Addendum No 1 Centrifuge Replacement Project.pdf
PDF 95 KB Posted
- Solicitation number
- 65117415
- Issued by
- Sedgwick County, Colorado
About this file
Addendum No. 1 for the Blue River Wastewater Treatment Plant (BRWWTP) Centrifuge Replacement Project, issued by the Silverthorne-Dillon Joint Sewer Authority, modifies the original bidding and contract documents. The addendum changes the bid submission method from physical sealed bids to electronic PDF submissions to BRWTP@silverthorne.org, with the bid deadline remaining July 18, 2023, at 2:00 PM. The project involves replacing centrifuges at the wastewater treatment plant, with revised milestone dates for demolition and installation of two centrifuges, including specific start and completion dates between August and October 2023.
The addendum updates the contract's liquidated damages schedule for missed milestones, with penalties ranging from $1,000 to $10,000 per day depending on the specific milestone not met. The changes include adjusting the demolition and installation timelines for the first and second centrifuges, with new milestone dates for beginning demolition, completing installation, and starting demonstration of each centrifuge. The modifications aim to provide more precise scheduling and clearer expectations for the contractor's progress throughout the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2480 West 26th Avenue, B225
Denver, CO 80211 T: +1 303-964-3333 www.merrick.com
TOTAL PAGES: 4
(including letter)
ADDENDUM NO. 1
DATE: JULY 10, 2023
TO: ALL HOLDERS OF BIDDING AND CONTRACT DOCUMENTS
RE: SILVERTHORNE-DILLON JOINT SEWER AUTHORITY
BLUE RIVER WASTEWATER TREATMENT PLANT (BRWWTP)
CENTRIFUGE REPLACEMENT PROJECT
Holders:
Attached is ADDENDUM NO. 1 to the Silverthorne-Dillon Joint Sewer Authority BRWWTP Centrifuge
Replacement Project.
To verify that you have received this ADDENDUM NO. 1, we request that you respond via email to jody.allen@merrick.com.
Please contact us with any questions you may have.
Sincerely, Jody M. Allen
Project Engineer
Attachment – Addendum No. 1
SILVERTHORNE-DILLON JOINT SEWER AUTHORITY ADDENDUM NO. 1
BRWWTP CENTRIFUGE REPLACEMENT PROJECT Page 2 of 4 07/10/23
ADDENDUM NO. 1 TO THE
SILVERTHORNE-DILLON JOINT SEWER AUTHORITY
BIDDING AND CONTRACT DOCUMENTS FOR THE
BLUE RIVER WASTEWATER TREATMENT PLAN (BRWWTP)
CENTRIFUGE REPLACEMENT PROJECT
TO: ALL HOLDERS OF BIDDING AND CONTRACT DOCUMENTS
DATE: JULY 10, 2023
The following changes, additions, and/or deletions are hereby made part of the Bidding and Contract
Documents for the Blue River Wastewater Treatment Plant (BRWWTP) Centrifuge Replacement
Project.
CHANGES TO SPECIFICATIONS:
Addendum
Number
Section / Section Name /
Article / Page Addendum Item
AD1-1 Section 00 11 16, Invitation to Bid, Article 1, Page 1 of 1.
REPLACE:
“The Silverthorne Dillon Joint Sewer Authority (JSA) will receive sealed bids at the District’s office, 26452
Highway 9, Silverthorne, CO 80498 for the Blue River
WWTP Centrifuge Replacement Project until 2:00 PM on July 18, 2023, at which time bids that have been duly received will be opened publicly.”
WITH:
“The Silverthorne Dillon Joint Sewer Authority (JSA) will receive electronically submitted bids in PDF format to BRWTP@silverthorne.org. until 2:00 PM on
July 18, 2023, at which time bids that have been duly received will be opened publicly.”
AD1-2 Section 00 52 00, Agreement, Article 4.04, Milestones, Page 2 of 8.
REPLACE:
“2. Milestone 2: Begin demolition of first centrifuge no later than September 6, 2023.
3. Milestone 3: Begin demolition of second centrifuge no later than September 13, 2023.
4. Milestone 4: Complete first centrifuge and appurtenant installation, including demonstration
BRWWTP CENTRIFUGE REPLACEMENT PROJECT Page 3 of 4 07/10/23
Addendum
Number
Section / Section Name /
Article / Page Addendum Item period and Owner operation of one centrifuge no later than September 29, 2023.”
WITH:
“2. Milestone 2: Begin demolition of first centrifuge no later than August 28, 2023.
3. Milestone 3. Complete first centrifuge and appurtenant installation, including first centrifuge start of demonstration by Centrisys on September 11, 2023.
4. Milestone 4: Begin demolition of second centrifuge no later than September 25, 2023.
5. Milestone 5. Complete second centrifuge and appurtenant installation, including second centrifuge start of demonstration by Centrisys on October 9, 2023.”
AD1-3 Section 00 52 00, Agreement, Article
4.05.A.3, Milestones.
REPLACE:
“b. Contractor shall pay Owner $1,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 2, until Milestone 2 is achieved, or until the time specified for Substantial
Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.
c. Contractor shall pay Owner $5,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of
Milestone 3, until Milestone 3 is achieved, or until the time specified for Substantial Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.
d. Contractor shall pay Owner $10,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 4, until Milestone 4 is achieved, or until the time specified for Substantial
Completion is reached, at which time the rate
BRWWTP CENTRIFUGE REPLACEMENT PROJECT Page 4 of 4 07/10/23
Addendum
Number
Section / Section Name /
Article / Page Addendum Item indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.”
WITH:
“b. Contractor shall pay Owner $1,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 2, until Milestone 2 is achieved, or until the time specified for Substantial
Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.
c. Contractor shall pay Owner $5,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of
Milestone 3, until Milestone 3 is achieved, or until the time specified for Substantial Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.
d. Contractor shall pay Owner $5,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of
Milestone 4, until Milestone 4 is achieved, or until the time specified for Substantial Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.
e. Contractor shall pay Owner $10,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 5, until Milestone 5 is achieved, or until the time specified for Substantial
Completion is reached, at which time the rate indicated in Paragraph 4.05.A.1 will apply, rather than the Milestone rate.”
END OF ADDENDUM NO. 1
File details come from the government source that posted it. Updated .