Addendum 4 - VSL Phase 1B Stages 4 and 5 Liner Construction Project~1.pdf

PDF 2 MB Posted

Attached to
Phase 1B Stages 4 and 5 Liner Construction Project at the Victorville Sanitary Landfill
Solicitation number
PWG126-SOLID-6322
Issued by
San Bernardino County, California

About this file

Addendum No. 4 to Phase 1B Stages 4 and 5 Liner Construction Project at Victorville Sanitary Landfill

This addendum modifies the bid documents for the Phase 1B Stages 4 and 5 Liner Construction Project at the Victorville Sanitary Landfill in Victorville, California, issued by San Bernardino County's Solid Waste Management Division. The project encompasses approximately 29 acres of composite liner system construction, including clearing and grubbing, unclassified excavation and fill operations, rock blasting (675,000 cubic yards), installation of leachate collection and removal system (LCRS) components, placement of HDPE geomembranes and geosynthetic clay liners, protective soil cover installation, and perimeter access road construction. The addendum revises the bid schedule (pages 22-1B through 22-3B), adds Item No. 70 for Anchor Trench Excavation and Backfill (2,850 lineal feet), modifies Item No. 14 for Screening (82,000 cubic yards), and updates Veneer Fill Material specifications. Sealed bids are due at 10:00 a.m. on April 2, 2026, with a mandatory pre-bid meeting and job walk held on March 17, 2026. Contract performance requires completion within 230 working days from Notice to Proceed, with two critical milestones: Sequence 1 (North Stage 4, approximately 16 acres) within 160 working days and Sequence 2 (South Stage 4, approximately 13 acres) within 230 working days. Liquidated damages of $6,000 per working day apply for failure to meet completion deadlines, with work anticipated to commence in June 2026.

The addendum clarifies that no fuel adjustment clauses or material price variation adjustments will be provided; all costs associated with diesel fuel, HDPE materials, and resin shall be included in unit and lump sum prices with no payment modifications during construction. The existing boulder stockpile referenced in the original specifications has been removed and is not expected to be relocated. Approved veneer fill material must be classified as SC or SC-SM with a plasticity index of 3 or greater, or an approved equivalent with sufficient cohesion to prevent dislodging during geosynthetics placement. LCRS Gravel is specified as an imported material due to technical specifications outlined in Section 2D of the Technical Specifications. Interface Shear Testing shall be performed per Section 2E, with testing frequency of one per 200,000 square feet or one per interface, whichever results in greater number of tests. The hard caliche layer requiring blasting is expected in the final 20-25 feet of excavation, corresponding to approximately 40 feet below original grade where excavation depths range from 0 to 65 feet. Bidders must submit the construction schedule prior to start of construction following contract award. Course of Construction/Installation (Builder's Risk) Property Insurance shall be based on the contractor's proposed bid amount. Attachment 2 provides the intended haul route and anticipated fill plan for reference, with contractors required to refer to Sheet C9 of the Plans for all other construction notes and details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SAN BERNARDINO COUNTY

SOLID WASTE MANAGEMENT DIVISION

222 West Hospitality Lane, 2nd Floor San Bernardino, CA 92415-0017

Fax: 909-386-8900

ADDENDUM NO. 4

TO THE PLANS AND BID DOCUMENTS FOR THE

PHASE 1B STAGES 4 AND 5 LINER CONSTRUCTION PROJECT

at the VICTORVILLE SANITARY LANDFILL in Victorville, California

March 30, 2026

BID OPEN: 10:00 A.M. April 2, 2026

The following changes and/or additions shall be made to the Plans and Bid Documents for the Phase 1B Stages 4 and 5 Liner Construction Project at the Victorville Sanitary Landfill. All other requirements of the Plans and Bid Documents shall remain the same.

The following changes shall be made part of the Contract Documents, and the Bidder should acknowledge receipt thereof on the Bid Proposal.

I. SPECIAL PROVISIONS

1. BID SCHEDULE, delete and replace in its entirety Bid Schedule Pages 22-1A thru 22-3A with the Bid Schedule Pages 22-1B thru 22-3B included in this Addendum No. 4 as Attachment 1. Bids must be submitted on these sheets or will be deemed non-responsive.

