Addendum I.pdf

PDF 169 KB Posted

Attached to
26-044 Mountain Creek Road Maintenance Phase 2 Project
Solicitation number
PE-66098-NONST-2026-000000127
Issued by
Cobb County, Georgia

About this file

This is Addendum Number 1 to ITB #26-044 for the Mountain Creek Road Maintenance Phase 2 Project in Georgia, issued to all prospective offerors. The project encompasses the installation of Centrifugally Cast Concrete Pipe (CCCP) to replace approximately 90 linear feet of 60" Corrugated Metal Pipe (CMP), removal and installation of the downstream headwall, installation of stream bed protection in the downstream section, installation of black coated handrail, site grading, and erosion control. The Notice to Proceed (NTP) is scheduled to start in May 2026, with the ITB response due date of April 6, 2026 at 2:00 p.m. Prospective offerors are required to complete the addendum, obtain necessary signatures, and submit it with their ITB response by the stated deadline.

The engineer's budget for this project is in excess of $100,000. No Disadvantaged Business Enterprise (DBE) requirements or good faith efforts are associated with this project. The addendum serves as an acknowledgment form requiring offerors to provide company name, contact person, complete address information, phone, fax, email, signature, and date to confirm receipt and incorporation of Addendum Number 1 into their bid response.

View the file

Other files

File Type Posted
Notice_of_Intent_to_Award_(NOIA) (1).pdf PDF
26_044 Mountain Creek Road Maintenance Phase .pdf PDF
Addendum 2.pdf PDF
26_044 Bid Tabulation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum Number 1

ITB #26-044 Mountain Creek Road Maintenance Phase 2 Project

COMPLETE THIS ADDENDUM, SIGN and SUBMIT with the ITB

RESPONSE DUE DATE: April 6, 2026, 2:00 p.m.

To All Prospective Offerors: In reference to the ITB listed above, the following answers to questions, additions, deletions, and changes are hereby incorporated into the ITB:

Question Answer Q1. When will NTP start?

May 2026

Q2. What is the engineer's budget? In excess of $100k Q3. Can the Owner please confirm if there are any DBE Requirements or good faith efforts to complete for this project?

There are no DBE requirements associated with the project

I hereby acknowledge receipt of Addendum Number 1 for 26-044 Mountain Creek Road Maintenance

Phase 2 and have incorporated the changes into my response for the above-mentioned ITB

COMPANY NAME:

CONTACT PERSON:

ADDRESS:

CITY: _________________________________STATE: ___________ ZIP: ________________________

PHONE: ________________ FAX: _______________

EMAIL ADDRESS: ______________________________________

SIGNATURE: ____________________________________________

DATE: ______________________________________