Addendum No_ 1_ 2026_04_17.pdf
PDF 860 KB Posted
- Attached to
- Cell Nos. 6A & 6B - Thomasville MSW Landfill
- Solicitation number
- PE-66084-NONST-2026-000000052
- Issued by
- Terrell County, Georgia
About this file
This is an Addendum No. 1 and pre-bid meeting minutes for a sealed bid solicitation issued by the City of Thomasville, Georgia, for the construction of Cells 6A & 6B at the Thomasville/Sunset Drive MSW Landfill, with engineering services provided by Hodges, Harbin, Newberry & Tribble, Inc. The project consists of MSW landfill cell construction including earthwork, erosion control, composite liner construction, geosynthetics installation, protective cover, leachate collection system, stormwater management, and a perimeter access road. Key bid items include clearing and grubbing (approximately 1.8 acres for cell footprint and laydown area, plus 4 acres in existing borrow area if needed), 24-inch compacted clay liner, 60-mil textured HDPE geomembrane liner, geocomposite drainage media, leachate collection system piping, 24-inch protective cover, geogrid reinforcement, and an access road (approximately 17,280 square feet or 1,920 square yards). Addendum No. 1, dated April 17, 2026, clarified and revised several bid items and technical specifications, including removal of HDPE riser pipes and flat stock plates from the Leachate Penetration Assembly, revision of unit measurements for the access road from square yards to square feet, and clarification of geocomposite transmissivity requirements. The pre-bid meeting was held April 2, 2026, with site observations conducted. The bid deadline was April 23, 2026, at 10:00 A.M., with a contract time of 210 consecutive calendar days and questions due by April 15, 2026, at 12:00 P.M. Plan procurement deadline was April 15, 2026, at 2:00 P.M. from the engineer at $150 per set.
Pricing is on a unit price and quantity basis, with payment made on installed quantities as determined by the Confirmation Surveyor. Mobilization and General Conditions may not exceed six percent of the Total Base Bid, with fifty percent payable on the first pay request, twenty-five percent at fifty percent project completion, and twenty-five percent upon completion of demobilization. Performance and Payment Bonds are required, with fifty percent payment at mobilization initiation and fifty percent at completion of demobilization. Monthly payment applications are due by the 25th of each month, with the contractor responsible for providing construction records and draft applications by the 20th. The contractor is responsible for all costs including labor, equipment, materials, testing, surveying, permits, insurance, and overhead, with no separate fuel surcharges allowed. The contractor must maintain the clay liner surface until the CQA Engineer verifies minimum thickness and permeability requirements and the geomembrane is deployed, and must maintain the protective cover surface through EPD inspection and final approval. The project requires NPDES Construction Stormwater permit compliance with qualified personnel on-site and monthly sampling and reporting to the City. The City of Thomasville reserves the right to reject any and all bids and to waive informalities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Advertisement for Bids_ 2026_03_20.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
DATE: APRIL 17, 2026
PROPOSAL, CONTRACT, BOND AND SPECIFICATIONS
FOR:
CONSTRUCTION OF CELLS 6A & 6B
AT THE THOMASVILLE/SUNSET DRIVE MSW LANDFILL
FOR
CITY OF THOMASVILLE
THOMASVILLE, GEORGIA
APRIL 17, 2026
1. The pre-bid meeting minutes and sign-in sheet are included with this addendum and officially incorporated into the Bid Documents.
2. The Bid Form has been updated to:
a. Revise Bid Item C-1 and clarify the Clearing and Grubbing line item applies to the Cell Footprint and Laydown Area. The laydown area is approximately 1.8 acres, and the cell footprint is approximately 13.7 acres.
b. Add Bid Item C-2 as a separate line item for Clearing and Grubbing in the Existing Borrow Area (if needed). A quantity of 4 acres was assumed for bidding purposes.
c. Revise Bid Item G-4 to remove language associated HDPE Riser Pipes and HDPE Flat stock plates as they do not apply and are not needed for the Leachate Penetration Assembly (LPA). Language was added saying “Complete, see details” for LPA construction information.
d. Revise Bid Item K-1 to change units from Square Yards to Square Feet
3. The Technical Specifications have been updated to:
a. Revise the Leachate Penetration Assembly item in Section 01025 – Measurement and Payment of the Technical Specifications to remove language associated HDPE Riser Pipes and HDPE Flat stock plates as they do not apply and are not needed for the Leachate Penetration Assembly (LPA) and were revised to the following:
i. Measurement – Measurement shall be the quantity actually installed for complete assembly as shown on the Plans.
ii. Payment – Payment shall be at the Unit Price in the Bid Worksheet.
b. Revise Section 02755 – Geocomposite Drainage Media to clarify the geocomposite transmissivity requirements to be:
i. Hydraulic Gradient of 0.02
ii. Max Confining Pressure of 15,000 psf
4. Response to Bidder questions:
• The plans and specifications have a GCL alternate in them, but I do not see a line in the bid form and the Measurement and Payment states, “Not Used”. Please clarify.
GCL is not required and will not be used for the project. The technical specifications HHNT provides are updated on a project specific basis and when an item is not applicable to project, HHNT designates it as “Not Used” in the Measurement and Payment Section rather than removing it entirely.
• Please confirm the SY quantity for the Access Road. When we scale it we see a significantly different quantity. The provided quantity seems to be in square footage, and not square yards.
The access road quantity was originally shown in units of square yards, however it should be shown in units of square feet. The correct quantity should be ~17,280 SF OR ~1,920 SY, which is a rough estimate of the 2d area of the proposed access road. Bid Item K-1 was updated accordingly to change the units from square yards (SY) to square feet (SF).
• Is the Tack On Stormwater Diversion Berm shown in Pay Item C2 a duplicate of the Ditch – 6’ wide that is shown in Pay Item I-5?
No, the stormwater diversion berm and 6 ft wide ditch are two separate items that serve different purposes in two different areas of project.
The stormwater diversion berms are temporary construction features designed to divert stormwater away from the active cell construction area. Both berms are located on the north side of proposed Cells 6A and 6B on the slopes of existing Cells 5A and 5B.
