Addendum 3 Q& A RFP 190000001842.docx
DOCX document 14 KB Posted
- Solicitation number
- RFP 472 190000001842 4
- Issued by
- Ingham County, Lansing City, Michigan
About this file
This is Addendum 3 to RFP 190000001842 issued by the Michigan Department of Corrections (MDOC) providing clarifications to bidder questions regarding product sourcing and delivery requirements. The RFP pertains to the procurement of materials, with bidders required to submit labeled samples with corresponding item numbers and pricing for each proposed item. The State prefers delivery within 30 calendar days from receipt of order, though bidders should propose timeframes for both initial and subsequent orders as part of their bid submission. MDOC will evaluate all proposed delivery times during the proposal evaluation process.
Regarding manufacturing origin, MDOC has no country of origin restrictions and will accept products manufactured domestically or internationally, or a combination thereof, based on best value determination for the State. Bidders proposing offshore-manufactured materials must supply documentation as specified in the RFP's Proposal Preparation instructions. The addendum indicates that while an initial pipeline stocking period of 90 days with subsequent deliveries at 7-10 days was questioned by a bidder, MDOC will evaluate all delivery time proposals as evaluation criteria rather than establishing a mandatory stocking requirement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 4 RFP 190000001842.docx | DOCX document | |
| ADDENDUM 2.docx | DOCX document | |
| Mesh RFP.docx | DOCX document | |
| Sample Evaluation Form-DTMB for MSI.doc | DOC document | |
| ADDENDUM 1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 190000001842
Addendum 3 Questions and Answers
1) Question: is there is a country of origin requirement or restriction?
Response: See RFP Section 1.1 Specifications MDOC will accept products manufactured on-shore or off-shore to determine the best value to the State. Bidders may propose material manufactured on-shore, off-shore, or both. Bidder must supply documentation as stated in Proposal Instructions 1. Proposal Preparation. Each sample must be labeled with an item number.
Bidder must reference the sample item numbers in their responses. Bidder must provide pricing for each item number proposed.
2) Question:
A) What is MI’s preferred delivery timeframe ARO?
B) Would initial pipeline stocking of 90 days be acceptable, with subsequent deliveries at 7-10 days?
Response:
A) See RFP Section 2.1 Time Frames.
The State prefers that deliveries be made within 30 calendar days from receipt of order. The Bidder should include time frames for initial and subsequent orders in their bid.
B) MDOC will evaluate delivery times as part of the Proposal evaluation.