Addendum Eight.pdf
PDF 176 KB Posted
- Solicitation number
- RFB 785 2500000645 16
- Issued by
- Harrison County, Kentucky
About this file
This is Addendum Eight to Invitation to Bid No. RFB-235-25 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for the Upper Guide Wall Repairs Project at Kentucky River Locks 2 & 3 in Henry County, Kentucky, managed by the Kentucky River Authority. The addendum, dated July 25, 2025, addresses clarification regarding the project schedule, construction season parameters, and weather-related delays. The project establishes a construction season designated as July 1 through November 30 annually, during which high-water event delays will be considered for schedule extensions. Contractors are permitted to work outside the specified construction season from December 1 through June 30, though project adjustments will not be accepted for high-water conditions during this period.
Liquidated damages will be assessed based solely on the established adjusted Substantial Completion date and are not tied to construction season parameters. Contractors will receive extension of time only for delays caused by weather and flooding, with no adjustments to contract price considered for either river level conditions or general conditions adjustments. The Owner intends to establish the Completion Date between July 1 and November 30 to avoid liquidated damages assessments outside the construction season. Schedule extension requests must comply with Article 16 of the General Conditions and the Special Conditions regarding Temporary Shutdowns and Elevated Water Levels. Contractors remain responsible for site protection and security at all times, regardless of whether work is occurring during or outside the construction season.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-235-25
FOR: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky
DATE: July 27, 2025
RFB-785-2500000645
ADDENDUM NO. Eight (8)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-235-25 For: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky
Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration
ADDENDUM NO. Eight (8)
Date: July 25, 2025
RFB – 235-25
Item 1: Question and answer listed below:
Question 1: If weather and flooding delays cause the contractor’s schedules to push outside of
“construction season” (July 1 – November 30) prohibiting the contractor from starting work again until the following July 1st date, will liquidated damages be charged for the days in between or will the construction schedule be paused?
Response: No. Liquidated damages will be computed based only on the established, adjusted
Substantial Completion date. Liquidated damages are not tied to the “construction seasons” as specified.
For clarity:
• The Contractor is not prohibited from working outside the specified dates of the Construction Season. Work is allowed December 1 through June 30, although project adjustments will not be accepted for high-water conditions during this time.
• The Owner will not consider adjustments to the Contract Price based on river levels, regardless of dates (Refer to Article 4, Temporary Shutdowns/Elevated Water Levels of the Special Conditions).
• If the Work is delayed, only an extension in time will be granted. No adjustments to the Contract Price will be considered for the General Conditions.
• Requests for schedule extensions shall adhere to the requirements outlined in Article 16 of the General Conditions and the Special Conditions - Temporary Shutdowns/Elevated Water Levels.
• Schedule extensions due to high river levels will be considered by the Owner ONLY for high water events that occur during the Construction Seasons (July 1 – November 30 annually).
• Liquidated damages will accrue only if substantial completion is not achieved by the established, adjusted date for completion, regardless of the dates.
• To avoid assessments of Liquidated Damages outside of the Construction Season, the Owner intends to establish a Completion Date between July 1 and November 30.
• The Contractor is responsible for protecting and securing the site(s) at all times, including dates outside the Construction Season (Refer to Article 14.3, Construction Sequence of the Special Conditions).