The 6-foot-wide ditch is a permanent post-construction drainage feature located south of the proposed cell, as shown in the plans.
• Is it possible that a typo was made on the quantity for the Geogrid Reinforcement also? It is the line item just above the Access Road we discussed. It is shown in square yards. Should that also be square feet?
The geogrid reinforcement quantity is correct. The assumed quantity is based on historical data for bidding purposes. As a unit price project, the actual quantity installed will be paid to the selected bidder.
• In the specifications, the bid form G.4 calls out for a leachate penetration that matches the details 13&15, but not the description in that bid item for two 24" risers with plate stock. Could I get you to have that clarified of what's required?
The two 24” riser pipes with plate stock are not required for this project. Cells 6A and 6B use a Leachate Penetration Assembly as shown in Details 13 and 15 on the plans. Details 13 and 15 are correct and accurately represent the required configuration and should be referenced during construction. Bid Form Item G-4 and Section 01025 in the Technical Specifications have been updated to remove the reference to the 24-inch risers and flat stock plate.
• Now if it is per the detail will existing manhole #7 have a penetration with valve coming off it of for tie-in?
Based on previous as-built information and manhole submittals from the Construction of Cell 5A and Sediment Pond No. 3, existing manhole #7 does have an existing stubout.
• We need Clarification regarding the geocomposite transmissivity requirements, as there are discrepancies between the specification and the drawings:
o The specification requires testing at a load of 8,200 psf with a hydraulic gradient of 0.1.
o The drawing indicates a load of 15,000 psf and references gradients of both 0.1 and 0.02.
These differing requirements would result in different product selections.
The RT was completed using the most stringent criteria, which required the use of a Fabrinet BP 300-6-6.
The transmissivity conformance testing shall utilize a hydraulic gradient of 0.02 and a max confining pressure of 15,000 psf in accordance with Note 3 of Table 6 in the CQA Plan Drawing. Section 02755 – Geocomposite Drainage Media of the Technical Specifications has been revised accordingly.
--- END OF ADDENDUM NO. 1 ---
PRE-BID MEETING MINUTES
CONSTRUCTION OF CELL NOS. 6A & 6B
THOMASVILLE/SUNSET DRIVE MSW LANDFILL, THOMASVILLE GEORGIA
HODGES, HARBIN, NEWBERRY & TRIBBLE, INC.
3920 Arkwright Road Suite 101 Macon, Georgia 31210
Phone (478) 743-7175 Fax (478) 743-1703 www.hhnt.com
Thomasville/Sunset Drive MSW Landfill
April 2nd, 2026, at 10:00 a.m.
Participants:
See Sign-In Sheet
I. INTRODUCTIONS
a. Owner: City of Thomasville
• City Engineer: Todd Powell, P.E.
• Landfill Director: Jimmy Smith, Jr.
• Solid Waste and Landfill Superintendent: Lee Thomas (On-site contact)
b. Engineer: Hodges, Harbin, Newberry & Tribble, Inc. (HHNT)
• Daniel Cheek, P.E.
• Dalton Chapman, E.I.T.
c. CQA Consultant: (TBD)
d. Certification Surveyors: (TBD)
II. PLANS AND SPECIFICATIONS
a. Available from HHNT per advertisement
III. IMPORTANT DATES
a. Bid Opening: Thursday, April 23rd, 2026 at 10:00 am
b. Plan Request Deadline: Wednesday, April 15th, 2026 at 2:00pm (to HHNT)
c. Contract Time – 210 consecutive calendar days
d. Last Day for Questions: Wednesday, April 15th, 2026 at 12:00pm (to HHNT)
IV. ADDENDUM / CONTRACT ISSUES
a. All addenda will be issued to Paid Plan Holders. Plans must be purchased from HHNT to be on Paid Plan Holder List.
b. Unit Price / Quantity Bid - Payment will be made on installed quantities.
c. Liquidated damages - as noted in Contract Documents.
V. PROJECT DESCRIPTION
a. Project description: Construction of MSW Lined Cell Nos. 6A & 6B (as shown on plans)
b. General Contractor’s responsibilities: Described in documents.
c. Owner’s responsibilities: Described in documents.
d. Contractor to provide unit prices as outlined on the Bid Form.
CONSTRUCTION OF CELL NOS. 6A & 6B
THOMASVILLE/SUNSET DRIVE MSW LANDFILL, THOMASVILLE GEORGIA
e. CQA and certification Surveyor to be separate contract administered by City of Thomasville.
f. Pre-construction survey is General Contractor’s responsibility. It is to be done following topsoil removal in the proposed cell area.
g. Water source: Sediment Pond No. 2 and/or No. 3 (east of the proposed cell).
h. Erosion & Sediment Control: All installed erosion control measures must meet minimum requirements of Georgia Erosion Control Manual and be maintained throughout the duration of the project. Contractor is responsible for compliance with the NPDES Construction Stormwater permit, including sampling, reporting, inspections and maintenance of all BMPs. Contractor must have a qualified person on-site and shall provide inspections & sampling data to the City of Thomasville monthly w/ pay requests.
i. Storm water control is the Contractor’s responsibility. The Contractor shall place a large emphasis on compliance with storm water installation, monitoring, maintenance, and compliance. The GC shall meet project requirements for project dewatering, protection of all phases of work from erosion and siltation, and maintenance of E&S measures, ditches, culverts, etc.
j. Structural fill and clay are to be from the on-site borrow area or cell footprint. CQA Engineer’s representative is available to test interim moisture and density at Contractor’s request and can discuss soil conditions but is not responsible for and will not direct work.
k. Protective Cover material is intended to be used for Liner Protection from on-site soil. Unit Price shall include required testing, screening, hauling, installation, fine grading, complete.
l. Contractor to provide materials and installation of the geosynthetics for the cell.
m. Geosynthetic materials and installation to be provided by General Contractor. The geosynthetic installation duration of 21 days is included in the total contract time. State (GA EPD) certification for each surface of Cell Nos. 6A & 6B (subgrade, clay, FML and protective cover completion) is possible but not expected. Entire surface must be complete at the time of GA EPD inspection. Each surface must be accepted by Owner, CQA Engineer, and Design Engineer.
n. Each completed surface may be inspected by the GA EPD but must be approved by the Owner, CQA Engineer, and Design Engineer prior to beginning the next phase of construction. The contractor should make time allowances for the required inspections.
