This is Addendum No. 4 to SEPTA's (Southeastern Pennsylvania Transportation Authority) Sealed Bid No. 26-00160-AKQC for the Construction of the Chinatown Station ADA Improvement Project - REBID. The addendum extends the bid opening date from the previously scheduled Monday, August 24, 2026 at 10:00 pm ET to Friday, October 30, 2026 at 10:00 am ET. Due to new phasing plans and scope reduction, updated project drawings and specification modifications will be delayed until October 2026 and will be issued via a subsequent addendum prior to the new bid due date. The project encompasses construction of two new accessible elevators within a new headhouse, structural repairs, waterproofing systems, accessible renovations to emergency egress headhouses, accessible doors and walls, street-level improvements, and civil work for plaza improvements and landscaping at Chinatown Station located at 8th and Race Streets, Philadelphia. The work will be executed through multiple prime contracts including General Contractor, Mechanical Contractor, and Electrical Contractor scopes, with a contract duration of 1,004 calendar days (33.5 months) from Notice to Proceed.
The project is subject to Title VI of the Civil Rights Act of 1964 and requires compliance with nondiscrimination provisions ensuring disadvantaged business enterprises have full opportunity to submit bids. The contract is subject to the Buy America Act and any resulting contract will be subject to a financial assistance agreement between SEPTA and the U.S. Department of Transportation. Bidders must acknowledge Addendum No. 4 on the Addenda Bid Form or their proposal may be deemed non-responsive. Submitted bids must remain firm for at least 90 days from the bid opening date. All inquiries regarding this bid must be directed to Karen Cyphers, Sr. Contract Administrator in the Procurement and Supply Chain Management Department at kcyphers@septa.org.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
August 18, 2026
To all Bidders:
Attached is Addendum No. 4 to SEPTA's Sealed Bid No. 26-00160-AKQC - Construction of the
Chinatown Station ADA Improvement Project - REBID.
The bid opening date and time that was scheduled for Monday, August 24, 2026 at 10:00 pm ET has been extended. The new bid opening date and time is scheduled for Friday, October 30, 2026 at
10:00 am ET.
Any inquiries regarding this bid must be directed to Karen Cyphers of the Procurement and Supply
Chain Management Department at kcyphers@septa.org.
Sincerely, Karen Cyphers a
Karen Cyphers
Sr. Contract Administrator
Procurement & Supply Chain Management
Addendum No. 4
Dated: August 18, 2026
SEALED BID NO. 26-00160-AKQC – CONSTRUCTION OF THE CHINATOWN
STATION ADA IMPROVEMENT PROJECT - REBID
ADDENDUM NO. 4
To All Bidders:
The following constitutes Addendum No. 4 to SEPTA's Sealed Bid No. 26-00160-AKQC -
Construction of the Chinatown Station ADA Improvement Project - REBID. Addendum No. 4 must be acknowledged by inserting the date of the Addendum on the Addenda Bid Form. Failure to do so may render a bidder’s proposal as non-responsive.
The bid opening date and time that was scheduled for Monday, August 24, 2026 at 10:00 pm ET has been extended. The new bid opening date and time is scheduled for Friday, October 30, 2026 at
10:00 am ET.
A. General
1. Due to the new phasing plans and scope reduction, issuance of updated project drawings and specification modifications will be delayed until October 2026.
These documents will be issued prior to the new bid due date via an addendum.
2. The new bid opening date and time is scheduled for Friday, October 30, 2026 at 10:00 am ET.
3. The ITB Letter has been updated to reflect the new bid due date.
3. All else remains unchanged.
B. Specifications - No changes