Addendum No_ 2.pdf

PDF 146 KB Posted

Attached to
Red Oak Road Bridge Over Mill Creek
Solicitation number
PE-77648-NONST-2025-000000016
Issued by
Terrell County, Georgia

About this file

This is Addendum No. 2 issued by Watkins & Associates Engineering for the Tift County Board of Commissioners' Red Oak Road Bridge Over Mill Creek project. The sole modification announced in this addendum is a change to the bid submission deadline, which has been moved from Wednesday, January 22, 2025, at 2:00 PM to Wednesday, January 29, 2025, at 11:00 AM.

The underlying project involves the construction of a 32-foot wide, 80-foot-long bridge structure using pre-stressed concrete slabs, PSC pilings, and approach slabs, including removal of existing drainage structures. The project has a completion timeline of 45 consecutive calendar days to substantial completion, with final contract closeout required within 60 consecutive calendar days.

View the file

Other files

File Type Posted
_Addendum No_ 1_Tift Co_ Red Oak Road.pdf PDF
00111 _ Advertisement for Bids.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

T: 229.388.8823 | 1606 Whiddon Mill Road, Tifton, GA 31793 | WWW.WATKINSENG.COM

ADDENDUM NO. 2

CONTRACT DOCUMENTS & SPECIFICATIONS

January 21, 2025

PROJECT: Red Oak Road Bridge Over Mill Creek

W&A Project No.: W2036-125-01

OWNER: Tift County Board of Commissioners

BID DATE: Wednesday, January 22, 2025, at 2:00 PM

Wednesday, January 29, 2025, at 11:00 AM

1. CONTRACT DOCUMENTS – Section 00410, Bid Form:

The Bid Date and Time has been changed to Wednesday, January 29, 2025, at 11:00 AM.

END ADDENDUM NO. 2