Each surface to be surveyed on a 50’ grid along with all grade breaks to contour the cell.
The certification grid will be established by HHNT.
o. Maintenance of the clay surface through Owner acceptance and liner deployment and maintenance of protective cover surface through EPD inspection and final approval is the Contractor’s responsibility.
p. As-built surveys of all surfaces is the Owner’s responsibility. Two trips per surface will be budgeted. Any costs for extra trips are to be reimbursed by the Contractor. The Contractor is to provide as-built survey shots in AutoCAD to the Owner and Engineer on the leachate pipe and any other infrastructure installed for inclusion on the relative as-builts.
q. Construction sequencing and means/methods is the Contractor’s responsibility.
r. Discuss liner tie-in for Cell Nos. 6A & 6B. Removal of waste and leachate management will be incidental to compacted soil liner unit price.
s. Leachate Collection System of existing landfill must remain operational during construction.
t. No leachate will be allowed to reach the storm water management system
u. Lines and grades are critical. Construction surveying control is Contractor’s responsibility.
Grading tolerances are outlined in Contract Documents. All layers must meet elevation and thickness requirements.
v. Time weather delays outlined in Contract Documents.
w. Grassing must be in accordance with the project documents.
x. Safety is the Contractor’s responsibility. Contractor must provide their safety plan to the City of Thomasville.
y. Restrictions on work hours – Normal operating hours for the Landfill are 7:00am – 5:00pm (M-F) and 8:00am – 2:00pm (Sat.), gate access will be provided, and accommodations will be made accordingly in order to not restrict contractor during construction activities.
Coordination with contractor for access outside of these hours will not be an issue.
z. Vegetative material may be burned or ground (Contractor is responsible for this).
Contractor to call and get a burn permit. Material may also be placed in the C&D Landfill on-site.
aa. Fuel surcharge – Not allowed.
• Non-moving fuel tank must be double lined or in secondary containment area.
• Mobile fuel truck must be parked overnight in a lined area.
• Contractor to provide site-specific spill prevention plan to cover their fuel tanks.
bb. Moisture conditioning of all soils is Contractor’s responsibility.
cc. City of Thomasville expects project startup to be immediate.
dd. Discuss current waste and dirt truck traffic routes. (on-site, if necessary)
ee. Screening requirements for structural fill and soil liner will be at the Bidder’s discretion but must meet the particle size requirements and technical specifications (CQA Plan requirements for each specific layer).
ff. All questions should be submitted through HHNT so that answers may be provided to all Bidders.
gg. Contractor storage/lay-down area is shown on plans.
hh. Porta John is shown on plans. Exact location to be determined by Contractor.
ii. Discuss on-going subgrade investigation and geogrid bid item
Following discussions of the items above, the meeting attendees will observe Cell Nos. 6A & 6B and the on-site borrow area.
VI. ADDITIONAL ITEMS
1. GCL will not be used in cell construction.
2. Native soil to be used for Protective Cover with a hydraulic conductivity of ≤ 1.0 x 10-4 cm/sec.
3. Structural Fill bid item was clarified to be any suitable structural fill obtained from the borrow area. The proposed cell has an overall Net Cut, so structural fill does not include mass excavation and flipping cut soil from within the cell footprint to get to grade.
4. The landfill has a trailer with power and can be used by the contractor during construction as a field office, a separate job trailer will not be needed.
5. Geosynthetics must be selected and installed according to engineering and manufacturing specifications. MQC and CQC testing to be the responsibility of the contractor and confirmed by the selected CQA consultant.
6. Plywood rub sheets are called to be used for the temporary edge of liner construction.
VII. CELL NOS. 6A & 6B AND BORROW AREA OBSERAVTIONS
1. Proposed Laydown area of approximately 1.8 acres was observed; area may be used and cleared as needed.
2. Existing Borrow Area was observed. The site manager had no preference regarding obtaining soil from either borrow pit (if needed).
3. Existing edge of liner marker posts for Cells 5A and 5B were observed from a distance.
Cells 5A and 5B were each constructed in the last 7 years, and it was made known that existing tie-ins should be easy to locate.
4. On-going subgrade investigation project was discussed and whether geogrid will be needed or not will be clarified once results are received from initial testing.
5. The site manager mentioned the existing barricade will be removed that is currently blocking the west side access road of the landfill before construction activities begin.
6. Limestone boulders shall be moved to the south side of the on-site borrow area, outside of the future waste footprint. Final location shall be determined by the site manager.
THOMASVILLE/SUNSET DRIVE MSW LANDFILL
CELL NOS. 6A & 6B CONSTRUCTION
BID FORM
REVISED: APRIL 2026
Item No. Units Unit Price Total Price
A.
1. LS
2. LS
3. LS
B.
1. LS
2. EA
C.
1. AC
2. AC
3. LF
D.
1. CY
2. CY
3. CY
E.
1. CY
F.
1. SF
2. LF
3. LF
4. LF
5. SF
G.
1. LF
2. LF
3. EA
4. EA
H.
1. CY
I.
