED SLAB FOR FUEL DISPENSER AND FUEL LINES SEE B1/C502
AutoCAD SHX Text
PIPE BOLLARDS PLACED 1' FROM DISPENSER SUMP CORNERS.
AutoCAD SHX Text S51
AutoCAD SHX Text E8
AutoCAD SHX Text E6
AutoCAD SHX Text
SEED AND MULCH ALL AREAS AFFECTED BY CONSTRUCTION/GRADING
AutoCAD SHX Text
PROVIDE NEW FUEL EMERGENCY SHUTOFF SWITCH, ALL WIRING, CONDUITS, AND LABELS
AutoCAD SHX Text
FUEL SYSTEM CONTROL BOX
AutoCAD SHX Text
PROPOSED GALVANIZED STEEL BOLLARD WITH YELLOW PLASTIC COVER SEE A1/C501
AutoCAD SHX Text
MATCH GRADE OF EXISTING BIT.
AutoCAD SHX Text
PROPOSED SLAB SEE B1/C502
PROVIDE INSULATION FOR THE EXISTING, ABOVE GROUND, DIESEL LINE.
SUSAN CORBIN
DIRECTOR
STATE OF MICHIGAN
DEPARTMENT OF LABOR AND ECONOMIC OPPORTUNITY
WAGE AND HOUR DIVISION
Prevailing Wage Rates for State Funded Projects Official Rate Schedule
GRETCHEN WHITMER
GOVERNOR
ORS#: ORS-001507
Date Issued: 12/13/2024 Contract Award By Date: 03/13/2025 Contracting Agency: DTMB Design & Construction Division (CA-0007) Contracting Agency Representative: Don Klein (KleinD4@michigan.gov) Project Number: 472/23439.IND Project Name: Baraga Correctional Facility Project Description: UST Removal and Replacement
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 1 of 138
FOR ALL AWARDED CONTRACTS ONLY
• Every Contractor and Subcontractors shall keep Posted on the Construction Site, in a conspicuous place, a copy of all applicable prevailing wage rate schedules contained in a contract.
• The Prevailing rate schedule provides an hourly rate which includes wage and fringe benefit totals for designated classifications.
• Please refer to WHD-9917 & WHD 9918 for any additional information.
Official Rate Schedule
Baraga
Classification Name Category Last Updated
Boilermaker Boilermaker 05/10/2024 Classification Description: Boilermaker
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $72.47 $107.55 $142.63 Apprentice: 1st Period $53.53 $79.15 $104.75 Apprentice: 2nd Period $55.14 $81.56 $107.97 Apprentice: 3rd Period $56.73 $83.94 $111.15 Apprentice: 4th Period $58.31 $86.31 $114.31 Apprentice: 5th Period $59.85 $88.62 $117.39 Apprentice: 6th Period $63.03 $93.39 $123.75 Apprentice: 7th Period $66.17 $98.10 $130.03 Apprentice: 8th Period $69.32 $102.83 $136.33
Overtime Provisions Over 8-hour day/40-hour week
9th hour $90.82 10th hour $90.82 Beyond 10 hours $90.82
Saturday First 8 hours $90.82 9th hour $90.82 10th hour $90.82 Beyond 10 hours $90.82
Sunday/Holiday $109.17
Four 10-hour days allowed? - Yes Make Up Day Allowed? - No
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 2 of 138
Baraga
Classification Name Category Last Updated
Bricklayer/Mason/Plasterer/Terrazzo – BAC 2 - UP Bricklayer 12/12/2024
Classification Description: Regardless of new or different methods of installation, bricklayers, cement masons, marble masons, mosaic workers, plasterers, pointer-caulkers-cleaners, stone masons, terrazzo workers, tile layers, refractory specialists, plant masonry workers, and allied craftworkers. The operation of any robotic or mechanical device used to install and finish masonry products shall be included.
