Addendum No. 03 for ARFQ DNR25*07 is issued by the West Virginia Division of Natural Resources (DNR) for the Parks and Recreation Section, specifically concerning paint repairs for the Blennerhassett Mansion at Blennerhassett State Park in Parkersburg, WV. The addendum extends the bid opening date to April 1, 2025, at 1:30 PM ET and provides official responses to 15 technical questions from potential contractors. The project involves comprehensive painting services, including preparation, priming, and painting of the mansion's exterior, shutters, metal handrails, and window sills, with contractors having options for hardware replacement and specific paint specifications.

The technical questions and answers clarify critical project details, such as surface preparation (contractors are responsible for power washing), paint product specifications (Sherwin Williams Duration Exterior Acrylic Latex is acceptable), and scope modifications. Contractors can replace shutter hardware matching existing styles, must stain and clear seal thresholds, and are required to replace four window sills. The project allows for a working supervisor and includes a formal change order process for addressing unforeseen repairs. No specific budget or funding source is explicitly stated in the addendum, but the document provides comprehensive guidance for bidders to prepare accurate and responsive proposals for the mansion paint repair project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Printed: Mar 21, 2025 Page 1 FORM ID: WV-PRC-ARFQ-002 2020/05

State of West Virginia Agency Request for Quote

Construction

Addendum No. 03 is issued to publish and distribute the attached information to the Vendor Community.

2025-03-21

DIVISION OF NATURAL RESOURCES

PROPERTY & PROCUREMENT OFFICE

324 4TH AVE

SOUTH CHARLESTON WV 25303-1228

US

Vendor Customer Code:

Vendor Name :

Address :

Street :

City :

State : Country : Zip :

Principal Contact :

Vendor Contact Phone: Extension:

Date Printed: Mar 21, 2025 Page 2 FORM ID: WV-PRC-ARFQ-002 2020/05

ADDITIONAL INFORMATION

DIVISION OF NATURAL

RESOURCES

DIVISION OF NATURAL

RESOURCES

PARKS & RECREATION-PEM

SECTION

BLENNERHASSETT ISAND

HISTORICAL STATE PARK

324 4TH AVE 137 JULIANA ST

SOUTH CHARLESTON WV PARKERSBURG WV

US US

1 Residential building construction services

1 MANDATORY PRE-BID MEETING @ 11 a.m. ET 2025-02-26 2 TECHNICAL QUESTION DEADLINE @ 9 a.m. ET 2025-02-28

Document Phase Document Description Page

DNR2500000007 Parks: Blennerhassett Mansion Paint Repairs

Revised 6/8/2012

SOLICITATION NUMBER: [Insert RFQ, RFP No.] Addendum Number: [Insert Number]

The purpose of this addendum is to modify the solicitation identified as [insert RFQ, RFP No.] (“Solicitation”) to reflect the change(s) identified and described below.

Applicable Addendum Category:

[ ] Modify bid opening date and time

[ ] Modify specifications of product or service being sought

[ ] Attachment of vendor questions and responses

[ ] Attachment of pre-bid sign-in sheet

[ ] Correction of error

[ ] Other

Description of Modification to Solicitation:

Additional Documentation: Documentation related to this Addendum (if any) has been included herewith as Attachment A and is specifically incorporated herein by reference.

Terms and Conditions:

1. All provisions of the Solicitation and other addenda not modified herein shall remain in full force and effect.

2. Vendor should acknowledge receipt of all addenda issued for this Solicitation by completing an Addendum Acknowledgment, a copy of which is included herewith.

Failure to acknowledge addenda may result in bid disqualification. The addendum acknowledgement should be submitted with the bid to expedite document processing.

ARFQ DNR2500000007

No.03

Addendum issued to publish and distribute the attached documentation to the vendor community.

1. To extend bid opening date to 04/01/2025 at 1:30PM ET.

1. To publish vendor questions and responses.

Attachment A

ARFQ DNR25*07 - Addendum No. 03 • Technical Questions West Virginia Division of Natural Resources

Parks: Blennerhassett Mansion Paint Repairs

Q1: Will power washing be a part of the project bid, or will the parks and recreation handle the power washing? Paint manufacturers recommend power washing exterior surfaces prior to painting.