1. EA
2. AC
3. AC
4. LF
5. LF
6. LF
7. EA
Leachate Cleanout (Includes caps, fittings, nuts, bolts, blind flange and stainless steel bolts/backup ring) 3
60 mil HDPE Flexible Membrane Liner (Textured) (including Material, Installation, Anchor Trench Material, Rain Flap Berms, and Tie-Ins to existing Liner)
Leachate Penetration Assembly (complete including 2-24" dia HDPE SDR-11 Riser with 8'x8'x2' HDPE flat Stock Plate, connnector pipe, ASTM No. 57 stone, ASTM No.89 stone filter, filter geotextile, and 24 osy cushion geotextile) (Complete, see details)
Ditch - 2' Wide and 4' Deep with Turf-Reinforcement Mat (TRM) Lining
Temporary Grassing
Temporary Edge of Liner Protection (includes anchoring temporary edge of liner and pressure treated plywood)
Leachate Collection System
Install Piping: 8" Dia. Perforated HDPE Pipe (inside cell, including pipe, sleeves, tie-ins, fittings, stone, end caps, geotextile wrap and add'l 24 osy geotextile cushion)
Install Piping: 8" Dia. Solid HDPE Pipe (inside cell)
Liner Protection
24" Thick Protective Cover - Native Soil (incl. excavation & haul from on-site borrow area, placement, compaction, fine grading and maintenance;
compacted soil backfill along new edge of cell shall be incidental)
Site Improvements/Stormwater Management
Construction Exit
1,776
590,092Double Sided Geocomposite Drainage Media (GDM) (including material and installation)
Geosynthetics
Rain Flap Berm (Construct Only) Permanent Anchor Trench (permanent edge, including opening and back filling)
1.8 15.5
Unsuitable Material (Remove & Replace) (assumed quantity for pricing) 2,000
Structural Fill (Unclassified) (Incl. additional excavation and haul from on-site borrow area, placement, compaction, maintenance of road, and BA) *Assumed quanitity for pricing
5,000
Performance Bond Payment Bond
Surveying
Construction Surveying Marker Posts
Description Approx. Quantity
Mobilization & General Conditions
General Conditions
43,711
Site Preparation
Clearing and Grubbing (Cell Footprint and Laydown Area) Clearing and Grubbing (in Existing Borrow Area if needed) Tack-on Stormwater Diversion Berm (including soil, construction, grassing, DS channel matting, SS slope matting and maintenance)
Earthwork
Contracted Excavation (Unclassified) (Incl. placement of all material either as structural fill, stockpile or disposal of any encountered woody debris;
stockpile locations to be coordinated with landfill manager)
43,711
614,676
4.0
1,762
71,500
Clay Liner
24" Thick Compacted Clay Liner [k ≤ 1.0 x 10-7 cm/sec] (incl. subgrade prep, excavation & haul from on-site borrow area, placement, compaction, fine grading; also incl. tie-in seam prep and geosynthetic unload/storage as incidental)
1,902
Permanent Grassing
Ditch - 6' Wide and 4' Deep with Double-sided Excelsior Matting
Stone Check Dam
Silt Fence (Type C)
8. EA
9. EA
10. LF
11. EA
12. SY
13. SY
14. SY
15. LS
J.
1. SY
K.
1. SY SF
Drop Inlet Protection (including steel posts, washed stone, and hardware cloth)
9,680
17,280
Subgrade Stabilization
36' Wide Permanent Perimeter Access Road (8" Thick Aggregate Stone Road Surface, and fabric;
includes structural fill for truck turn around area and cell access ramp)
Concrete Drop Inlet (D.I. 300)
NPDES Stormwater Compliance Monitoring
Geogrid Reinforcement (layout to be provided by Geotechnical Engineer) (complete; incl. material purchase, delivery, 2' subgrade overexcavation, placement of two (2) layers of uniaxial geogird, backfill, compaction and fine grading subgrade; geogrid shall be Huesker Inc. Fortrac 200 uniaxial geogrid or engineer approved equal) **Assuned Quantity for Pricing.
Access Road
54" Dia. Concrete Headwall 6" Dia. Rip-Rap Outlet Protection (GDOT Type 1 & 3 as specified) 9" Dia. Rip-Rap Outlet Protection (GDOT Type 1 & 3 as specified) 12" Dia. Rip-Rap Outlet Protection (GDOT Type 1 & 3 as specified)
54" Dia Corrugated Metal Pipe (CMP)
TOTAL BASE BID
Technical Specifications Construction of Cell Nos. 6A and 6B City of Thomasville
February 2026 HHNT Project No. 7600-045-01
01025 - 1
01025 MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 DESCRIPTION
The items listed in this section refer to and represent pay items listed on the Bid Form. The items found in the Bid Form represent all of the lump sum and unit price pay items for the completion of the Work. No direct or separate payment will be made for providing miscellaneous temporary or incidental work, plant, or services, CONTRACTOR'S field office(s), job signs, sanitary requirements, testing and safety devices, submittals, record drawings, water supplies, power, maintaining traffic, removal of contractor-generated waste, watchmen, security, bonds, insurance, warrantees, or any other similar items not specifically specified, but necessary to complete the work. Compensation for all such labor, materials, and services shall be included in the Bid Form price stipulated for the lump sum, unit price, and contingency pay items and Total Base Bid.
1.2 RELATED ITEMS
Bid Form Section 01000 - General Requirements General Conditions of the Contract Supplementary Conditions of the Contract
1.3 BID FORM
Work required under this project is represented by the items on the Bid Form and includes furnishing all labor, equipment, tools and materials and performing all operations required to complete the Work satisfactorily and provide a fully functional and operational system as intended, as specified and as indicated on the Drawings.
A. The Bid Form lists each item of work for which payment will be made. No payment will be made for any items other than those listed on the Bid Form. Those items listed on the Bid Form represent the total Work required to provide a complete, functional and operational project as explicitly shown, implied or intended.
B. Essential, unlisted components of the Work for the satisfactory completion of the Work that are not specifically included on the Bid Form, and that are not specified in this section to be measured or paid for or included in one of the items listed on the Bid Form, shall be considered incidental to the Work. The cost of all items that are incidental to the Work shall be included in the Total Base Bid as it appears on the Bid Form.
01025 - 2
C. All costs including the CONTRACTOR’S overhead costs and profit shall be considered as included in the lump sum or unit price Bid Form for the Item to which it is related, is associated, or to which it pertains. The CONTRACTOR shall prepare the Bid Form accordingly.
D. Each pay item Bid Form price will include an amount considered by the CONTRACTOR to be adequate compensation to cover the CONTRACTOR'S overhead and profit for each of the separately identified pay items.