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $54.15 $68.40 $82.65 Apprentice: Apprentice Level 1 $41.79 $50.86 $59.93 Apprentice: Apprentice Level 2 $43.40 $53.28 $63.15 Apprentice: Apprentice Level 3 $45.01 $55.69 $66.37 Apprentice: Apprentice Level 4 $46.62 $58.11 $69.59 Apprentice: Apprentice Level 5 $48.23 $60.52 $72.81 Apprentice: Apprentice Level 6 $49.84 $62.94 $76.03 Apprentice: Apprentice Level 7 & 8 $51.45 $65.35 $79.25
Overtime Provisions Over 8-hour day/40-hour week
9th hour $68.40 10th hour $68.40 Beyond 10 hours $68.40
Saturday First 8 hours $68.40 9th hour $68.40 10th hour $68.40 Beyond 10 hours $68.40
Sunday/Holiday $82.65
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 3 of 138
Baraga
Classification Name Category Last Updated
Bricklayer-L2-UP Bricklayer 09/24/2024 Classification Description: Regardless of new or different methods of installation, bricklayers, cement masons, marble masons, mosaic workers, plasterers, pointer-caulkers-cleaners, stone masons, terrazzo workers, tile layers, refractory specialists, plant masonry workers, and allied craftworkers. The operation of any robotic or mechanical device used to install and finish masonry products shall be the work of Bricklayers
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $54.15 $68.40 $82.65 Apprentice: Bricklayer Apprentice Level 3 $45.01 $55.69 $66.37
Apprentice: Bricklayer Apprentice Level 6 $49.84 $62.94 $76.03
Apprentice: Bricklayer Apprentice Level 7 & 8 $51.45 $65.35 $79.25
Apprentice: Bricklayers Apprentice Level 1 $41.79 $50.86 $59.93
Apprentice: Bricklayers Apprentice Level 2 $43.40 $53.28 $63.15
Apprentice: Bricklayers Apprentice Level 4 $46.62 $58.11 $69.59
Apprentice: Bricklayers Apprentice Level 5 $48.23 $60.52 $72.81
Overtime Provisions Over 8-hour day/40-hour week
9th hour $68.40 10th hour $68.40 Beyond 10 hours $68.40
Saturday First 8 hours $68.40 9th hour $68.40 10th hour $68.40 Beyond 10 hours $68.40
Sunday/Holiday $82.65
Four 10-hour days allowed? - Yes
Base Rate Comment: Saturday shall be considered a make-up day for lost time Monday through Friday. If the makeup day is utilized, a full eight (8) hour work day must be scheduled for everyone that reports to work, with all hours in excess of forty (40) hours to be paid at the rate of time and one-half.
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 4 of 138
Baraga
Classification Name Category Last Updated
Carpenter-L1510 Carpenter 09/17/2024 Classification Description: Carpenter, Drywall Taper & Finisher, & Floor Layer
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $52.28 $68.29 $84.29 Apprentice: Apprentice 0-6 months $42.68 $53.89 $65.09 Apprentice: Apprentice 13-18 months $44.28 $56.29 $68.29 Apprentice: Apprentice 19-24 months $45.88 $58.69 $71.49 Apprentice: Apprentice 25-30 months $47.48 $61.09 $74.69 Apprentice: Apprentice 31-36 months $49.08 $63.49 $77.89 Apprentice: Apprentice 37-42 months $50.68 $65.89 $81.09 Apprentice: Apprentice 43-48 months $51.48 $67.09 $82.69 Apprentice: Apprentice 7-12 months $43.48 $55.09 $66.69
Overtime Provisions Over 8-hour day/40-hour week
9th hour $52.28 10th hour $52.28 Beyond 10 hours $68.28
Saturday First 8 hours $68.28 9th hour $68.28 10th hour $68.28 Beyond 10 hours $68.28
Sunday/Holiday $84.29
Four 10-hour days allowed? - Yes
Saturdays may be used as a makeup day on a voluntary basis, with a minimum of eight (8) hours scheduled.