2. Section 2C – Earthwork, Section 4 – Measurement and Payment, add Item 4.13 with the following:

“4.13 ANCHOR TRENCH EXCAVATION AND BACKFILL (PER DETAILS

1/C17, 2/C17, 5/C17, AND 6/C17) – ITEM NO. 70

The contract unit price paid per lineal foot for Anchor Trench Excavation and Backfill shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in Anchor Trench Excavation and Backfill for the northerly, easterly, and southerly typical geosynthetic termination anchor trenches including all excavation, grading, 3” minus backfill, compaction, and other appurtenances as shown on the plans, as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer. Intermediate Anchor Trench on the westerly Portion shall be paid for separately and per Bid Item 35.

Final pay quantities shall be determined by computing the actual lineal footage of Anchor Trench Excavation and Backfill placed to the limits indicated on the Plans.

Geosynthetics placed in the Anchor Trench to the Pay Limit will be included in respective geosynthetic material Bid Item(s). The proposed “notch” at the northerly, easterly, and southerly top bench/road terminations shall be included in the Excavation to Stockpile bid items for subgrade establishment/preparation and shall be considered incidental thereto. Anchor Trench Excavation and Backfill placed beyond those limits will not be compensated unless previously authorized by the Engineer.”

3. Section 2C – Earthwork, Section 4 – Measurement and Payment, delete and replace Item 4.7 with the following:

“4.7 Screening – Item No. 14

The contract unit price paid per cubic yard of Screening shall include full compensation for furnishing all labor, tools, equipment, and incidentals and for doing all work involved in Screening, including processing, screening, and stockpiling of oversized material to the stockpile 2 area, as shown on the Plans, as specified in the Standard Specifications and these Technical Specifications, and as directed by the Engineer.

Final pay quantities will be based on the in-place compacted volumes of screened/engineered fill materials generated for the project including Bid Item 16 Compacted/Screened 1-inch Minus Material on Floor, Bid Item 17 Veneer Fill Placement – Slopes, Bid Item 26 PSC Base, Bid Item and 39 thru 41 PSC Various Locations, as determined by pre- and post- item installation as-built survey (square foot * depth) or volumetric analysis (cubic yard) per respective bid item. Screening completed beyond the tolerances indicated in the Technical Specifications, or limits indicated on the Plans will not be compensated unless previously approved by the Engineer.”

4. Section 2C – Earthwork, Subsection 2.8 – Veneer Fill Material, Paragraph 3, delete and replace with the following:

“These provisions, for allowing incorporation of rock or rock fragments within the fill shall not relieve the Contractor of the responsibility to prepare the final subgrade surface for geosynthetic installation in accordance with other provisions of these Technical Specifications. Approved Materials include screened on-site native material from the Unclassified Excavation or if imported the material shall be classified as SC or SC-SM with a plasticity index of 3 (or greater) or an approved equivalent. Approved import material shall have enough cohesion to prevent dislodging/desiccation during geosynthetics placement.”

II. QUESTIONS

1. Will there be any clause for fuel and resin?

A1. No clause for diesel fuel or HDPE and Resin materials will be added to the bid documents. Bidders are advised that all costs associated with fuel and materials, including potential price variations, shall be included in the unit price and lump sum prices submitted with the bid. No payment adjustments will be made to such cost changes during construction.

2. Paragraph 2.7 of the Technical Specification refers to relocating an existing boulder stockpile to stockpile 2. What is the quantity of this boulder stockpile and how is this paid for?

A2. There is no existing rock stockpile expected to be moved within this project. It has since been removed by landfill operations and most recently County Flood Control District.

3. Paragraph 2.8 of the Earthwork Technical Specification titled Veneer Fill Material (Page 2C-5) has the following requirement: The Veneer fill material shall be classified as SC or SC-SM with a PI of 3 or greater. If the screened material does not yield a material that meets these requirements, how are we to proceed?

A3. Please refer to Special Provisions Revision No. 4 for clarification.

4. We are unable to locate the specification for the LCRS Gravel? Where do we obtain this material?

A4. LCRS Gravel is anticipated to be an imported material due to the specifications listed in Section 2D – LCRS, Lysimeter, and LFG Collection Systems Subsection

2.1 – Gravel of the Technical Specifications.

5. We have noted that there is no pay item for the Anchor Trench. Would it be possible to add this as a line item?

A5. Please refer to Special Provisions Revision No. 2 for added Measurement and Payment Item and Special Provisions Revision No. 1 for updated Bid Schedule reissued with this line item included in this Addendum No. 4.