E. The Total Base Bid shown on the Bid Form will be determined in part by multiplying each Bid Form unit price by the estimated quantity. The product of these when placed in the Bid Form price column and summed with other Bid Form prices in the same column, equal the Total Base Bid.
1.4 DEFINITIONS
A. This Section specifies administrative and procedural requirements for Lump Sum and unit prices.
1. A Lump Sum price is an amount proposed by Bidders and stated on the Bid Form as a price where measurement will not be made for payment for materials, services and/or work identified in the Drawings and Specifications for a particular pay item. The CONTRACTOR will not be entitled to any adjustment in a Lump Sum Bid Form Price as a result of any change caused by a variation in quantities as a result of more accurate measurements. The CONTRACTOR agrees to accept the aforesaid Lump Sum Bid Form price as complete and total compensation for all work to be performed under a Lump Sum pay item.
2. Lump sum prices include all material, labor, equipment, overhead, profit and applicable taxes.
3. A unit price is an amount proposed and stated on the Bid Form as a price per unit of measurement based on the measured quantities for materials and/or services.
4. Additional work may be required during the progress of the project primarily due to changing conditions. A Change Order will be issued to the CONTRACTOR by the OWNER or ENGINEER for additional work which the OWNER considers necessary. It will be the responsibility of the CONTRACTOR to request additional time to be added to the Contract Time Period for any work added to the project by Change Order.
01025 - 3
5. The OWNER reserves the right to reject the CONTRACTOR's measurement of work in place that involves use of established unit cost Bid Form prices, and to have this work measured by an independent surveyor at the OWNER’s expense.
1.5 MEASUREMENT AND PAYMENT
A. Measurement of an item of the Work will be by the unit as indicated on the Bid Form.
Payment of an item of the Work will be made by the unit price times the number of units or quantities as indicated on the Bid Form.
B. Measurement and payment for an item will include all necessary and incidental work not specifically described or specified as a part of the Bid Form item on the Bid Form to which it is related.
C. Unless otherwise stated in individual sections of the Specifications or in the Bid Form, no separate payment will be made for any item of the Work, materials, parts, equipment, supplies or related items that are required to perform and complete the Work. The costs for all items required shall be included in the Bid Form price item in the Bid Form of which it is a part.
D. The Total Base Bid shall constitute full compensation to the CONTRACTOR for furnishing all plant, labor, equipment, tools and materials, and for performing all tasks to complete all the Work. The Work shall be complete in place, functional as intended, as specified and as indicated on the Drawings.
E. The CONTRACTOR’S mobilization, demobilization, General Conditions and Supplementary Conditions shall be included in the Total Base Bid and the line item to which it is related.
F. CONTRACTOR shall locate all utilities prior to excavation. Utility location shall not be paid for separately and shall be included in the unit price(s) to which it pertains.
G. All CONTRACTOR Health and Safety provisions to perform the work will not be paid for separately and shall be included in the Bid Form prices stipulated for the lump sum and unit price pay items.
H. Monthly Payment Applications for lump sum or unit price items in progress shall be based on the percent complete of the item at the end of each month as determined by the ENGINEER. By the 20th of each month, the CONTRACTOR is responsible for providing the ENGINEER with records of construction that has occurred during the month and a DRAFT payment application. The ENGINEER will consider the information provided by the CONTRACTOR and other information as necessary before making a determination on the percent complete of each item for the month. The CONTRACTOR’S monthly FINAL payment application is due by the 25th of each month
01025 - 4 and should reflect the percent complete for each item as determined by the ENGINEER minus any retainage.
1.6 VALUES OF UNIT PRICES
A. The number of units or estimated quantities on the Bid Form is approximate only, and final payment will be made for the actual number of units and quantities incorporated in the Work or made necessary to complete the project.
B. In the event that Work, and materials or equipment are required to be furnished to a greater or lesser extent than is indicated on the Bid Form, such work and materials or equipment shall be furnished in greater or lesser quantities at the Bid Form unit price on the Bid Form.
1.7 CHANGES AND EXTRA WORK
Changes and extra work will be measured and paid for in accordance with the requirements of this Section. It will be the responsibility of the CONTRACTOR to request additional time to be added to the Contract Time Period for any work added to the project by changes.
1.8 REJECTED MATERIALS
Quantities of material wasted or disposed in a manner not called for in the Specifications;
rejected loads of material, including material rejected after it has been placed by reasons of the failure of CONTRACTOR to conform to the provisions of the Specifications; material not unloaded from transporting vehicles; material placed outside the limits indicated by the Drawings or established by OWNER; or material remaining on hand after completion of the Work, will not be paid for, and such quantities will not be included in the final total quantities.
No compensation will be made for loading, hauling, and disposing of rejected material.
1.9 SPECIAL REQUIREMENTS
N/A
1.10 MEASUREMENT AND PAYMENT DESCRIPTIONS
The following narrative is a summary of the Work required to complete the project. The tabulation does not name every item and incidental but does include descriptions of the major Work items needed to complete the project. Providing this list of items does not relieve the CONTRACTOR of his duty to complete the Work as intended and provide a fully functional project.
Measurement and payment items are listed below for the items in the Bid Form.
01025 - 5
A. General
1. Mobilization & General Conditions
Measurement – No separate measurement will be made for this item.
Payment - Payment for Mobilization shall be made at the unit price found on the Bid Form. Payment shall be full compensation for the preparatory work and operations in mobilizing for the commencement of the Work including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for any other pre-construction expenses necessary for the start of the Work, regardless of how many times such moves are made. The item shall also include all costs to clean the site and demobilize.
Fifty percent (50%) payment may be requested on the first pay request, twenty-five percent (25%) may be requested at 50% of project completion, and twenty-five percent (25%) may be requested at completion of demobilization and site cleanup to the satisfaction of the OWNER and
ENGINEER.
Mobilization and General Conditions shall also include providing insurance;
permits; permit compliance; utility services; time and materials for meetings;
sanitary facilities; CONTRACTOR's temporary field office(s); security;
construction photographs; licensures; taxes; site clean-up and demobilization.