Make Up Day Allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 5 of 138
Baraga
Classification Name Category Last Updated
Diver-L1510 Carpenter 09/18/2024 Classification Description: Carpenter - Diver
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $71.09 $94.98 $118.86 Apprentice: 1st 6 months $56.81 $73.53 $90.25 Apprentice: 2nd 6 months $58.00 $75.32 $92.63 Apprentice: 3rd 6 months $59.20 $77.12 $95.03 Apprentice: 4th 6 months $61.59 $80.70 $99.81 Apprentice: 5th 6 months $63.97 $84.27 $104.57 Apprentice: 6th 6 months $66.36 $87.86 $109.35 Apprentice: 7th 6 months $68.75 $91.44 $114.13 Apprentice: 8th 6 months $69.95 $93.24 $116.53
Overtime Provisions Over 8-hour day/40-hour week
9th hour $71.09 10th hour $71.09 Beyond 10 hours $94.97
Saturday First 8 hours $94.97 9th hour $94.97 10th hour $94.97 Beyond 10 hours $94.97
Sunday/Holiday $118.86
Four 10-hour days allowed? - Yes
Saturdays may be used as a makeup day on a voluntary basis, with a minimum of eight (8) hours scheduled.
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 6 of 138
Baraga
Classification Name Category Last Updated
Journeyman Resilient Floorlayer-L1510 Carpenter 09/18/2024 Classification Description: Journeyman Resilient Floorlayer
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $55.22 $72.52 $89.81 Apprentice: Apprentice 1st Year $44.99 $57.17 $69.35 Apprentice: Apprentice 2nd Year $46.70 $59.74 $72.77 Apprentice: Apprentice 3rd Year $50.11 $64.85 $79.59 Apprentice: Apprentice 4th Year $53.52 $69.97 $86.41
Overtime Provisions Over 8-hour day/40-hour week
9th hour $55.22 10th hour $55.22 Beyond 10 hours $72.52
Saturday First 8 hours $72.52 9th hour $72.52 10th hour $72.52 Beyond 10 hours $72.52
Sunday/Holiday $89.81
Four 10-hour days allowed? - No
Saturdays may be used as a makeup day on a voluntary basis, with a minimum of eight (8) hours scheduled.
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 7 of 138
Baraga
Classification Name Category Last Updated
Pile Driver-L1510 Carpenter 09/17/2024 Classification Description: Pile driver
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $52.48 $68.59 $84.69 Apprentice: 2nd 6 months $46.72 $58.40 $70.07 Apprentice: 3rd 6 months $47.53 $59.61 $71.69 Apprentice: 4th 6 months $49.14 $62.03 $74.91 Apprentice: 5th 6 months $50.75 $64.44 $78.13 Apprentice: 6th 6 months $52.36 $66.86 $81.35 Apprentice: 7th 6 months $53.97 $69.27 $84.57 Apprentice: 8th 6 months $54.77 $70.47 $86.17 Apprentice: Apprentice 1st 6 months $45.92 $57.20 $68.47
Overtime Provisions Over 8-hour day/40-hour week
9th hour $52.48 10th hour $52.48 Beyond 10 hours $68.58
Saturday First 8 hours $68.58 9th hour $68.58 10th hour $68.58 Beyond 10 hours $68.58
Sunday/Holiday $84.69
Four 10-hour days allowed? - Yes
Saturday
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 8 of 138
Baraga
Classification Name Category Last Updated
Communication Technician Communication Technician 05/13/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58
Overtime Provisions Over 8-hour day/40-hour week
9th hour $98.24 10th hour $98.24 Beyond 10 hours $98.24
Saturday First 8 hours $98.24 9th hour $98.24 10th hour $98.24 Beyond 10 hours $98.24
Sunday/Holiday $128.58
Four 10-hour days allowed? - Yes
ONLY due to inclement weather or customer requirements may Friday be used as a make up day if the normal scheduled work week was interrupted and time lost of five (5) hours or more was incurred by workmen covered under the terms of the 6-17-C/6-876-T agreement.
