addendum-3-rfb-dncr-2026-10--1-.pdf

PDF 277 KB Posted

Attached to
Bridge Approach Construction and Bridge Installation
Solicitation number
RFB DNCR 2026-10
Issued by
Carroll County, New Hampshire

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

February 24, 2026

Addendum #3 to answer questions (third posting after Addendum 1 and Addendum 1A/2)

For

Bridge Approach Construction & Bridge Installation on Corridor 19 Snowmobile Trail in Chatham, NH

Department of Natural and Cultural Resources, Division of Parks and Recreation, Bureau of Trails

Request for Bid DNCR 2026-10 (Project Number TB-2601)

Key dates for bid timeline:

• Bid period opens on January 13, 2026

• End of Q&A period: Thursday February 19, 2026.

• State reply posting from Q&A period: Thursday February 26, 2026

• End of Bid period/Bid Opening: Thursday March 5, 2026.

Bridge Approach Construction & Bridge Installation on Corridor 19 Snowmobile Trail in Chatham, NH February 24, 2026

Addendum response to Q&A

RFB DNCR 2026-10 (Project No. TB-2601)

ADDENDUM #3 (third posting after Addendum 1 and Addendum 1A)

TO: ALL CONTRACT BIDDERS

This addendum forms a part of the contract documents and modifies the bidding documents for Bridge Approach

Construction & Bridge Installation on Corridor 19 Snowmobile Trail in Chatham, (PROJECT No. TB-

2601), with amendments and deletions noted below.

Acknowledge receipt of this addendum in the space provided in the bid proposal form. Failure to do so may disqualify the Bidder.

This addendum consists of 1 page.

CLARIFICATION TO BID QUESTIONS:

1. Will CAD files be available for construction?

a. RESPONSE: There are no CAD files included in this project.

2. Will the contractor be responsible for disposing of the bridge(s) to be removed by DNCR?

a. RESPONSE: no, DNCR will remove and dispose of existing bridges. This timing will be coordinated at the pre-construction meeting once the construction contractor has been selected.

3. Is there a bid bond requirement?

a. RESPONSE: There is no bid bond requirement for this project.