The amount of this item may not exceed six (6) percent of the Total Base Bid.
2. Performance Bond
Measurement-Measurement of this item will not be made for payment. All work related to this item shall be included in the unit price found on the Bid Form.
Payment-Payment for Performance Bond shall be full compensation for the preparatory work, bond attainment, copies of bond provided to OWNER or ENGINEER, and potential renewal of said bond.
The CONTRACTOR will be paid one half (50%) of the lump sum price at the initiation of mobilization and the remainder of the lump sum price at the completion of demobilization and site cleanup to the satisfaction of the OWNER or ENGINEER. Bond must be current at project completion for full payment.
01025 - 6
3. Payment Bond
Measurement-Measurement of this item will not be made for payment. All work related to this item shall be included in the unit price found on the Bid Form.
Payment-Payment for Payment Bond shall be full compensation for the preparatory work, bond attainment, copies of bond provided to OWNER or ENGINEER, and potential renewal of said bond.
The CONTRACTOR will be paid one half (50%) of the lump sum price at the initiation of mobilization and the remainder of the lump sum price at the completion of demobilization and site cleanup to the satisfaction of the OWNER or ENGINEER. Bond must be current at project completion for full payment.
B. Surveying
1. Construction Surveying
Measurement - Measurement of the work under this item will not be made for payment. All items shall be included in the unit price found in the Bid Form.
Payment - Payment will be made to CONTRACTOR for the Total unit price found in the Bid Form and will include all costs to perform pre-construction surveys, stake-outs, surveys to complete quantities, intermediate surveys, surveys for grade, preparation of grading materials, surveys to document as-built conditions, and the preparation of Record Drawings. One-quarter of the Lump Sum survey payment will be made upon completion and verification by the CQA ENGINEER that all the pre-construction surveys and stake-outs meet the requirements of the specifications. The remaining three-quarters of the Lump Sum payment will be made upon the completion and the CQA ENGINEER’s verification that the as-built survey and Record Drawings meet the requirements of these specifications and the CQA Plan.
2. Marker Posts
Measurement - Measurement shall be by the actual quantity installed.
Payment - Payment shall be at the Bid Unit Price shown on the Bid Form.
C. Site Preparation
1. Clearing and Grubbing
Measurement - Measurement will be made horizontally by the acre of the area cleared and grubbed.
01025 - 7
Payment - Payment will be at the unit price per acre in the Bid Form and shall include all labor, materials, and proper disposal of debris and/or shaping/use of cleared material to construct brush barriers around the perimeter of the project, as allowed by Owner.
2. Tack-On Stormwater Diversion Berm
Measurement – Measurement shall be by the linear foot from end to end along the center line of the top of the berm.
Payment – Payment shall be at the Unit Price in the Bid Form and includes all labor, materials, soil excavation, haul, placement, fine grading, double-sided channel matting, single-sided slope matting, seeding and maintenance throughout construction.
3. Strip and Stockpile Topsoil (Not Used)
Measurement - Measurement for Topsoil Strip and Stockpile shall be made horizontally by the acre of the area of topsoil actually stripped.
Payment - Payment shall be made at the unit price in the Bid Form and shall include all labor, materials, stockpiling, haul, erosion control of stockpile, and re-spreading topsoil on all borrow areas to be grassed.
D. Earthwork
1. Contracted Excavation (Unclassified)
Measurement - Unclassified Excavation shall consist of all the excavated material for (1) clay liner subgrade, (2) road subgrade, or (3) other structural subgrade. Unclassified excavation shall also include the subsequent placement as structural fill of all material above the subgrades whether into embankments, disposal, or stockpiling in designated areas of all material, regardless of its nature or the manner in which it is removed from existing grade to the subgrade placement. Unclassified excavation shall include all processing and compaction required by the project specifications.
Measurement shall be made by of in-place material from topographic surveys performed before and after the work.
Payment - Payment shall be for the cubic yard unit price stated on the Bid Form for “Contracted Excavation”. No payment will be made for undercut excavation performed prior to approval by the CQA ENGINEER. Additionally, no payment shall be made for over excavation of unsuitable materials and no payments shall be made for excavation of unsuitable material volumes filled prior to inspection by the CQA ENGINEER.
01025 - 8
2. Unsuitable Material (Remove and Replace)
Measurement - Areas requiring undercutting due to being unsuitable as determined by the CQA ENGINEER shall be measured in the presence of the CQA ENGINEER. Undercut excavation shall include the subsequent placement of all suitable fill material required to replace undercut material.
Measurement shall be of in-place material.
Measurement will be made as the difference in topographic conditions before the unsuitable material is removed and the “as constructed” conditions established according to the construction requirements of Section 02210- Grading. Measurement shall be in cubic yards.
Payment - Payment shall be for the cubic yard unit price stated on the Bid Form for unsuitable material. No payment will be made for undercut excavation performed prior to approval by the CQA ENGINEER. Additionally, no payment shall be made for over excavation of unsuitable materials and no payments shall be made for excavation of unsuitable material volumes filled prior to inspection by the CQA ENGINEER.
3. Solid Rock Excavation (Not Used)
Measurement - Areas requiring rock excavation shall be measured in the presence of the CQA ENGINEER. Only non-rippable rock will be considered rock excavation. Non-rippable rock is defined as rock that cannot be ripped using a single tooth ripper mounted on a D-8 dozer, making three (3) passes in perpendicular direction and producing less than 0.5 cubic yards of loosened rock.
Payment - Payment shall be by the cubic yard unit price on the Bid Form (as applicable).
No payment will be made for rock over-excavation or boulders. Boulders shall be defined as rock if more than 1.0 cubic yards in volume.
4. Structural Fill from Borrow Area
Measurement - Measurement shall be made using quantity or as-built surveys and shall represent the in-place quantity after compaction, not the amount of material taken out of the borrow area. Measurement shall be in cubic yards.
Payment - Payment shall be at the unit price in the Bid Form and shall include all equipment, labor, tools, testing, and incidentals to load, haul, place, compact and fine grade borrow area soils from an area designated by the OWNER to the Project area. This item is included in the event there is not sufficient material from excavating at the Project area.