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 9 of 138
Baraga
Classification Name Category Last Updated
Drywall Finisher Drywall 05/10/2024 Classification Description: Drywall Finisher, Soundproofing, & Plural Component Applicator
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $42.87 $57.12 $71.36 Apprentice: 1st 1,000 hours $31.47 $40.02 $48.56 Apprentice: 2nd 1,000 hours $32.90 $42.16 $51.42 Apprentice: 3rd 1,000 hours $34.32 $44.29 $54.26 Apprentice: 4th 1,000 hours $35.75 $46.44 $57.12 Apprentice: 5th 1,000 hours $37.17 $48.56 $59.96 Apprentice: 6th 1,000 hours $38.60 $50.71 $62.82 Apprentice: 7th 1,000 hours $40.02 $52.84 $65.66 Apprentice: 8th 1,000 hours $41.45 $54.98 $68.52
Overtime Provisions Over 8-hour day/40-hour week
9th hour $57.12 10th hour $57.12 Beyond 10 hours $57.12
Saturday First 8 hours $57.12 9th hour $57.12 10th hour $57.12 Beyond 10 hours $57.12
Sunday/Holiday $71.36
Four 10-hour days allowed? - No
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 10 of 138
Baraga
Classification Name Category Last Updated
Electrician - 906 H - Z1 Electrician 05/10/2024 Classification Description: Journeyman - Inside wireman for work above $160,000
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $61.03 $79.26 $97.48 Apprentice: 1st period $30.57 $37.99 $45.40 Apprentice: 2nd period $32.43 $40.78 $49.12 Apprentice: 3rd period $36.13 $46.33 $56.52 Apprentice: 4th period $39.84 $51.89 $63.94 Apprentice: 5th period $45.56 $59.64 $73.72 Apprentice: 6th period $49.31 $65.26 $81.22
Overtime Provisions Over 8-hour day/40-hour week
9th hour $79.26 10th hour $79.26 Beyond 10 hours $79.26
Saturday First 8 hours $79.26 9th hour $79.26 10th hour $79.26 Beyond 10 hours $79.26
Sunday/Holiday $97.48
Four 10-hour days allowed? - Yes
4 consecutive tens allowed M-Th F makeup day for inclement weather and holidays
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 11 of 138
Baraga
Classification Name Category Last Updated
Electrician - 906 H - Z2 Electrician 05/10/2024 Classification Description: Inside wireman for work above $160,000
A 4 ten schedule may be worked if 4 consecutive days, M-Th
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $59.14 $77.43 $95.72 Apprentice: 1st period $30.38 $37.71 $45.02 Apprentice: 2nd period $32.20 $40.43 $48.66 Apprentice: 3rd period $35.87 $45.94 $56.00 Apprentice: 4th period $39.52 $51.42 $63.30 Apprentice: 5th period $43.18 $56.90 $70.62 Apprentice: 6th period $46.84 $62.39 $77.94
Overtime Provisions Over 8-hour day/40-hour week
9th hour $76.90 10th hour $76.90 Beyond 10 hours $76.90
Saturday First 8 hours $76.90 9th hour $76.90 10th hour $76.90 Beyond 10 hours $76.90
Sunday/Holiday $94.66
Four 10-hour days allowed? - Yes
Friday
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 12 of 138
Baraga
Classification Name Category Last Updated
Electrician - 906 L - Z1 Electrician 05/10/2024 Classification Description: Inside wireman for work below $160,000
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $57.57 $75.08 $92.59 Apprentice: 1st period $29.75 $36.76 $43.76 Apprentice: 2nd period $31.50 $39.38 $47.26 Apprentice: 3rd period $35.00 $44.63 $54.26 Apprentice: 4th period $38.50 $49.88 $61.26 Apprentice: 5th period $42.00 $55.13 $68.26 Apprentice: 6th period $45.51 $60.40 $75.28
Overtime Provisions Over 8-hour day/40-hour week
9th hour $74.57 10th hour $74.57 Beyond 10 hours $74.57
Saturday First 8 hours $74.57 9th hour $74.57 10th hour $74.57 Beyond 10 hours $74.57
Sunday/Holiday $91.57
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 13 of 138
Baraga
Classification Name Category Last Updated
Electrician - 906 L - Z2 Electrician 05/10/2024 Classification Description: Inside wireman for work below 160,000 A 4 ten schedule may be worked if 4 consecutive days, M-Th
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $57.08 $74.34 $91.60 Apprentice: 1st period $29.55 $36.46 $43.36 Apprentice: 2nd period $31.27 $39.04 $46.80 Apprentice: 3rd period $34.73 $44.23 $53.72 Apprentice: 4th period $38.18 $49.40 $60.62 Apprentice: 5th period $41.63 $54.58 $67.52 Apprentice: 6th period $45.08 $59.76 $74.42
