This Addendum I document issued by the Florida Department of Agriculture and Consumer Services (FDACS) provides clarifications and answers to written questions submitted regarding Invitation to Bid (ITB) GS 25 26 48 for New Boardwalk Construction Services at Myakka State Forest in Englewood, Florida. The addendum addresses 15 questions related to project specifications and requirements, including permit responsibilities, bid evaluation methodology, signage and layout provisions, splice block details, material substitutions, and construction procedures. The response due date for the original solicitation is January 29, 2026, with a bid opening scheduled for January 30, 2026. The contractor must complete all construction and punch list items by August 31, 2026, as specified in the addendum's response to the anticipated construction duration question.
Key clarifications in the addendum establish that the contractor is responsible for obtaining all relevant permits except for the Environmental Resource Permit and USACE clearance letter already secured by the Department. The Department will provide signage for installation and design plans that serve as the surveyed layout guide for the boardwalk and parking area. Material specifications require Type 316 stainless steel for all exterior and exposed hardware unless otherwise noted, with galvanized hardware acceptable only where explicitly identified on structural drawings. For pile installation, both minimum embedment depth of 10 feet and practical refusal criteria (20 blows per inch or less than 1-inch penetration) must be satisfied, with any deviations requiring engineer approval. The Department will provide one kiosk at the boardwalk start, and as-built plans are not required upon completion. Where specific materials are unavailable, contractors may propose Department-approved comparable substitutions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB GS 25 26 48_Final.pdf | ||
| EXHIBIT A.pdf | ||
| APPENDIX I - Design Plans.pdf | ||
| EXHIBIT A.pdf | ||
| APPENDIX I - Design Plans.pdf | ||
| APPENDIX II - Maps.pdf | ||
| ITB GS 25 26 48_Final.pdf | ||
| Addendum I.pdf | ||
| APPENDIX I - Design Plans.pdf | ||
| ITB GS 25 26 48_Final.pdf | ||
| APPENDIX II - Maps.pdf | ||
| EXHIBIT A.pdf | ||
| Addendum II - Timeline Revision.pdf | ||
| APPENDIX II - Maps.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum Date: January 21, 2026
Addendum Number: 1
Solicitation Number: ITB GS 25 26 48
Solicitation Title: New Boardwalk Construction Services - Myakka State Forest
Response Due Date: January 29, 2026
Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes, or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Protests must be filed with the Department’s Agency Clerk. Filings may be made physically at:
Florida Department of Agriculture and Consumer Services The Holland Building 600 South Calhoun Street Tallahassee, Florida 32399
Please be advised that the information contained on the next page is applicable to the original specifications of the above referenced solicitation.
All questions regarding this Addendum should be submitted in writing to the Procurement Officer at Bids@FDACS.gov or contact the Procurement Office at (850) 617-7181.
This Addendum includes the following changes:
Change No. 1:
This Addendum provides the Department’s answers to written questions received by the deadline in the above-referenced solicitation.
[REMAINDER OF PAGE INTENTIONALLY LEFT BLANK]
mailto:Bids@FDACS.gov
RESPONSES TO WRITTEN QUESTIONS
ADDENDUM NUMBER: 1
SOLICITATION NUMBER: ITB GS 25 26 48
SOLICITATION TITLE: New Boardwalk Construction Services - Myakka State Forest
Question Number Question Answer
What permits will be required for the contractor to obtain?
The contractor is responsible for obtaining all relevant permits to fully complete this project.
The Department has obtained an Environmental Resource permit from the Southwest Florida Water Management District. And the Department obtained a letter from United States Army Corps of Engineers (USACE) stating that a USACE-issued permit is not required.
2 Will the award of the contract be based on the base bid only or the combination of base bid and alternate bid?
Please refer to Section 4.19 – BASIS OF AWARD of this ITB, located on page 13.
3 Will the State be providing signage to the contractor for installation, or is the contractor responsible for obtaining? If so, how do we know the size of the sign and information required?
The Department’s Florida Forest Service will provide the signage and future installation. The contractor will use the design plans as a guide for providing the appropriate locations of mounting material.
4 Will the State be providing the surveyed layout of the boardwalk and parking area? Please refer to APPENDIX I – DESIGN PLANS.
5 Will there be required Asbuilt Plans to be done by the contractor upon completion?
No. The contractor is not required to provide Asbuilt Plans at the completion of the project.
Do you have details on the size of splice blocks needed for the interior joists and how they will be attached?
Interior joist splices shall be constructed using full-depth splice blocks matching the joist size, installed tight to the joint and fastened to each adjoining joist in accordance with AWC NDS-2023 requirements for wood-to-wood structural connections.
No separate splice detail is provided, as these connections are considered conventional wood framing governed by the General Structural Notes and applicable code standards. Contractor shop drawings shall indicate splice configuration and fastening for Engineer review prior to installation.
Confirm bid bond requirements. Please refer to Sections 4.13 – BID BOND GUARANTEE and 4.14 – BOND
REQUIREMENTS of this ITB, located on page 11.
8 Can approved substitutions be made for the guardrail cap material? The current 2x8 WEARDECK profile is not available.
Where the specific materials from the design plan are not available, the contractor may use a Department-approved comparable substitution.
Can you confirm the number of kiosks to be included?
Please refer to the Department’s answer to Question #4.
There is only one kiosk at the start of the boardwalk. This is different from the mountings for signage mid-walk and at the observation deck.
Is galvanized hardware acceptable?
The default hardware material for this project is stainless steel.
• All exterior and exposed hardware shall be Type 316 stainless steel, unless specifically noted otherwise on the plans.
• Galvanized structural bolts and hardware are acceptable only where explicitly noted on the structural drawings or details.
References to galvanized hardware apply only to those locations where such hardware is clearly identified. Where stainless steel is required, it shall govern.
Are locking nuts required?
Lock nuts are not required unless specifically noted on the plans. Standard hex nuts with flat washers are acceptable, provided all bolted connections comply with applicable ASTM standards and AWC NDS-2018, including minimum thread projection beyond the nut.
Locking nuts may be used as an acceptable alternate, provided material compatibility and corrosion resistance requirements are maintained.
What is the required procedure if minimum embedment is achieved but the required resistance is not met?
Pile installation shall satisfy both of the following requirements:
1. Minimum embedment depth shown on the plans (10'- 0" minimum), and
2. Practical refusal, defined as 20 blows per inch or less than 1-inch penetration, with rebound less than 1/4 inch per blow.
If practical refusal is encountered prior to achieving minimum embedment, or if minimum embedment is achieved without meeting refusal criteria, pile installation shall cease, and the condition shall be reported to the Engineer of Record.
Any corrective action (continued driving, pre-drilling, alternate installation method, or modification) shall be engineer-directed. Field adjustments without Engineer approval are not permitted.
13 Please clarify the anticipated duration of construction and whether bidders should assume a reasonable construction period upon issuance.
The Construction period must be completed (along with punch list items) and a final invoice submitted by August 31, 2026. This is due to our funding timeline.
Please confirm required insurance coverage. Please refer to section 5.15 – INSURANCE REQUIREMENTS of this ITB, located on page 19.
Please confirm whether standard marine-grade timber piles treated with CCA 2.5 pcf is acceptable.
Please refer to the Department’s answer to Question #4.
Contractor should adhere to the design plans as closely as possible when considering materials. If specific materials from the design plan are not available, the vendor may use a comparable substitution.