6. The Blasting quantity indicated in the bid documents appears to be relatively high.

Please clarify the basis used to develop this quantity and provide any supporting calculations or assumptions.

A6. Based on the rippability investigation and air-track rotary drilling, an elevation/planar surface defining the blasting limit was developed. This surface was compared with the proposed subgrade elevations which established the blasting volume, which was ultimately increased to account for uncertainties.

7. Are there any Phase 2 Area biological concerns as it relates to the Probe work?

A7. SWMD is currently working with the regulatory agencies to obtain the final permits for the Phase 2 Area. Until permits are finalized, contractor should refer to the Plans and Technical Specifications to ensure proper buffers and protection is maintained for any nearby waters, habitat, wildlife, and other related environmentally protected resources.

8. Section 2.2.8 lists a total of 4-tests (2-dry and 2-soaked tests). Section 3.6.1 has a frequency of 1 per 200k sq ft or 1 per interface, whichever results in greater number of tests. If the engineer wants to follow section 3.6.1 and just using the GCL quantity, there could be a total of 28-sets of tests (instead of 4).

A8. Perform Interface Shear Testing per Section 2E – Geomembrane Subsection

2.2.8 – Interface Shear Testing.

9. Page 11, Section XVII in the Instruction to Bidders references a schedule to be submitted by the Contractor. Is this schedule to be submitted with the bid or once the job is awarded?

A9. Schedule will be submitted by awarded Bidder prior to the start of construction.

10. Due to the current volatile market in regards to Fuel, HDPE materials, and Resin pricing. Will the county entertain any compensation once project is underway if there are substantial increase in these materials, given the contractors have no control over?

A10. Please refer to answer provided to Question No. 1.

11. Based on discussions during the previous job walk, there was a mention of a new waste fill plan. We understand that current landfill waste operations have shifted in certain areas, which may impact proposed haul routes & construction logistics.

Could the county confirm that the haul routes indicated on the plans will not change however if so would it be possible to receive the updated waste fill plan to plan our haul routes accordingly.

A11. Please see Attachment 2 included in this Addendum No. 4 showing the intended haul route with the anticipated fill plan for reference only. Refer to Sheet C9 of the Plans for all other construction notes and details.

12. Based on the specifications, it is indicated that the last 20'-25' from design will be the harder caliche material that will require blasting however the geotechnical report states 40' from original grade. Which one supersedes the other?

A12. The harder caliche layer is expected in the final 20-25 feet of excavation. The geotechnical rippability report indicates blasting may be needed at about 40 feet below original grade. With excavation depths ranging from 0 to 65 feet, blasting at ± 40 feet below original grade corresponds to the final 20 to 25 feet above subgrade where caliche is encountered.

13. Please confirm the required limits for the Builder’s Risk coverage detailed in the Standard Contract, Section 5.3.2, Subsection E.

A13. The Course of Construction/Installation (Builder’s Risk) Property Insurance shall be based on the Contractor’s proposed bid amount.

If you have any questions, please contact Joshua LeRoy at (909) 386-8629 or you may contact me at (909) 386-9017.

Johnny Gayman, P.E. Date Engineering Manager

E4635 Johnny Gayman 2024

E4635 Text Box 03/30/2026

ATTACHMENT NO. 1

(BID SCHEDULE, Pages 22-1B thru 22-3B)

VICTORVILLE SANITARY LANDFILL

Const Note

Item No. Description QTY Unit Unit Price Item Total

- 1 Mobilization / Demobilization 1.0 LS

- 2 Construction Support Tasks 1.0 LS

- 3 Stormwater Compliance Tasks 1.0 LS

- 4 Construction Survey 1.0 LS

- 5 Waste Removal and Relocation 75,000 DLR $1.00 $75,000.00

- 6 Geoelectric Leak Location Survey 1.0 LS

Const Note

Item No. Description QTY Unit Unit Price Item Total

2, 4 7 Clearing, Grubbing, and Demolition (29 acres) 1.0 LS

- 8 Miscellaneous Site Work 1.0 LS

5 9 Unclassified Excavation/Transport to Stockpile 1 - Liner Cell Area 787,500 CY

5 10 Unclassified Excavation/Transport to Stockpile 2 - Liner Cell Area 335,000 CY

5 11 Unclassified Excavation/Transport to Stockpile 2 - Entrance Road Area 2,000 CY