Overtime Provisions Over 8-hour day/40-hour week
9th hour $73.84 10th hour $73.84 Beyond 10 hours $73.84
Saturday First 8 hours $73.84 9th hour $73.84 10th hour $73.84 Beyond 10 hours $73.84
Sunday/Holiday $90.60
Four 10-hour days allowed? - Yes
Friday
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 14 of 138
Baraga
Classification Name Category Last Updated
Elevator Constructor Mechanic Elevator Constructor 05/10/2024 Classification Description: Elevator Constructor Mechanic
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $96.72 $83.78 $152.57 Apprentice: 1st year $68.96 $46.08 $99.68 Apprentice: 2nd year $74.88 $54.45 $111.18 Apprentice: 3rd year $77.85 $58.65 $116.95 Apprentice: 4th year $84.65 $67.02 $129.33
Overtime Provisions Over 8-hour day/40-hour week
9th hour $152.57 10th hour $152.57 Beyond 10 hours $152.57
Saturday First 8 hours $152.57 9th hour $152.57 10th hour $152.57 Beyond 10 hours $152.57
Sunday/Holiday $152.57
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 15 of 138
Baraga
Classification Name Category Last Updated
Fiber Optic Splicer Fiber Optic Splicer 05/13/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58
Overtime Provisions Over 8-hour day/40-hour week
9th hour $98.24 10th hour $98.24 Beyond 10 hours $98.24
Saturday First 8 hours $98.24 9th hour $98.24 10th hour $98.24 Beyond 10 hours $98.24
Sunday/Holiday $128.58
Four 10-hour days allowed? - Yes
ONLY due to inclement weather or customer requirements may Friday be used as a make up day if the normal scheduled work week was interrupted and time lost of five (5) hours or more was incurred by workmen covered under the terms of the 6-17-C/6-876-T agreement.
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 16 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58
Overtime Provisions Over 8-hour day/40-hour week
9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Saturday First 8 hours $90.71 9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Sunday/Holiday $113.52
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 17 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58
Overtime Provisions Over 8-hour day/40-hour week
9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Saturday First 8 hours $90.71 9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Sunday/Holiday $113.52
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 18 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58
Overtime Provisions Over 8-hour day/40-hour week
9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Saturday First 8 hours $90.71 9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Sunday/Holiday $113.52
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 19 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58
Overtime Provisions Over 8-hour day/40-hour week
9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Saturday First 8 hours $90.71 9th hour $90.71 10th hour $90.71 Beyond 10 hours $90.71
Sunday/Holiday $113.52
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 20 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $75.47 $109.62 $143.74
Overtime Provisions Over 8-hour day/40-hour week
9th hour $109.61 10th hour $109.61 Beyond 10 hours $109.61
Saturday First 8 hours $109.61 9th hour $109.61 10th hour $109.61 Beyond 10 hours $109.61
Sunday/Holiday $143.74
Four 10-hour days allowed? - Yes
ONLY due to inclement weather or customer requirements may Friday be used as a make up day if the normal scheduled work week was interrupted and time lost of five (5) hours or more was incurred by workmen covered under the terms of the 6-17-C/6-876-T agreement.
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 21 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $75.47 $109.61 $143.74
Overtime Provisions Over 8-hour day/40-hour week
9th hour $101.14 10th hour $101.14 Beyond 10 hours $101.14
Saturday First 8 hours $101.14 9th hour $101.14 10th hour $101.14 Beyond 10 hours $101.14
Sunday/Holiday $126.80
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 22 of 138
Baraga
Classification Name Category Last Updated