A1: Preparation for all painting will be provided by the Contractor. Cleanup of all debris will be the Contractor’s responsibility.

Q2: Do we need to powder coat the shutter hardware? Powder coating is an expensive process and as such it may be more cost efficient to replace with new, or to simply wire wheel, prime with a rust prohibiting primer, and finish with an exterior enamel paint direct to metal paint.

A2: The Contractor will have the option to provide new shutter hardware matching the existing style and size, as approved by the Architect.

Q3: Will there be a change order process to address repairs not in the bid plans? At the pre bid site visit there were several necessary repairs observed not mentioned in the bid plans.

A3: Any unforeseen or unknown issues that need to be corrected in order to complete the project as bid will be addressed through formal change order.

Q4: Do we need to include the metal handrails in the paint bid?

A4: Yes, the preparation and painting of all metal handrails is to be included in the bid.

Q5: Are the thresholds being stained and clear sealed, just clear sealed, or primed and painted?

A5: Stain and clear seal all thresholds.

Q6: Can Exterior Latex Duration be used in place of A-100 Flat due to warranty expectations?

A6: Sherwin Williams Duration Exterior Acrylic Latex would be acceptable. As it is self priming, the primer coat may be eliminated. However, two finish coats will still be required.

Q7: Does entire structure need to be fully primed?

A7: Yes, unless the Contractor uses 2 coats of an approved self-priming paint like SW Exterior Latex

Duration, in which case the prime coat may be eliminated.

Q8: Has the missing shutters and hardware been found?

A8: No, the Contractor must provide the shutter to match the existing shutters.

Q9: Is all the existing paint needing to be removed with paint removers as indicated in paint spec 2.6?

A9: Paint removal is included for the preparation of shutter hardware for powder coating.

ARFQ DNR25*07 - Addendum No. 03 • Technical Questions West Virginia Division of Natural Resources

Parks: Blennerhassett Mansion Paint Repairs

Q10: Does all the shutter hardware need to be power coated?

A10: The Contractor will have the option to provide new shutter hardware matching the existing style and size, as approved by the Architect.

Q11: Do we need a non-working supervisor or a working supervisor on site at all times?

A11: No, a working supervisor is acceptable.

Q12: Can we just replace all hardware on shutters?

A12: The Contractor will have the option to provide new shutter hardware matching the existing style and size, as approved by the Architect.

Q13: Will the owner look at using new hardware for the shutters.

A13: The Contractor will have the option to provide new shutter hardware matching the existing style and size, as approved by the Architect.

Q14: If the owner will use new hardware for the shutters, will there be a submittal for the contractors to go by.

A14: The Contractor will have the option to provide new shutter hardware matching the existing style and size, as approved by the Architect.

Q15: Is the owner going to put in addendum a total number of windowsills to be replaced?

A15: Provide replacement of 4 window sills in the project in addition to the trim and sills required at the oval windows.

Revised 6/8/2012

ADDENDUM ACKNOWLEDGEMENT FORM

SOLICITATION NO.:_____________

Instructions: Please acknowledge receipt of all addenda issued with this solicitation by completing this addendum acknowledgment form. Check the box next to each addendum received and sign below.

Failure to acknowledge addenda may result in bid disqualification.

Acknowledgment: I hereby acknowledge receipt of the following addenda and have made the necessary revisions to my proposal, plans and/or specification, etc.

Addendum Numbers Received:

(Check the box next to each addendum received)

[ ] Addendum No. 1 [ ] Addendum No. 6

[ ] Addendum No. 2 [ ] Addendum No. 7

[ ] Addendum No. 3 [ ] Addendum No. 8

[ ] Addendum No. 4 [ ] Addendum No. 9

[ ] Addendum No. 5 [ ] Addendum No. 10

I understand that failure to confirm the receipt of addenda may be cause for rejection of this bid. I further understand that any verbal representation made or assumed to be made during any oral discussion held between Vendor’s representatives and any state personnel is not binding. Only the information issued in writing and added to the specifications by an official addendum is binding.

Company

Authorized Signature

Date

NOTE: This addendum acknowledgement should be submitted with the bid to expedite document processing.

ARFQ DNR25*07

File details come from the government source that posted it. Updated .