5 12 Blasting 675,000 CY

5 13 Unclassified Excavation to Fill - Liner Cell Area 105,000 CY

5 14 Screening 82,000 CY

5 15 Daily Cover to Active Landfill Area 70,000 CY

9, 11, 13 16 Compacted/Screened 1-inch Minus Material on Floor 665,000 SF

9 17 Veneer Fill Placement - Slopes 550,000 SF

9 18 Subgrade Surface Preparation for Geosynthetics - Slope, Bench, and Access Roads 615,000 SF

14 19 Lysimeter Liner Section (Per Detail 3/C15) 12,500 SF

14 20 60-mil HDPE Encapsulation Geomembrane (Textured Both Sides) - Base 650,000 SF

14 21 Geosynthetic Clay Liner (GCL) - Base 650,000 SF

14 22 60-mil HDPE Geomembrane (Textured Both Sides) - Base 650,000 SF

14 23 Geotextile Fabric 12 oz/sy - Base 650,000 SF

14 24 LCRS Drainage Layer - Gravel 670,000 SF

14 25 Geotextile Fabric 8 oz/sy - Base 650,000 SF

PHASE 1B STAGE 4 AND 5 SUPPORT BID ITEMS

PROJECT SUPPORT BID ITEMS SUBTOTAL:

PHASE 1B STAGE 4 AND 5 CONSTRUCTION BID ITEMS

Page 22-1B

Const Note

Item No. Description QTY Unit Unit Price Item Total

14 26 Protective Soil Cover - Base 650,000 SF

29 27 Wrapped Gravel Infiltration Corridor (Per Detail 4/C16) 225 LF

15, 20 28 60-mil HDPE Encapsulation Geomembrane (Textured Both Sides) - Slope, Bench, and Access Roads 700,000 SF

15, 20 29 Geosynthetic Clay Liner (GCL) - Slope, Bench, and Access Roads 700,000 SF

15, 20 30 60-mil HDPE Geomembrane (Textured Both Sides) - Slope, Bench, and Access Roads 700,000 SF

15, 20 31 Geotextile Fabric 16 oz/sy - Slope, Bench, and Access Roads 700,000 SF

31 32 Drainage Geocomposite - Northwesterly Construction Bench (Per Detail 5/C15) 13,000 SF

16 33 Base to Slope Liner Transition 3,800 LF

21, 22 34 Westerly Bench Liner Join (Per Detail 3/C17) 5,000 LF

23 35 Intermediate Bench/Road Anchor Trench (Per Detail 3/C17) 1,750 LF

34 36 Slope Liner Join (Per Detail 4/C17) 290 LF

33 37 Base Liner Join - 1B Stage 3 to 1B Stages 4/5 (Per Detail 9/C16) 20 LF

24 38 Protective Plastic Cover and HDPE Geotextile Balllast (Per Detail 2/C15) 530,000 SF

6, 15, 20 39 Protective Soil Cover - Slope, Bench, and Cell Access Road 170,000 SF

32, 38 40 Protective Soil Cover - Easterly Access Road (Per Detail 1/C17) 90,000 SF

6 41 Protective Soil Cover - Gap Fill Area 4,000 CY

7 42 Native Unclassified Fill Above PSC - Westerly Bench and Gap Fill Area 13,250 CY

17 43 Liner Cell Access Road with Geotextile Underlay (Per Detail 7/C15) 20,000 SF

18 44 Road Edge K-Rail Concrete Barrier 195 LF

19 45 LCRS Header Pipe (Per Details 3/C15 and 7/C16) 2,100 LF

25 46 LCRS Lateral Pipe (Per Detail 8/C16) 4,100 LF

26 47 LCRS Pipe Junctions (Per Detail 1/C16) 12 EA

27 48 6" Solid HDPE LCRS Riser Pipe (Per Detail 2/C16) 1,950 LF

28 49 6" Slotted HDPE LCRS Access Road Collector (Per Detail 7/C15) 400 LF

53 50 LCRS Test Port Riser (Per Detail 10/C16) 315 LF

30 51 LCRS/LFG Bench Crossing (Per Detail 6/C15) 4 EA

35, 51 52 LCRS/LFG Riser Termination Support (Per Detail 6/C16) 22 EA

43, 54 53 Easterly and Southeasterly Perimeter Access Road Pavement Section (Per Details 1/C17 and 5/C17) 90,500 SF