Foreman Foreman 05/10/2024 Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $76.98 $111.87 $146.76
Overtime Provisions Over 8-hour day/40-hour week
9th hour $103.22 10th hour $103.22 Beyond 10 hours $103.22
Saturday First 8 hours $103.22 9th hour $103.22 10th hour $103.22 Beyond 10 hours $103.22
Sunday/Holiday $129.45
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 23 of 138
Baraga
Classification Name Category Last Updated
Glazier Glazier 05/10/2024 Classification Description: Glazier 4 tens allowed on consecutive days
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $49.84 $67.73 $85.62 Apprentice: 1st level $31.62 $40.40 $49.18 Apprentice: 2nd level $35.12 $45.66 $56.18 Apprentice: 3rd Level $40.38 $53.54 $66.70 Apprentice: 4th level $45.66 $61.46 $77.26
Overtime Provisions Over 8-hour day/40-hour week
9th hour $66.72 10th hour $66.72 Beyond 10 hours $66.72
Saturday First 8 hours $66.72 9th hour $66.72 10th hour $66.72 Beyond 10 hours $66.72
Sunday/Holiday $83.59
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 24 of 138
Baraga
Classification Name Category Last Updated
Ironworker - A Ironworker 05/10/2024 Classification Description: For work over $10 million: Structural, Ornamental, Machinery Rigger & Reinforcing Ironworker;
installation of sheet metal siding
A 4-10 work week allowed Monday thru Thursday. Friday may be used as a make-up day. Hours in excess of 40 must be paid tim
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $50.07 $69.76 $89.45 Apprentice: 0 - 1,000 hours $25.39 $37.75 $50.11 Apprentice: 1,001 - 2,000 hours $37.71 $51.22 $64.73 Apprentice: 2,001 - 3,000 hours $39.01 $53.17 $67.33 Apprentice: 3,001 - 4,000 hours $40.31 $55.12 $69.93 Apprentice: 4,001 - 5,000 hours $41.61 $57.07 $72.53 Apprentice: 5,001 - 6,000 hours $42.92 $59.04 $75.15 Apprentice: 6,001 - 7,000 hours $44.22 $60.98 $77.75
Overtime Provisions Over 8-hour day/40-hour week
9th hour $63.09 10th hour $63.09 Beyond 10 hours $76.10
Saturday First 8 hours $63.09 9th hour $76.10 10th hour $76.10 Beyond 10 hours $76.10
Sunday/Holiday $76.10
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 25 of 138
Baraga
Classification Name Category Last Updated
Ironworker - B Ironworker 05/10/2024 Classification Description: For work under $10 Million: Structural, Ornamental, Machinery Rigger & Reinforcing Ironworker; pre-engineered metal buildings
A 4-10 work week allowed Monday thru Thursday. Friday may be used as a make-up day. Hours in excess of 40 must be paid time a
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $46.73 $64.76 $82.79 Apprentice: 0-1,000 hours $25.39 $37.75 $50.11 Apprentice: 1,001 - 2,000 hours $37.71 $51.22 $64.73 Apprentice: 2,001 - 3,000 hours $39.01 $53.17 $67.33 Apprentice: 3,001 - 4,000 hours $40.31 $55.12 $69.93 Apprentice: 4,001 - 5,000 hours $41.61 $57.07 $72.53 Apprentice: 5,001 - 6,000 hours $42.92 $59.04 $75.15 Apprentice: 6,001 - 7,000 hours $44.22 $60.98 $77.75
Overtime Provisions Over 8-hour day/40-hour week
9th hour $58.09 10th hour $58.09 Beyond 10 hours $69.44
Saturday First 8 hours $58.09 9th hour $69.44 10th hour $69.44 Beyond 10 hours $69.44
Sunday/Holiday $69.44
Four 10-hour days allowed? - Yes
ORS#: ORS-001507 | CA#: CA-0007 | Date Issued: 12/13/2024 | Contract Award By Date: 03/13/2025 Page 26 of 138
Baraga
Classification Name Category Last Updated
Journeyman Signal Technician Journeyman Signal Technician 05/13/2024
Classification Description:
Wage Rates Straight Time
Time and a Half
Double Time
Total Hourly Wage $67.89 $98.24 $128.58 Apprentice: Apprentice 1st 6 months $43.61 $61.82 $80.02 Apprentice: Apprentice 2nd 6 months $46.65 $66.38 $86.10 Apprentice: Apprentice 3rd 6 months $49.68 $70.92 $92.16 Apprentice: Apprentice 4th 6 months $52.71 $75.47 $98.22 Apprentice: Apprentice 5th 6 months $55.75 $80.03 $104.30 Apprentice: Apprentice 6th 6months $61.82 $89.13 $116.44
Overtime Provisions Over 8-hour day/40-hour week
9th hour $98.24 10th hour $98.24 Beyond 10 hours $98.24
Saturday First 8 hours $98.24 9th hour $98.24 10th hour $98.24 Beyond 10 hours $98.24
Sunday/Holiday $128.58
Four 10-hour days allowed? - Yes
ONLY due to inclement weather…