01025 - 9
E. Clay Liner
1. 24” Thick Compacted Clay Liner (k < 1.0 x 10-7 cm/sec)
Measurement - Measurement shall be made by survey in square feet with the quantity for payment being the three-dimensional surface area of the flexible membrane liner times 2 feet over the area covered by Compacted Clay Liner computed by the Confirmation Surveyor.
Clay liner placed beyond the limits of the lines and grades as shown on the Drawings will not be accepted and must be removed, if directed by the ENGINEER, at the CONTRACTOR’S expense.
The entire Clay Liner must meet or exceed the specified thickness, density and permeability requirements prior to payment. The CONTRACTOR must maintain the Clay Liner until the CQA ENGINEER has verified that the minimum thickness and permeability requirements have been met and the 60-mil textured geomembrane liner has been completely deployed.
Payment - Payment shall be by the cubic yard unit price on the Bid Form.
F. Geosynthetics
1. 60 Mil Textured HDPE Geomembrane Liner
Measurement - Measurement shall be by the three-dimensional area, in square feet, of the geomembrane liner as measured by the confirmation surveyor. Geomembrane liner shall be measured to the upper inside corner of all anchor trenches or the limit of geomembrane liner run-out (edge of liner) where no anchor trench is shown.
All testing, patches, repairs, material in the anchor trenches, waste, overlap, and material beyond the required pay limits will be considered incidental to the construction and will be excluded from payment.
Payment - Payment shall be at the unit price in the Bid Form. No payment shall be made until liner is completely installed and the installation is verified by the CQA ENGINEER.
2. Rain Flap Berms (Construct Only)
Measurement- Measurement shall be made by the linear foot along the top of the rain flap installed.
Payment – Payment shall be at the Unit Price on the Bid Worksheet and shall include materials (other than Rain Flap material), equipment, labor and incidentals to construct the full rain flap berm as shown in the Drawings. HDPE
01025 - 10 geomembrane liner material for rain flap and welding to base liner is to be completed by CONTRACTOR.
3. Permanent Anchor Trench
Measurement – Measurement shall be made by the linear foot for the length of trench actually installed.
Payment – Payment shall be at the Unit Price on the Bid Worksheet and shall include opening and backing of trench and all incidentals.
4. Temporary Edge of Liner Protection
Measurement – Measurement shall be made by the linear foot for the actual length of temporary edge of liner installed.
Payment – Payment shall be at the Unit Price on the Bid Worksheet and shall include pressure treated plywood, anchoring the HDPE geomembrane as shown in the Drawings, and all incidental materials and labor to protect the temporary edge of liner.
5. Double Sided Geocomposite Drainage Media (GDM)
Measurement - Measurement shall be made by survey in square feet with the quantity for payment being the three-dimensional surface area of the geocomposite as computed by the Confirmation Surveyor.
All testing, patches, repairs, waste, overlap, and material beyond the required pay limits will be considered incidental to the construction and will be excluded from payment.
Payment - Payment shall be at the unit price in the Bid Form.
6. Reinforced Geosynthetic Clay Liner (GCL) (Not Used)
Measurement - Measurement shall be by the horizontal surface area, in square foot, of the installed area of the GCL. Pay limits shall be measured to the upper inside corner of all anchor trenches or the limit of the installed geosynthetic clay liner.
All testing, patches, repairs, material in the anchor trenches, wastes, overlap, and material beyond the required pay limits will be considered incidental to the construction and will be excluded from payment. All materials and work required of the CONTRACTOR for excavation, backfill, and compaction of the anchor trenches are also considered incidental to the installation and will also not be included as pay items.
01025 - 11
Payment - Payment shall be at the unit price in the Proposal. No payment shall be made until the GCL is completely installed and its installation verified by the CQA ENGINEER.
G. Leachate Collection System
1. 8-inch Dia. Perforated, SDR 11 HDPE Pipe
Measurement - Measurement shall be by the linear foot measured along the centerline of the pipe.
Payment - Payment shall be at the unit price on the Bid Form and shall include all stone, filter geotextile fabric, all cushion geotextile fabric, ASTM No. 57 stone filter, 8-inch dia. perforated SDR 11 HDPE, fittings, contractor surveying, and all incidental materials and labor.
2. 8-inch Dia. Solid SDR 11 HDPE Leachate Pipe
Measurement - Measurement shall be by the linear foot measured along the centerline of the pipe.
Payment - Payment shall be at the unit price on the Bid Form and shall include all pipe, fittings, contractor surveying, and all incidental materials and labor.
3. Leachate Cleanout
Measurement - Measurement shall be the quantity actually installed.
Payment - Payment shall be at the unit price on the Bid Form and shall include caps, fittings, stainless steel, back-up rings, nuts, bolts, washers, any support structure or soil required to support the cleanout, bollards and all incidental materials and labor.
4. Leachate Penetration Assembly
Measurement - Measurement of this item shall not be made.
Measurement – Measurement shall be the quantity actually installed for complete assembly as shown on the Plans.
Payment - Payment shall be at the unit price in the Bid Form and shall be complete including 2 - 24" dia. HDPE SDR-11 Riser with 8'x8'x2" HDPE Flat Stock Plate, connector pipe, ASTM No. 57 Stone, ASTM No. 89 stone filter, filter geotextile, and 24 OSY Cushion Geotextile. The sump assembly shall be required to be constructed by a manufacturer which meets the requirements of an HDPE fabricator listed in this specification.
Payment – Payment shall be at the Unit Price in the Bid Worksheet.
01025 - 12
5. Duplex Submersible Leachate Sump Pump System (Not Used)
Measurement - Measurement of this item shall not be made.
Payment - Payment shall be at the lump sum in the Bid Form and shall include a duplex pumping system, as detailed and specified, with each unit containing wheeled sump drainer, pump, motor, controls, control panel, discharge pipe, junction boxes, mounting, flowmeter, and all incidental materials and labor.