44 54 Northerly Perimeter Access Road Pavement Section (Per Detail 6/C17) 12,000 SF

Page 22-2B

Const Note

Item No. Description QTY Unit Unit Price Item Total

51 55 Class I Flexible Post Delineator (Per Caltrrans Std. Plan A73C) 100 EA

46 56 AC Dike (Per San Bernardino County Std. Plan 117) 2,750 LF

47 57 AC Speed Bump (Per Detail 1/C13) 100 LF

48 58 Roadside Inlet Structure (Per Detail 4/C18) 1.0 LS

36, 52 59 24" CHDPE Below Grade Strom Drain 40 LF

35 60 60" Diameter CHDPE Below Grade Storm Drain - Line A (Per Detail 1/C18) 440 LF

38 61 Line A Inlet Structure (Per Detail 1/C12) 1.0 LS

39 62 Line A Outlet Structure (Per Detail 2/C12) 1.0 LS

40 63 Class III Rip Rap per SSPWC Sec. 200-1.6 6,000 SF

41 64 Class V Rip Rap per SSPWC Sec. 200-1.6 3,550 SF

EC1, EC2 65 Erosion Control / Final Stabilization 1.0 LS

55 66 Diversion Berm and Geomembrane Flap (Per Detail 3/C13) 525 LF

56 67 Temporary Diversion Berm and Geomembrane Flap (Per Detail 2/C13) 780 LF

- 68 Abandon Existing Gas Probe (Per Detail 1/5) (Deletable) 3 EA

- 69 Install New Perimeter Gas Probe (Per Detail 1/4) (Deletable) 1900 VF

- 70 Anchor Trench Excavation and Backfill (Per Details 1/C17, 2/C17, 5/C17, and

6/C17) 2850 LF

CONSTRUCTION BID ITEMS SUBTOTAL:

PROJECT SUPPORT BID ITEMS (1-6) SUBTOTAL:

CONSTRUCTION BID ITEMS (7-70) SUBTOTAL:

The project will be bid on a UNIT PRICE basis and quantities are to be VERIFIED by the Bidders. Actual quantities shall be measured for final payment, or as approved by the Engineer.

SWMD reserves the right to delete any specific item on the bid schedule in its entirety. Should SWMD elect not to proceed with a specified item of work, it will be deleted from the contract.

The Bid Schedule shown above does not constitute agreed-upon costs for the items described. The purpose of this cost breakdown is to provide SWMD with cost allocations for comparison and budgeting purposes only. Final cost allocations for each individual item for the project’s schedule of values and progress payments will be established by the Construction Manager in negotiation with the Contractor.

THE AWARD OF THIS CONTRACT WILL BE BASED ON THE LOWEST RESPONSIBLE BID TOTAL.

TOTAL PROJECT BID (ITEMS 1-70) =

Page 22-3B

ATTACHMENT NO. 2

(Fill Plan w/ Intended Haul Route)

29402930

3150 3120

3040 3080

30403050

30703050

3080 3070

3040 30

311031

DIRECTOR OF PUBLIC WORKS DATE

DEPUTY DIRECTOR

RECOMMENDED / APPROVED BY

J.L. REF. W.O. NO. SCALE SHT. NO.

AS SHOWN

DATE

TOT. SHT'S.

SUBMITTED BY

CHIEF OF ENGINEERING

PROJ. ENGR.DRAWN BY DESIGNED BY

DATE

SAN BERNARDINO COUNTY

DEPARTMENT OF PUBLIC WORKS

Z:\Landfills\_Victorville\CAD\Grading Plans\Fill Sequencing\2026\26VSL FS9\FS9+6FT\26 VSL FS9 and Haul Route Plan.dwg 3/27/2026 9:20 AM

PHASE 1B STAGE 1-3 FS9

FILL SEQUENCE PLAN

VICTORVILLE SANITARY LANDFILL

JLAVAV

DATE OF TOPOGRAPHY : JANUARY 9, 2026

FEET

0 150 300

CONTRACTOR HAUL ROAD

LEGEND

10.0%

DRAFT

NOT FOR CONSTRUCTION

40'

40'

5.0%

3.0%

40'

SHARED HAUL ROAD AND

ACTIVE LANDFILL AREA

PHASE 1B STAGE 4 AND 5

EXCAVATION AREA

STOCKPILE 1

FILL SEQUENCE 9

March 30, 2026

File details come from the government source that posted it. Updated .