6. 4” x 8” Dia. Dual Contained Leachate Force Main (Not Used)
Measurement - Measurement shall be linearly along the centerline of the piping.
Payment - Payment shall be at the unit price in the Bid Form and shall include slip lining (if required), bedding, backfill, trenching, double walled pip, fittings, thrust blocks, welding, contractor surveying, all required testing per the Specifications, and all incidental materials and labor.
7. 18” Dia. Steel Casing for Force Main (Not Used)
Measurement - Measurement shall be linearly along the centerline of the steel encasement piping
Payment - Payment shall be at the unit price in the Bid Form and shall include bedding, backfill, trenching, fittings, thrust blocks, CONTRACTOR surveying, all required testing per the Specifications, and all incidental materials and labor.
8. Leachate Force Main Air Release Valve Vault (Not Used)
Measurement - Measurement shall be made by the actual quantity installed.
Payment - Payment shall be at the unit price in the Bid Form and shall include supports, fittings, bollards, access hatch, foundation stone, all required testing per the Specifications, and all incidental labor and materials as detailed on the Drawings.
H. Liner Protection
1. Native Soil Protective Soil Cover
Measurement - Measurement shall be made by survey in square feet with the quantity for payment being the three-dimensional surface area of the flexible membrane liner times 2 feet over the area covered by Protective Soil Cover computed by the Confirmation Surveyor.
01025 - 13
Protective Soil Cover placed beyond the limits of the lines and grades as shown on the Construction Drawings will not be accepted and must be removed, if directed by the ENGINEER, at the CONTRACTOR's expense.
The entire Protective Soil Cover must meet or exceed the specified thickness, gradation and permeability requirements prior to payment.
Payment - Payment will be made for Protective Soil Cover at the cubic yard unit price on the Bid Form and shall include all required material, testing, screening, haul, placement, and maintenance of surface until final approvals.
I. Site Improvements/Stormwater Management
1. Construction Exit
Measurement - Measurement shall be by the actual quantity installed.
Payment - Payment shall be at the unit price on the Bid Form and include all labor, stone, and geotextile fabric as detailed in the Drawings.
2. Temporary Grassing
Measurement - Measurement shall be horizontally by the acre for areas actually seeded. Mulch installed for temporary seeding is not measured separately.
Payment - Payment shall be at the unit price on the Bid Form and shall include all labor, mulch, seed, and seed bed preparation.
3. Permanent Grassing
Measurement - Measurement shall be made horizontally by the acre.
Payment - Payment shall be by the unit price in the Bid Form and shall include all fine grading and shaping, seed, seed bed preparation, mulching, fertilizer, and all incidentals for obtaining a complete stand of permanent grass.
Payment will be made only upon establishment of a complete stand of grass as defined in the specification section.
4. Silt Fence (Type C)
Measurement - Measurement shall be measured linearly from end-to-end along its base of each separate installation actually installed.
Payment - Payment shall be at the unit price on the Bid Form and shall include all labor, materials, and maintenance throughout the construction project.
01025 - 14
5. Excelsior Matting (Slope Stabilization) (Not Used)
Measurement - Measurement of Excelsior Matting for slope stabilization shall be measured horizontally by the square yard for slope actually lined.
Payment - Payment shall be at the unit price in the Bid Form and includes all labor, materials, shaping, and maintenance.
6. Grass Lined Ditch with Double-Sided Excelsior Matting
Measurement - Measurement for installed grass lined ditch with excelsior matting shall be measured along the length of the center line of the excelsior lined ditch in linear feet for ditch actually lined.
Payment - Payment shall be at the unit price in the Bid Form and includes all labor, materials, and shaping.
7. Geosynthetic Lined Ditch (Turf Reinforcement Matting (TRM))
Measurement - Measurement for installed TRM lined ditch shall be measured along the length of the center line of the ditch in linear feet for ditch actually lined.
Payment - Payment shall be at the Unit Price in the Bid Worksheet and includes all labor, materials, shaping and maintenance.
8. Stone Check Dam
Measurement - Measurement shall be of the actual quantity installed.
Payment -Payment shall be at the unit price on the Bid Form and includes all labor and materials, stone, geotextile fabric and maintenance as detailed in the Drawings.
9. Concrete Drop Inlet
Measurement – Measurement shall be made by the actual quantity installed.
Payment – Payment shall be made at the unit price on the Bid Form including structures, bedding, fittings and all incidental material and labor as detailed in the Drawings.
10. Inlet Protection
Measurement – Measurement shall be made by the actual quantity installed.
01025 - 15
Payment – Payment shall be at the Unit Price on the Bid Form and includes all steel posts, washed stone, hardware cloth, labor and materials, and incidentals for the installation and maintenance as detailed in the Drawings.
11. 54” Corrugated Metal Pipe (CMP)
Measurement - Measurement shall be by the linear foot measured to and from centers of structures or ends of pipe along the centerline of the pipe, without regard to depth after installation has been completed.
Payment - Payment shall be by the unit price on the Bid Form and shall include all pipes, unloading, storing, surveying, testing, bedding, backfill, fittings, pipe accessories, pipe joint materials, and all labor, equipment, materials and incidentals. Where multiple pipes are required, payment shall include all pipes specified.
12. Reinforced Concrete Pipe (RCP) (Not Used)
Measurement - Measurement shall be by the linear foot measured to and from centers of structures or ends of pipe along the centerline of the pipe, without regard to depth after installation has been completed.
Payment - Payment shall be by the unit price on the Bid Form and shall include all pipe, unloading, storing, surveying, testing, bedding, backfill, fittings, pipe accessories, pipe joint materials, and all labor, equipment, materials and incidentals. Where multiple pipes are required, payment shall include all pipes specified.
13. Concrete Headwall
Measurement - Measurement shall be by the number of concrete headwalls actually installed.
Payment - Payment shall be by the unit price on the Bid Form and shall include connections to pipe, bedding, unloading, and all labor, materials and incidentals that are required.
14. Rip-Rap Outlet Protection (GDOT Type 1 & 3 as specified)
Measurement - Rip-rap for outlet protection and other areas shall be measured by the square yard of…